← Back
Unlicensed parking lot
HAMILTON PLACE
BROOKLYN · BIN 3429009
💬 Discuss this project
0Year Built
—Stories
G7Building Class
M1-2Zoning
0 sfGross Floor Area
0Units
Unlicensed parking lot · Owner of record: 12TH STREET ASSOCIATES A LLC · 22,455 sf lot · 0 FAR built · Flood zone X
Locations of Work
No floor-level scope or drawing coverage on file for this building.
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
TWO TREES MANAGEMENT CO903/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
GUTH DECONZO CONSULTING ENGINEERS,409/20/2022
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
MICROGRID NETWORKS803/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
JAJ ENGINEERING PLLC930206/26/2021
Building Lifecycle
All (19)Filed (4)Permit Issued (1)Signed Off (1)Special Inspection (13)
09/20/2022
Filed — Alteration
B00536491-I1
09/15/2021
Signed off — Alteration
INSTALLATION OF NEW ELECTRICAL VAULT(MANHOLE). NO CHANGE IN USE, EGRESS OR OCCUPANCY
B00505696-I1
07/01/2021
Permit issued — Earth Work
B00505696-I1-GC-CX
06/29/2021
Special inspection requirement — Subgrade Inspections
Joseph Jabour
06/29/2021
Special inspection requirement — Concrete - Precast
Joseph Jabour
06/29/2021
Special inspection requirement — Subsurface Conditions – Fill Placement & In-Place Density
Joseph Jabour
06/29/2021
Special inspection requirement — Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable)
Joseph Jabour
06/29/2021
Special inspection requirement — Excavations - Sheeting, Shoring, and Bracing
Joseph Jabour
06/29/2021
Special inspection requirement — Final
John Guth
06/26/2021
Filed — Alteration
INSTALLATION OF NEW ELECTRICAL VAULT(MANHOLE). NO CHANGE IN USE, EGRESS OR OCCUPANCY
B00505696-P2
06/25/2021
Special inspection requirement — Concrete - Precast
Joseph Jabour
06/25/2021
Special inspection requirement — Excavations - Sheeting, Shoring, and Bracing
Joseph Jabour
06/25/2021
Special inspection requirement — Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable)
Joseph Jabour
06/25/2021
Special inspection requirement — Subgrade Inspections
Joseph Jabour
06/25/2021
Special inspection requirement — Subsurface Conditions – Fill Placement & In-Place Density
Joseph Jabour
06/25/2021
Special inspection requirement — Final
John Guth
06/23/2021
Filed — Alteration
INSTALLATION OF NEW ELECTRICAL VAULT(MANHOLE). NO CHANGE IN USE, EGRESS OR OCCUPANCY
B00505696-P1
06/10/2021
Special inspection requirement — Final
05/17/2021
Filed — Alteration
INSTALLATION OF NEW ELECTRICAL VAULT(MANHOLE). NO CHANGE IN USE, EGRESS OR OCCUPANCY
B00505696-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWEarth WorkSigned-offPAUL J. SCARIANO INC07/01/2021
Nothing on file for this building.
▾Special Inspection Requirements (DOB NOW) — 13
DateRequirementInspectorRole
06/29/2021Subgrade InspectionsJoseph Jabourspecial
06/29/2021Concrete - PrecastJoseph Jabourspecial
06/29/2021Subsurface Conditions – Fill Placement & In-Place DensityJoseph Jabourspecial
06/29/2021Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable)Joseph Jabourspecial
06/29/2021Excavations - Sheeting, Shoring, and BracingJoseph Jabourspecial
06/29/2021FinalJohn Guthprogress
06/25/2021Concrete - PrecastJoseph Jabourspecial
06/25/2021Excavations - Sheeting, Shoring, and BracingJoseph Jabourspecial
06/25/2021Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable)Joseph Jabourspecial
06/25/2021Subgrade InspectionsJoseph Jabourspecial
06/25/2021Subsurface Conditions – Fill Placement & In-Place DensityJoseph Jabourspecial
06/25/2021FinalJohn Guthprogress
06/10/2021Final—progress
▾Documents — 15 on file (BIS + DOB NOW)
▸Plans & Drawings4
▸DOB NOWPlans/Sketch4
09/01/2026B00505696-P2Request digital key ↗
09/01/2026B00505696-P1Request digital key ↗
09/01/2026B00505696-I1Request digital key ↗
Showing 3 of 4 on file for this type
▸Seals & Professional Certifications10
▸DOB NOWDPL-1: Design Professional Seal & Signature4
09/01/2026B00505696-P2Open ↗
09/01/2026B00505696-P1Open ↗
09/01/2026B00505696-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
09/01/2026B00505696-I1Open ↗
09/01/2026B00505696-I1Open ↗
08/25/2026B00505696-P2Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWProgress Inspector Seal & Signature2
09/01/2026B00505696-I1Open ↗
08/25/2026B00505696-P2Open ↗
▸Other Documents1
▸DOB NOWAdjoining Owners Notification1
08/13/2026B00505696-I1Open ↗