| Owner | Filings | Most Recent |
|---|---|---|
| VISTAH GROUP | 19 | 07/08/2026 |
| KAMALI ORGANIZATION | 10 | 04/09/2026 |
| GREEN JJ MANAGEMENT | 2 | 03/22/2026 |
| MSNP MANAGEMENT | 2 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| ARNOLD MONTAG ARCHITECT AM/PM DESI | 7 | 09/17/2025 |
| SYNERGIC DESIGN ARCHITECTS | 1 | 09/23/2024 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| GREEN JJ MANAGEMENT INC | General Contractor | 9 | 07/08/2026 |
| TRI STATE PLBG & HTG INC | Plumbing | 4 | 07/08/2026 |
| YAFE MEOD CORP | General Contractor | 3 | 03/21/2026 |
| POWER SURGE ELECTRIC, INC | Electrical | 1 | 03/22/2026 |
| ACCORD POWER INC | General Contractor | 1 | 07/08/2026 |
| PLANET CONSTRUCTION & DE* | General Contractor | 1 | 04/09/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| G ENGINEERING PC | 7778 | 2 | 09/17/2025 |
| SYNERGIC DESIGN LLC | 8561 | 1 | 09/23/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Curb Cut | Signed-off | PLANET CONSTRUCTION & DE* | 01/12/2026 |
| DOB NOW | Plumbing | Signed-off | DW PLUMBING INC | 10/02/2025 |
| DOB NOW | Plumbing | Signed-off | DW PLUMBING INC | 09/03/2025 |
| DOB NOW | Plumbing | Signed-off | DW PLUMBING INC | 08/21/2025 |
| DOB NOW | Mechanical Systems | Signed-off | GREEN JJ MANAGEMENT INC | 02/10/2025 |
| DOB NOW | Structural | Signed-off | GREEN JJ MANAGEMENT INC | 02/10/2025 |
| DOB NOW | Construction Fence | Signed-off | GREEN JJ MANAGEMENT INC | 01/23/2025 |
| DOB NOW | Foundation | Permit Issued | GREEN JJ MANAGEMENT INC | 01/23/2025 |
| DOB NOW | Structural | Signed-off | GREEN JJ MANAGEMENT INC | 10/29/2024 |
| DOB NOW | Solar | Signed-off | ACCORD POWER INC | 09/26/2024 |
| DOB NOW | Plumbing | Signed-off | DW PLUMBING INC | 09/25/2024 |
| DOB NOW | Construction Fence | Signed-off | GREEN JJ MANAGEMENT INC | 06/12/2024 |
| DOB NOW | General Construction | Permit Issued | GREEN JJ MANAGEMENT INC | 06/06/2024 |
| DOB NOW | Structural | Permit Issued | YAFE MEOD CORP | 02/02/2024 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 09/17/2025 | Signed-off | PLANET CONSTRUCTION & DE* | Air Conditioning Systems, Ventilation Systems | Cooling Midea LOCATION OSP: CONDENSER 1: DLCMHBH48EAK, CONDENSER 2: DLCMHBH48EAK, - (HEATING AND COOLING) 40,000 BTU · Furnace ×2 CONDENSER 3: DLCMRBH18BAK (HEATING AND COOLING) 2 tons · Condensing Unit ×1 Ventilation |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/17/2025 | Signed-off | TRI STATE PLBG & HTG INC | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/25/2024 | Complete | POWER SURGE ELECTRIC, INC | — |
| 09/10/2024 | Complete | KWONG MING ELECTRIC INC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/17/2025 | Signed-off | PLANET CONSTRUCTION & DE* | Concrete, Wood |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/17/2025 | Signed-off | PLANET CONSTRUCTION & DE* | Fence |
| Date | Type | Result | Report |
|---|---|---|---|
| 03/06/2026 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 01/20/2026 | Fail-Final Curb Cut Non-Directive 14 | Fail | View ↗ |
| 11/21/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 05/23/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 12/23/2024 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 12/23/2024 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 12/23/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 12/23/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/22/2025 | Structural Cold-Formed Steel | XIONGCAI GU | special |
| 07/22/2025 | Fenestration and door U-factor and product ratings | XIONGCAI GU | energy_progress |
| 07/22/2025 | Air barrier — testing | XIONGCAI GU | energy_progress |
| 07/22/2025 | Metering | XIONGCAI GU | energy_progress |
| 07/22/2025 | Fenestration areas | XIONGCAI GU | energy_progress |
| 07/22/2025 | Insulation placement and R values | XIONGCAI GU | energy_progress |
| 07/22/2025 | Air barrier - visual inspection | XIONGCAI GU | energy_progress |
| 07/22/2025 | HVAC-R and service water heating equipment | XIONGCAI GU | energy_progress |
| 07/22/2025 | Permanent certificate | XIONGCAI GU | energy_progress |
| 07/22/2025 | Interior lighting power | XIONGCAI GU | energy_progress |
| 07/22/2025 | Shutoff dampers | XIONGCAI GU | energy_progress |
| 07/22/2025 | Electric vehicle service equipment requirements | XIONGCAI GU | energy_progress |
| 07/22/2025 | Ventilation and air distribution system | XIONGCAI GU | energy_progress |
| 07/22/2025 | HVAC-R and service water heating system controls | XIONGCAI GU | energy_progress |
| 07/22/2025 | Fenestration air leakage | XIONGCAI GU | energy_progress |
| 07/22/2025 | Lighting controls | XIONGCAI GU | energy_progress |
| 07/22/2025 | Concrete - Cast-In-Place | XIONGCAI GU | special |
| 07/22/2025 | Fire-Resistant Penetrations and Joints | XIONGCAI GU | special |
| 07/22/2025 | Masonry | XIONGCAI GU | special |
| 07/22/2025 | Mechanical Systems | XIONGCAI GU | special |
| 07/22/2025 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | XIONGCAI GU | special |
| 07/22/2025 | Subgrade Inspections | XIONGCAI GU | special |
| 07/22/2025 | Subsurface Investigations (Borings/Test Pits) | ROBERT DYKSTRA | special |
| 07/22/2025 | Wood – Prefabricated I-Joists | XIONGCAI GU | special |
| 07/22/2025 | Energy Code Compliance Inspections | XIONGCAI GU | progress |