← Back
Two family brick
HAWTREE STREET
QUEENS · BIN 4623579
💬 Discuss this project
2022Year Built
2.5Stories
B1Building Class
R3XZoning
2,572 sfGross Floor Area
2Units
Two family brick · 3,610 sf lot · 0.71 FAR built · Flood zone X
Locations of Work
Structural
Floor 11p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
KAMALI ORGANIZATION307/08/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
06/26/2024$1.6M—— → —$605/sf building
04/24/2023$600K—MARVEK DEVELOPMENT LLC → Private party$233/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
ARNOLD MONTAG ARCHITECT AM/PM DESI203/22/2024
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
KAIETEUR CONSTRUCTION INC.General Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
AFM INSPECTIONS & ENGINEE4675109/02/2021
ARNOLD MONTAG ARCHITECT,4599209/02/2021
Building Lifecycle
All (19)Filed (2)Permit Issued (1)Inspection (6)Objection (2)Special Inspection (8)
03/11/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
01/27/2025
Permit issued — Structural
Q00526706-I1-GC-CX
03/22/2024
Filed — New Building
Proposed Detached one (1) car garage
Q00526706-P1
01/09/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
11/14/2023
Inspection — Pass-Final PL - Up to 9 Requested Floors
Pass
View inspection ↗
10/26/2023
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
12/19/2022
Inspection — Pass-Final PL - Underground
Pass
View inspection ↗
11/19/2022
Inspection — Pass-Final PL - Underground
Pass
View inspection ↗
09/14/2022
Special inspection requirement — Concrete - Cast-In-Place
09/14/2022
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
09/14/2022
Special inspection requirement — Subgrade Inspections
09/14/2022
Special inspection requirement — Wall Panels, Curtain Walls, and Veneers
09/14/2022
Special inspection requirement — Final
09/14/2022
Special inspection requirement — Fire-Resistance Rated Construction
09/14/2022
Special inspection requirement — Footing and Foundation
09/14/2022
Special inspection requirement — Structural Wood Frame
09/22/2021
Objection resolved — Addressed
09/15/2021
Objection raised — Other
09/02/2021
Filed — New Building
Proposed Detached one (1) car garage
Q00526706-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWStructuralPermit IssuedKAIETEUR CONSTRUCTION INC01/27/2025
1 project · most recent 02/03/2025
General Wiring
FiledStatusContractorScope
02/03/2025CompleteAYYUB ELECTRIC CORPGeneral Wiring
1 project · most recent 03/22/2024
Concrete Wood
FiledStatusContractorScope
03/22/2024Permit IssuedKAIETEUR CONSTRUCTION INCConcrete, Wood
▾Field Inspections (DOB CAP) — 6
DateTypeResultReport
03/11/2025Pass-Final CND-Occupancy InspectionPassView ↗
01/09/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
11/14/2023Pass-Final PL - Up to 9 Requested FloorsPassView ↗
10/26/2023Pass-Final PL - Up to 3 Requested FloorsPassView ↗
12/19/2022Pass-Final PL - UndergroundPassView ↗
11/19/2022Pass-Final PL - UndergroundPassView ↗
▾Special Inspection Requirements (DOB NOW) — 8
DateRequirementInspectorRole
09/14/2022Concrete - Cast-In-Place—special
09/14/2022Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation—special
09/14/2022Subgrade Inspections—special
09/14/2022Wall Panels, Curtain Walls, and Veneers—special
09/14/2022Final—progress
09/14/2022Fire-Resistance Rated Construction—progress
09/14/2022Footing and Foundation—progress
09/14/2022Structural Wood Frame—progress
▾Documents — 22 on file (BIS + DOB NOW)
▸Plans & Drawings2
▸DOB NOWPlans/Sketch2
08/27/2026Q00526706-P1Request digital key ↗
08/15/2026Q00526706-I1Request digital key ↗
▸Zoning, Tax Lot & Property Records5
▸DOB NOWZoning Exhibit form (1-5)2
08/15/2026Q00526706-I1Open ↗
08/13/2026Q00526706-P1Open ↗
▸DOB NOWZD1: DOB Zoning Diagram2
08/15/2026Q00526706-I1Open ↗
08/13/2026Q00526706-P1Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/15/2026Q00526706-I1Open ↗
▸Seals & Professional Certifications2
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/27/2026Q00526706-I1Open ↗
08/27/2026Q00526706-P1Open ↗
▸Trade Schedules & Equipment2
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)2
08/15/2026Q00526706-I1Open ↗
08/13/2026Q00526706-P1Open ↗
▸Safety & Tenant Protection3
▸DOB NOWStreet Tree Checklist2
08/27/2026Q00526706-P1Open ↗
08/15/2026Q00526706-I1Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/15/2026Q00526706-I1Open ↗
▸Cost, Insurance & Ownership2
▸DOB NOWCertification by Insurance Broker or Agency1
08/15/2026Q00526706-I1Open ↗
▸DOB NOWCertificate of Insurance1
08/15/2026Q00526706-I1Open ↗
▸Other Documents6
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone2
08/15/2026Q00526706-I1Open ↗
08/13/2026Q00526706-P1Open ↗
▸DOB NOWSite Survey: Initial2
08/15/2026Q00526706-I1Open ↗
08/13/2026Q00526706-P1Open ↗
▸DOB NOWFinal Survey1
08/15/2026Q00526706-I1Open ↗
▸DOB NOWAdditional Insured Authorizations1
08/15/2026Q00526706-I1Open ↗