Over six families without stores
LELAND AVENUE
BRONX · Soundview-Bruckner-Bronx River · BIN 2130462
💬 Discuss this project
2020Year Built
4Stories
C1Building Class
R6Zoning
7,965 sfGross Floor Area
10Units
Rent Stabilized0 Open Violations
Over six families without stores · Owner of record: 1369 LELAND LLC · 2,219 sf lot · 3.59 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingGeneral
Roof4p · 2 filings · 20 docs
Bulkhead1p · 1 filing · 20 docs
Penthouse3p · 2 filings · 20 docs
Floor 45p · 4 filings · 20 docs
Floor 34p · 2 filings · 20 docs
Floor 23p · 2 filings · 20 docs
Floor 12p · 1 filing · 18 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
HMF1507/08/2026
CITY WIDE BUILDER GRP1507/08/2026
1369 LELAND LLC1703/22/2026
CITYWIDE BUILDERS STEP IN103/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
02/12/2020$800K—Private party → 1369 LELAND LLC$100/sf building
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
EXPEDITING 4 U803/21/2026
GREEN STUDIO603/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
CITY WIDE BUILDERS GRP INGeneral Contractor607/08/2026
MPI PLUMBING CORPPlumbing507/08/2026
MANHATTAN D ENTERPRISESGeneral Contractor207/08/2026
SHMUEL WIEDERElectrical103/21/2026
PRIME PIPING & HEATING INFire Protection107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
BIG APPLE GROUP NY A RMA9168807/23/2021
Building Lifecycle
All (88)Filed (11)Permit Issued (8)Signed Off (6)Violation (7)Objection (26)Special Inspection (30)
10/06/2021
Signed off — Alteration
Sprinkler application filed in conjunction with NB job #220725730
X00392894-I1
10/06/2021
Signed off — Alteration
MECHANICAL APPLICATION FILED IN CONJUNCTION TO NEW BUILDING JOB #220725730
X00334710-I1
09/08/2021
Special inspection requirement — Heating Systems
SOORJBALLY HARILALL
09/08/2021
Special inspection requirement — Mechanical Systems
SOORJBALLY HARILALL
09/08/2021
Special inspection requirement — HVAC insulation and sealing
Soorjbally Harilall
09/08/2021
Special inspection requirement — Shutoff dampers
Soorjbally Harilall
09/08/2021
Special inspection requirement — HVAC and service water heating system controls
Soorjbally Harilall
09/08/2021
Special inspection requirement — Maintenance information
Soorjbally Harilall
09/08/2021
Special inspection requirement — HVAC and service water heating equipment
Soorjbally Harilall
09/08/2021
Special inspection requirement — Final
Soorjbally Harilall
09/08/2021
Special inspection requirement — Energy Code Compliance Inspections
Soorjbally Harilall
09/08/2021
Special inspection requirement — Fire-Resistant Penetrations and Joints
SOORJBALLY HARILALL
08/27/2021
Objection resolved — Addressed
08/25/2021
Special inspection requirement — Sprinkler Systems
SOORJBALLY HARILALL
07/28/2021
Objection raised — Other
07/27/2021
Signed off — Alteration
STRUCTURAL APPLICATION FILED IN CONJUNCTION TO NEW BUILDING JOB #220725730
X00343708-I1
07/23/2021
Filed — Alteration
MECHANICAL APPLICATION FILED IN CONJUNCTION TO NEW BUILDING JOB #220725730
X00334710-P1
07/21/2021
Special inspection requirement — Final
Soorjbally Harilall
07/21/2021
Special inspection requirement — Fire-Resistant Penetrations and Joints
SOORJBALLY HARILALL
07/21/2021
Special inspection requirement — Heating Systems
SOORJBALLY HARILALL
07/21/2021
Special inspection requirement — Mechanical Systems
SOORJBALLY HARILALL
07/21/2021
Special inspection requirement — Energy Code Compliance Inspections
Soorjbally Harilall
07/21/2021
Special inspection requirement — Maintenance information
Soorjbally Harilall
07/21/2021
Special inspection requirement — HVAC and service water heating equipment
Soorjbally Harilall
07/21/2021
Special inspection requirement — HVAC and service water heating system controls
Soorjbally Harilall
07/21/2021
Special inspection requirement — Shutoff dampers
Soorjbally Harilall
07/21/2021
Special inspection requirement — HVAC insulation and sealing
Soorjbally Harilall
07/16/2021
Signed off — Alteration
PLUMBING APPLICATION FILED IN CONJUNCTION TO NEW BUILDING JOB#220725730
X00334435-I1
07/13/2021
Filed — Alteration
Sprinkler application filed in conjunction with NB job #220725730
X00392894-P2
07/02/2021
Special inspection requirement — HVAC and service water heating system controls
Soorjbally Harilall
07/02/2021
Special inspection requirement — Fire-Resistant Penetrations and Joints
SOORJBALLY HARILALL
07/02/2021
Special inspection requirement — HVAC insulation and sealing
Soorjbally Harilall
07/02/2021
Special inspection requirement — Maintenance information
Soorjbally Harilall
07/02/2021
Special inspection requirement — HVAC and service water heating equipment
Soorjbally Harilall
07/02/2021
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
SOORJBALLY HARILALL
07/02/2021
Special inspection requirement — Energy Code Compliance Inspections
Soorjbally Harilall
07/01/2021
Objection resolved — Addressed
06/30/2021
Objection raised — Other
06/24/2021
Filed — Alteration
PLUMBING APPLICATION FILED IN CONJUNCTION TO NEW BUILDING JOB#220725730
X00334435-P1
06/24/2021
Filed — Alteration
Sprinkler application filed in conjunction with NB job #220725730
X00392894-P1
06/16/2021
Special inspection requirement — Sprinkler Systems
SOORJBALLY HARILALL
06/09/2021
Signed off — Alteration
INSTALLATION OF SIDEWALK SHED, OVERHEAD PROTECTION AS PER PLANS. SIDEWALK SHED LIVE LOAD WILL BE 300 PSF, SHALL COMPLY WITH CHAPTER #33 OF THE 2014 CODE NO CHANGE TO USE, EGRESS OR OCCUPANCY.
X00391178-I1
06/09/2021
Signed off — Alteration
INSTALLATION OF PIPE SCAFFOLD AS PER PLANS. PIPE SCAFFOLD SHALL COMPLY WITH CHAPTER #33 OF THE 2014 CODE NO CHANGE TO USE, EGRESS OR OCCUPANCY.
X00395601-I1
06/07/2021
Permit issued — Plumbing
X00334435-I1-PL
06/04/2021
Special inspection requirement — Energy Code Compliance Inspections
Soorjbally Harilall
06/02/2021
Violation issued (ECB, closed)
Construction
04/15/2021
Permit issued — Sprinklers
X00392894-I1-EW-SP
03/23/2021
Permit issued — Mechanical Systems
X00334710-I1-MS
01/25/2021
Permit issued — Plumbing
X00334435-I1-PL
12/29/2020
Violation issued (ECB, closed)
Construction
12/29/2020
Violation issued (ECB, closed)
Construction
12/23/2020
Permit issued — Structural
X00343708-I1-ST
12/02/2020
Filed — Alteration
INSTALLATION OF SIDEWALK SHED, OVERHEAD PROTECTION AS PER PLANS. SIDEWALK SHED LIVE LOAD WILL BE 300 PSF, SHALL COMPLY WITH CHAPTER #33 OF THE 2014 CODE NO CHANGE TO USE, EGRESS OR OCCUPANCY.
X00391178-P1
11/30/2020
Violation issued (ECB, closed)
Construction
11/30/2020
Violation issued (ECB, closed)
Construction
11/30/2020
Violation issued (ECB, closed)
Construction
11/30/2020
Violation issued (ECB, closed)
Construction
11/06/2020
Objection raised — Structural
11/06/2020
Objection resolved — Addressed
10/27/2020
Permit issued — Plumbing
X00334435-I1-PL
Latest 60 of 88 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offYG SERVICES INC06/07/2021
DOB NOWSprinklersSigned-offA M B MECHANICAL INC04/15/2021
DOB NOWMechanical SystemsSigned-offCITY WIDE BUILDERS GRP IN03/23/2021
DOB NOWPlumbingSigned-offYG SERVICES INC01/25/2021
DOB NOWStructuralSigned-offCITY WIDE BUILDERS GRP IN12/23/2020
DOB NOWPlumbingSigned-offYG SERVICES INC10/27/2020
DOB NOWSupported ScaffoldSigned-offMANHATTAN D ENTERPRISES09/08/2020
DOB NOWSidewalk ShedSigned-offMANHATTAN D ENTERPRISES09/03/2020
BIS—ISSUEDCITY WIDE BUILDERS GRP IN02/23/2021
BIS—ISSUEDCITY WIDE BUILDERS GRP IN01/20/2021
BIS—ISSUEDCITY WIDE BUILDERS GRP IN01/15/2021
BIS—ISSUEDCITY WIDE BUILDERS GRP IN01/15/2021
BIS—ISSUEDCITY WIDE BUILDERS GRP IN12/24/2020
BIS—ISSUEDCITY WIDE BUILDERS GRP IN12/24/2020
BISEQISSUEDMANHATTAN D ENTERPRISES11/13/2020
BIS—ISSUEDCITY WIDE BUILDERS GRP IN09/14/2020
BIS—ISSUEDCITY WIDE BUILDERS GRP IN09/14/2020
1 project · most recent 04/21/2021
General Wiring
FiledStatusContractorScope
04/21/2021CompleteACCURATE ELEC'L CORP.General Wiring
▾Special Inspection Requirements (DOB NOW) — 41
DateRequirementInspectorRole
09/08/2021Heating SystemsSOORJBALLY HARILALLspecial
09/08/2021Mechanical SystemsSOORJBALLY HARILALLspecial
09/08/2021HVAC insulation and sealing Soorjbally Harilallenergy_progress
09/08/2021Shutoff dampersSoorjbally Harilallenergy_progress
09/08/2021HVAC and service water heating system controls Soorjbally Harilallenergy_progress
09/08/2021Maintenance informationSoorjbally Harilallenergy_progress
09/08/2021HVAC and service water heating equipment Soorjbally Harilallenergy_progress
09/08/2021FinalSoorjbally Harilallprogress
09/08/2021Energy Code Compliance InspectionsSoorjbally Harilallprogress
09/08/2021Fire-Resistant Penetrations and JointsSOORJBALLY HARILALLspecial
08/25/2021Sprinkler SystemsSOORJBALLY HARILALLspecial
07/21/2021FinalSoorjbally Harilallprogress
07/21/2021Fire-Resistant Penetrations and JointsSOORJBALLY HARILALLspecial
07/21/2021Heating SystemsSOORJBALLY HARILALLspecial
07/21/2021Mechanical SystemsSOORJBALLY HARILALLspecial
07/21/2021Energy Code Compliance InspectionsSoorjbally Harilallprogress
07/21/2021Maintenance informationSoorjbally Harilallenergy_progress
07/21/2021HVAC and service water heating equipment Soorjbally Harilallenergy_progress
07/21/2021HVAC and service water heating system controls Soorjbally Harilallenergy_progress
07/21/2021Shutoff dampersSoorjbally Harilallenergy_progress
07/21/2021HVAC insulation and sealing Soorjbally Harilallenergy_progress
07/02/2021HVAC and service water heating system controls Soorjbally Harilallenergy_progress
07/02/2021Fire-Resistant Penetrations and JointsSOORJBALLY HARILALLspecial
07/02/2021HVAC insulation and sealing Soorjbally Harilallenergy_progress
07/02/2021Maintenance informationSoorjbally Harilallenergy_progress
Latest 25 of 41.
▾Documents — 175 on file (BIS + DOB NOW)
▸Plans & Drawings11
▸DOB NOWPlans/Sketch - Sprinkler3
08/25/2026X00392894-P1Request digital key ↗
08/25/2026X00392894-I1Request digital key ↗
08/15/2026X00392894-P2Request digital key ↗
▸DOB NOWPlans/Sketch - Sidewalk Shed2
08/26/2026X00391178-I1Request digital key ↗
08/15/2026X00391178-P1Request digital key ↗
▸DOB NOWPlans/Sketch - Plumbing2
08/15/2026X00334435-I1Request digital key ↗
08/15/2026X00334435-P1Request digital key ↗
▸DOB NOWPlans/Sketch - Mechanical Systems2
08/25/2026X00334710-I1Request digital key ↗
08/14/2026X00334710-P1Request digital key ↗
▸DOB NOWPlans/Sketch - Supported Scaffold1
08/26/2026X00395601-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Structural1
08/14/2026X00343708-I1Request digital key ↗
▸Applications & Permits22
▸BISPLAN / WORK APPROVAL APPLICATION12
06/22/2021220725730Open ↗
06/17/2021220725730Open ↗
06/16/2021220725730Open ↗
Showing 3 of 12 on file for this type
▸BISWORK PERMIT APPLICATION9
01/21/2021220725730Open ↗
01/19/2021220725730Open ↗
01/04/2021220725730Open ↗
Showing 3 of 9 on file for this type
▸BISCERTIFICATE OF OCCUPANCY: APPLICATION1
05/04/2021220725730Open ↗
▸Zoning, Tax Lot & Property Records8
▸BISZONING DIAGRAM2
09/08/2020220725730Open ↗
08/19/2020220725730Open ↗
▸BISZONING EXHIBIT III:DESC. & OWNRSHP.STMNT1
08/13/2020220725730Open ↗
▸BISVERIFY TAX LOT1
07/19/2021220725730Open ↗
▸BISADDRESS: NEW HOUSE NUMBER APPROVED1
05/21/2020220725730Open ↗
▸BISCO OBJ: VERIFY ADDRESS-TOPO STAMP1
07/19/2021220725730Open ↗
▸BISZONING EXHIBIT I: CERTIFICATION1
08/13/2020220725730Open ↗
▸BISTAX LOT: TENTATIVE LOT NUMBER ISSUED1
05/21/2020220725730Open ↗
▸Seals & Professional Certifications57
▸DOB NOWProgress Inspector Seal & Signature26
09/02/2026X00334435-P1Open ↗
09/02/2026X00334435-P1Open ↗
09/02/2026X00334435-P1Open ↗
Showing 3 of 26 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature15
09/02/2026X00334435-I1Open ↗
09/02/2026X00334435-P1Open ↗
09/02/2026X00334435-P1Open ↗
Showing 3 of 15 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature11
08/26/2026X00343708-I1Open ↗
08/26/2026X00391178-P1Open ↗
08/26/2026X00391178-I1Open ↗
Showing 3 of 11 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION2
09/14/2020220725730Open ↗
02/28/2020220725730Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
11/11/2020240293598Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
11/11/2020240293598Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
11/11/2020240293598Open ↗
▸Trade Schedules & Equipment3
▸BISDETECTOR:CARBON MONOXIDE-CERT.OF INSTALL1
07/19/2021220725730Open ↗
▸BIS* SEWER CONNECTION: DEP SD1 & SD21
08/24/2020220725730Open ↗
▸BISDETECTOR:SMOKE-CERT. OF INSTALLATION1
07/19/2021220725730Open ↗
▸Safety & Tenant Protection8
▸DOB NOWTenant Protection Plan3
08/13/2026X00391178-P1Open ↗
08/13/2026X00391178-I1Open ↗
08/13/2026X00395601-I1Open ↗
▸BISSTREET TREE CHECKLIST1
02/28/2020220725730Open ↗
▸BISSTREET TREE SIGNOFF1
07/19/2021220725730Open ↗
▸BISTENANT PROTECTION PLAN AND NOTES1
11/11/2020240293598Open ↗
▸BISEXCAVATION OR DEMOLITION: 5-DAY NOTICE1
09/14/2020220725730Open ↗
▸BISSTREET TREES: RECEIPT OF STREET TREES SITE PLAN1
09/14/2020220725730Open ↗
▸Energy Compliance9
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY6
07/19/2021220725730Open ↗
07/19/2021220725730Open ↗
07/19/2021220725730Open ↗
Showing 3 of 6 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS2
09/14/2020220725730Open ↗
02/28/2020220725730Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)1
07/19/2021220725730Open ↗
▸Inspections & Test Reports20
▸BISTECHNICAL REPORT: RESPONSIBILITY11
07/19/2021220725730Open ↗
07/19/2021220725730Open ↗
07/19/2021220725730Open ↗
Showing 3 of 11 on file for this type
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER3
08/18/2021220725730Open ↗
09/15/2020220725730Open ↗
09/14/2020220725730Open ↗
▸BISTECHNICAL REPORT: CONCRETE DESIGN MIX2
09/15/2020220725730Open ↗
09/14/2020220725730Open ↗
▸BISSOIL REPORT1
08/13/2020220725730Open ↗
▸BISTECHNICAL REPORT: SOIL INSPECTION1
08/13/2020220725730Open ↗
▸BISDEMOLITION (DM) JOB SIGNOFF1
07/19/2021220725730Open ↗
▸BISTR2: CONCRETE FIELD TESTING TECHNICAL REPORT1
07/19/2021220725730Open ↗
▸Approvals, Objections & Sign-offs20
▸BISLETTERS - SUPPORTING DOCUMENTATION9
01/21/2021220725730Open ↗
01/19/2021220725730Open ↗
01/04/2021220725730Open ↗
Showing 3 of 9 on file for this type
▸BISSCHEDULE A - OCCUPANCY / USE8
06/22/2021220725730Open ↗
06/17/2021220725730Open ↗
06/16/2021220725730Open ↗
Showing 3 of 8 on file for this type
▸BISSUPERSEDING LETTER2
01/04/2021220725730Open ↗
01/04/2021220725730Open ↗
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
06/09/2021240293598Open ↗
▸Cost, Insurance & Ownership3
▸BISPROJECT-SPECIFIC GL INSURANCE2
09/15/2020220725730Open ↗
09/14/2020220725730Open ↗
▸BISAcord 25 (Acord Certificate of Liability Insurance)1
09/15/2020220725730Open ↗
▸Filing & Intake Forms11
▸BISADDITIONAL INFORMATION8
08/18/2021220725730Open ↗
07/19/2021220725730Open ↗
07/19/2021220725730Open ↗
Showing 3 of 8 on file for this type
▸BISEFILING COVER SHEET2
05/01/2020220725730Open ↗
02/28/2020220725730Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
11/11/2020240293598Open ↗
▸Other Documents3
▸BISPLOT DIAGRAM2
07/19/2021220725730Open ↗
05/21/2020220725730Open ↗
▸BISSUSTAINABLE ROOF ZONE FORM1
05/21/2020220725730Open ↗