Miscellaneous hospital / health care facility
AECOM College, Laboratory Spaces and Weiler Campus
MORRIS PARK AVENUE · Morris Park · BIN 2097365
💬 Discuss this project
1954Year Built
9Stories
I9Building Class
R4Zoning
851,821 sfGross Floor Area
7Units
LL97 CoveredRent Stabilized0 Open ViolationsFISP: SAFEFDNY Report ↗
Miscellaneous hospital / health care facility · Owner of record: ALBERT EINSTEIN COLLEGE OF MEDICINE · 346,145 sf lot · 2.46 FAR built · Flood zone X
Locations of Work
Fire Protection
Cellar4p · 1 filing · 5 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
EINSTEIN307/08/2026
YESHIVA UNIVERSITY503/22/2026
MONTEFIORE MEDICAL CENTER203/22/2026
ALBERT EINSTEIN SCHOOL OF MEDICI503/21/2026
ALBERT EINSTEIN SCHOOL OF MED203/21/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
09/09/2015$99.5M—YESHIVA UNIVERSITY → COM AFFILIATION, INC.$117/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
SYNC ARCHITECTURE P.C607/27/2026
NEW YORK ENGINEERING ASSOC., P.C.108/26/2024
THE DESIGN ALLIANCE204/03/2018
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
NEW YORK ENGINEERING ASSOCIATES P C203/21/2026
MUNICIPAL BUILDING CONSULTANTS203/21/2026
FRANKLYN ESTRELLA ARCHITECT PLLC203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
HERBERT ROSE INCGeneral Contractor403/21/2026
ACE RENTAL CORPGeneral Contractor307/29/2026
BALANCE ELEC CONT'G CORP.Electrical103/22/2026
LUND FIRE PRODUCTS CO INCFire Protection107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
NEW YORK ENGINEERING ASSO851108/26/2024
Building Lifecycle
All (48)Filed (9)Permit Issued (6)Signed Off (4)Facade (FISP) (12)Violation (14)Special Inspection (3)
08/24/2026
Signed off — Alteration
Temporary tents for college events in the central courtyard. Removed at the end of the programing. No changes to existing structures, use or egress.
X01434680-I1
07/28/2026
Permit issued — General Construction
X01434680-I1-GC
07/27/2026
Filed — No Work
X01434940-I1
07/23/2026
Filed — Alteration
Temporary tents for college events in the central courtyard. Removed at the end of the programing. No changes to existing structures, use or egress.
X01434680-I1
07/22/2026
Special inspection requirement — Final
ANDY ENGLER ROTH
12/29/2025
Violation issued (FDNY_NOV, closed)
12/02/2025
Signed off — Alteration
Temporary tents for college events in the central courtyard. Removed at the end of the programing. No changes to existing structures, use or egress.
X01287982-I1
12/02/2025
Permit issued — General Construction
X01287982-I1-GC
09/17/2025
Filed — Alteration
Temporary tents for college events in the central courtyard. Removed at the end of the programing. No changes to existing structures, use or egress.
X01287982-I1
09/17/2025
Filed — No Work
X01287797-I1
09/17/2025
Special inspection requirement — Final
ANDY ENGLER ROTH
08/19/2025
Signed off — Alteration
Temporary tents for college events in the central courtyard. Removed at the end of the programing. No changes to existing structures, use or egress.
X01260270-I1
07/29/2025
Permit issued — General Construction
X01260270-I1-GC
07/28/2025
Filed — No Work
X01260519-I1
07/24/2025
Filed — Alteration
Temporary tents for college events in the central courtyard. Removed at the end of the programing. No changes to existing structures, use or egress.
X01260270-I1
04/28/2025
Violation issued (FDNY_NOV, closed)
02/12/2025
Permit issued — Sprinklers
X01042380-I1-EW-SP
08/26/2024
Filed — Alteration
X01042380-I1
04/26/2024
Special inspection requirement — Sprinkler Systems
LOUIS ARENA
02/09/2023
Cycle 9 facade report submitted
12/30/2022
Cycle 9 facade report signed — SAFE
12/27/2022
Cycle 9 facade inspection completed
09/09/2019
Signed off — Alteration
X00010316-I1
01/25/2019
Violation issued (ECB, closed)
Local Law
12/16/2018
Cycle 8 facade report signed — SAFE
09/28/2018
Cycle 8 facade report submitted
09/07/2018
Cycle 8 facade inspection completed
07/31/2018
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
06/06/2018
Permit issued — Sidewalk Shed
X00010316-I1-SH
04/03/2018
Filed — Alteration
X00010316-P1
02/08/2018
Permit issued — Sidewalk Shed
X00010316-I1-SH
01/12/2018
Filed — Alteration
X00010316-I1
10/16/2015
Violation issued (HPD, closed)
I
03/02/2015
Violation issued (HPD, closed)
I
09/30/2013
Violation issued (FDNY_NOV, closed)
02/21/2012
Cycle 7 facade report submitted
12/20/2011
Cycle 7 facade inspection completed
12/20/2011
Cycle 7 facade report signed — SAFE
09/01/2010
Violation issued (ECB, closed)
Construction
06/16/2010
Violation issued (ECB, closed)
Construction
03/31/2008
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
02/21/2007
Cycle 6 facade report submitted
02/15/2007
Cycle 6 facade report signed — SAFE
01/18/2007
Cycle 6 facade inspection completed
08/29/1995
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
06/09/1994
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
05/17/1993
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
08/06/1990
Violation issued (ECB, closed)
Public Assembly
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionSigned-offACE RENTAL CORP07/28/2026
DOB NOWGeneral ConstructionSigned-offACE RENTAL12/02/2025
DOB NOWGeneral ConstructionSigned-offACE RENTAL07/29/2025
DOB NOWSprinklersPermit IssuedLUND FIRE PRODUCTS CO INC02/12/2025
DOB NOWSidewalk ShedSigned-offHERBERT ROSE INC06/06/2018
DOB NOWSidewalk ShedSigned-offHERBERT ROSE INC02/08/2018
BISOTISSUEDHERBERT ROSE INC02/09/2018
BISMHISSUEDGRR COOLING EXPERTS INC08/07/2013
BISPLISSUEDPASQUALE QUARATINO INC06/26/2013
BISMHISSUEDGRR COOLING EXPERTS INC04/22/2013
BISPLISSUEDTRADELINE PLUMBING INC04/09/2013
BISOTISSUEDYESHIVA UNIVERSITY02/04/2013
BISOTISSUEDALBERT EINSTEIN COLLEGE OF MED.12/02/2011
BISOTISSUEDHERBERT ROSE INC08/16/2010
BISOTISSUEDHERBERT ROSE INC03/04/2010
BISMHISSUEDYESHIVA UNIVERSITY06/05/2009
BISOTISSUEDRYJAK LLC01/30/2008
BISEQISSUEDHERBERT ROSE INC01/17/2007
BISOTISSUEDHERBERT ROSE INC04/28/2006
BISEQISSUEDHERBERT ROSE INC04/26/2006
BISOTISSUEDHERBERT ROSE INC04/03/2006
BISEQISSUEDHERBERT ROSE INC03/22/2006
BISOTISSUEDYELLOWSTONE INDUSTRIES INC02/27/2001
BIS—ISSUEDHELLMAN CONSTRUCTION CO11/16/1998
BIS—ISSUEDHELLMAN CONSTRUCTION CO07/30/1998
BISPLISSUEDWILLIAM C. GERAKARIS P&H10/10/1996
BISMHISSUEDHELLMAN CONSTRUCTION CO.04/01/1994
BISOTISSUEDHELLMAN CONSTRUCTION CO.04/01/1994
1 project · most recent 01/29/2018
FiledStatusContractorScope
01/29/2018CompleteBALANCE ELEC CONT'G CORP.—
▾Special Inspection Requirements (DOB NOW) — 3
DateRequirementInspectorRole
07/22/2026FinalANDY ENGLER ROTHprogress
09/17/2025FinalANDY ENGLER ROTHprogress
04/26/2024Sprinkler SystemsLOUIS ARENAspecial
▾Documents — 215 on file (BIS + DOB NOW)
▸Plans & Drawings9
▸DOB NOWPlans/Sketch6
08/26/2026X00010316-P1Request digital key ↗
08/26/2026X00010316-I1Request digital key ↗
08/21/2026X01042380-I1Request digital key ↗
Showing 3 of 6 on file for this type
▸DOB NOWPlans/Sketch - Temporary Place of Assembly3
08/18/2026X01260519-I1Request digital key ↗
08/18/2026X01287797-I1Request digital key ↗
08/16/2026X01434940-I1Request digital key ↗
▸Applications & Permits39
▸BISPLAN / WORK APPROVAL APPLICATION23
04/22/2019210119548Open ↗
04/02/2019210119548Open ↗
09/05/2017220614057Open ↗
Showing 3 of 23 on file for this type
▸BISWORK PERMIT APPLICATION10
02/13/2018220614057Open ↗
08/07/2013220326902Open ↗
04/09/2013220254926Open ↗
Showing 3 of 10 on file for this type
▸BISPLACE OF ASSEMBLY5
04/02/2019210119548Open ↗
05/16/2018210119548Open ↗
04/26/2018210119548Open ↗
Showing 3 of 5 on file for this type
▸BISPLACE OF ASSEMBLY SIGN OFF1
04/22/2019210119548Open ↗
▸Seals & Professional Certifications60
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION29
09/17/2018220614057Open ↗
09/05/2017220614057Open ↗
09/20/2013220326902Open ↗
Showing 3 of 29 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature9
08/26/2026X00010316-I1Open ↗
08/26/2026X00010316-P1Open ↗
08/21/2026X01042380-I1Open ↗
Showing 3 of 9 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST8
09/24/2013220326902Open ↗
07/29/2013220326902Open ↗
02/27/2013220254800Open ↗
Showing 3 of 8 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM7
07/29/2013220326902Open ↗
02/27/2013220254800Open ↗
02/27/2013220254926Open ↗
Showing 3 of 7 on file for this type
▸BISPC FULL REPORT4
01/31/2008210037253Open ↗
12/28/2007210029057Open ↗
12/28/2007210029057Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWProgress Inspector Seal & Signature2
08/28/2026X01287982-I1Open ↗
08/25/2026X01434680-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
09/21/2026X01042380-I1Open ↗
▸Trade Schedules & Equipment10
▸BISSCHEDULE B - PLUMBING4
02/27/2013220254926Open ↗
03/16/2009210121269Open ↗
12/03/2007210021297Open ↗
Showing 3 of 4 on file for this type
▸BISSELF-CERT PLUMBING NOTICE3
07/13/2013220254926Open ↗
06/10/2013220254926Open ↗
11/06/2009210121269Open ↗
▸BISEQUIPMENT USE APPLICATION/PERMIT1
10/04/2013220326902Open ↗
▸BISEQUIPMENT USE PERMITS1
10/04/2013220326902Open ↗
▸BISFA - FDNY APPROVAL : FD-FAA1
09/23/2011220003920Open ↗
▸Safety & Tenant Protection1
▸BISTenant Protection Plan and Notes1
09/05/2017220614057Open ↗
▸Environmental & Asbestos15
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'6
11/22/2010220093770Open ↗
03/04/2010220050780Open ↗
03/16/2009210121269Open ↗
Showing 3 of 6 on file for this type
▸BISDEP ASBESTOS PROJECT COMPLETION FORM3
02/27/2013220254800Open ↗
02/27/2013220254926Open ↗
02/04/2013220249871Open ↗
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER3
11/10/2010220091772Open ↗
02/20/2009210119548Open ↗
11/08/2007210021297Open ↗
▸BISASBESTOS: CERTIFICATION (DEP ACP5)2
09/05/2017220614057Open ↗
07/29/2013220326902Open ↗
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/21/2026X01042380-I1Open ↗
▸Energy Compliance11
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS7
09/17/2018220614057Open ↗
09/05/2017220614057Open ↗
09/20/2013220326902Open ↗
Showing 3 of 7 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS4
09/17/2018220614057Open ↗
09/20/2013220326902Open ↗
08/10/2013220254800Open ↗
Showing 3 of 4 on file for this type
▸Approvals, Objections & Sign-offs37
▸BISADMINISTRATIVE OBJECTIONS12
02/27/2013220254800Open ↗
02/27/2013220254926Open ↗
01/29/2013220249871Open ↗
Showing 3 of 12 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST11
09/17/2018220614057Open ↗
10/04/2013220326902Open ↗
09/20/2013220326902Open ↗
Showing 3 of 11 on file for this type
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter9
08/26/2026X00010316-I1Open ↗
08/26/2026X00010316-P1Open ↗
08/16/2026X01434680-I1Open ↗
Showing 3 of 9 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION5
02/13/2018220614057Open ↗
08/24/2013220249871Open ↗
12/23/2010220093770Open ↗
Showing 3 of 5 on file for this type
▸Cost, Insurance & Ownership21
▸BISCOST AFFIDAVIT21
09/17/2018220614057Open ↗
10/30/2017220614057Open ↗
09/05/2017220614057Open ↗
Showing 3 of 21 on file for this type
▸Filing & Intake Forms11
▸BISEFILING COVER SHEET8
09/05/2017220614057Open ↗
07/29/2013220326902Open ↗
02/27/2013220254800Open ↗
Showing 3 of 8 on file for this type
▸BISBOROUGH INTAKE FORM2
04/02/2019210119548Open ↗
09/17/2018220614057Open ↗
▸BISADDITIONAL INFORMATION1
03/13/2018210119548Open ↗
▸Other Documents1
▸BISFA SELF CERT DEFECT : FD-FASC1
10/21/2011220003920Open ↗