Elevator apt, semi-fireproof with stores
PARK AVENUE
MANHATTAN · East Harlem (North) · BIN 1091743
💬 Discuss this project
2025Year Built
—Stories
D7Building Class
M1-6/R10Zoning
45,508 sfGross Floor Area
48Units
2 Open Violations 0 unresolved · 2 paperwork only ▸
Elevator apt, semi-fireproof with stores · Owner of record: LAS RAICES HOUSING DEVELOPMENT FUND COMP ANY, INC. · 4,583 sf lot · 9.93 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingFire Protection
Permit Issued — active, not yet Signed-off
RoofUnder Construction25p · 1 filing · 20 docs
Floor 13Under Construction24p · 1 filing · 20 docs
Floor 12Under Construction26p · 1 filing · 20 docs
Floor 11Under Construction25p · 1 filing · 20 docs
Floor 10Under Construction28p · 1 filing · 20 docs
Floor 9Under Construction27p · 1 filing · 20 docs
Floor 8Under Construction80p · 1 filing · 20 docs
Floor 7Under Construction80p · 1 filing · 20 docs
Floor 6Under Construction80p · 1 filing · 20 docs
Floor 5Under Construction80p · 1 filing · 20 docs
Floor 4Under Construction84p · 1 filing · 20 docs
Floor 3Under Construction82p · 1 filing · 20 docs
Floor 2Under Construction81p · 1 filing · 20 docs
Floor 1Under Construction81p · 1 filing · 20 docs
CellarUnder Construction82p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
COSAN CONSTRUCTION604/09/2026
LETTIRE CONSTRUCTION203/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
GF55 ARCHITECTS LLP508/27/2026
DAGHER ENGINEERING PLLC1108/20/2026
DE NARDIS ENGINEERING, LLC708/13/2026
TOHFAZ UDDIN PE PC212/29/2025
AMM ENGINEERING PC211/06/2025
ASHRAF CORP108/11/2025
PAUL PERDEK, PROF. ENG. PLLC405/07/2025
PILLORI ASSOCIATES301/28/2025
HANSEN ENGINEERING, PC107/09/2024
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
PRECISION 3SIXTY NYC, INC3803/21/2026
JM ZONING, LLC.103/21/2026
A1 EXPEDITING SERVICE1203/21/2026
EUROCELT EXPEDITING, INC203/21/2026
LETTIRE CONSTRUCTION103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
LETTIRE CONSTRUCTION CORPGeneral Contractor2407/08/2026
ROCKLEDGE SCAFFOLD CORPGeneral Contractor807/08/2026
DEMAR PLUMBING CORPFire Protection607/08/2026
COSAN CONSTRUCTION CORPGeneral Contractor204/09/2026
DEMAR PLUMBING CORPPlumbing207/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
PSI AGENCY INC.2542308/27/2026
AMM ENGINEERING PC725211/06/2025
Building Lifecycle
All (169)Filed (36)Permit Issued (37)Signed Off (6)Violation (4)Inspection (24)Objection (32)Special Inspection (30)
09/02/2026
Objection raised — Other
09/02/2026
Objection resolved — Addressed
08/27/2026
Filed — New Building
Plumbing work. Installation of fixtures and all related piping.
M00826434-B2
08/26/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
MAURICIO ANDRADE
08/26/2026
Special inspection requirement — Fire-Resistance Rated Construction
MAURICIO ANDRADE
08/26/2026
Special inspection requirement — Air barrier continuity plan testing
MAURICIO ANDRADE
08/26/2026
Special inspection requirement — Wall Panels, Curtain Walls, and Veneers
MAURICIO ANDRADE
08/26/2026
Special inspection requirement — Fenestration areas
MAURICIO ANDRADE
08/26/2026
Special inspection requirement — Air barrier — testing
MAURICIO ANDRADE
08/26/2026
Special inspection requirement — Insulation placement and R values
MAURICIO ANDRADE
08/26/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
MAURICIO ANDRADE
08/26/2026
Special inspection requirement — Vestibules
MAURICIO ANDRADE
08/26/2026
Special inspection requirement — Air barrier - visual inspection
MAURICIO ANDRADE
08/26/2026
Special inspection requirement — Protection of exposed foundation insulation
MAURICIO ANDRADE
08/26/2026
Special inspection requirement — Fenestration air leakage
MAURICIO ANDRADE
08/21/2026
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
08/20/2026
Filed — New Building
Plumbing work. Installation of fixtures and all related piping.
M00826434-B1
08/19/2026
Filed — New Building
Plumbing work. Installation of fixtures and all related piping.
M00826434-A8
08/13/2026
Filed — New Building
Plumbing work. Installation of fixtures and all related piping.
M00826434-A9
08/13/2026
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
MAURICIO ANDRADE
08/13/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
MAURICIO ANDRADE
08/06/2026
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
08/04/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
08/04/2026
Special inspection requirement — Subsurface Investigations (Borings/Test Pits)
THOMAS THOMANN
08/04/2026
Special inspection requirement — Subsurface Conditions – Fill Placement & In-Place Density
MAURICIO ANDRADE
08/04/2026
Special inspection requirement — Final
MAURICIO ANDRADE
08/04/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
MAURICIO ANDRADE
08/04/2026
Special inspection requirement — Subgrade Inspections
MAURICIO ANDRADE
08/04/2026
Special inspection requirement — Footing and Foundation
MAURICIO ANDRADE
08/04/2026
Special inspection requirement — Excavations - Sheeting, Shoring, and Bracing
MAURICIO ANDRADE
08/04/2026
Special inspection requirement — Concrete - Cast-In-Place
MAURICIO ANDRADE
08/04/2026
Special inspection requirement — Post-installed Anchors
MAURICIO ANDRADE
08/03/2026
Inspection — Certified Sprinkler (SP) - Booster Pump Test
Certified
View inspection ↗
08/03/2026
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
07/30/2026
Special inspection requirement — Sprinkler Systems
MAURICIO ANDRADE
07/30/2026
Special inspection requirement — Standpipe Systems
MAURICIO ANDRADE
07/15/2026
Inspection — Pass-Final SD - More than 10 Requested Floors
Pass
View inspection ↗
07/08/2026
Inspection — Pass-Final SD - Fire Pump
Pass
View inspection ↗
06/15/2026
Filed — New Building
Plumbing work. Installation of fixtures and all related piping.
M00826434-A3
06/15/2026
Inspection — Certified StandPipe-SD-Piping-Hydrostatic Test
Certified
View inspection ↗
06/02/2026
Signed off — Alteration
EQUIPMENT USE: SINGLE 6000 # CAPACITY PERSONNEL/MATERIAL HOIST DURING NB CONST, FILED SEP. HOIST SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. ELEVATOR APPLICATION SUBMITTED SEPARATELY
M01173578-I1
06/02/2026
Signed off — Alteration
EQUIPMENT USE: SINGLE 6000 # CAPACITY PERSONNEL/MATERIAL HOIST DURING NB CONST, FILED SEP. HOIST SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. ELEVATOR APPLICATION SUBMITTED SEPARATELY
M01173578-S2
06/02/2026
Signed off — Alteration
EQUIPMENT USE: SINGLE 6000 # CAPACITY PERSONNEL/MATERIAL HOIST DURING NB CONST, FILED SEP. HOIST SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. ELEVATOR APPLICATION SUBMITTED SEPARATELY
M01173578-S1
06/02/2026
Signed off — Alteration
EQUIPMENT USE: SINGLE 6000 # CAPACITY PERSONNEL/MATERIAL HOIST DURING NB CONST, FILED SEP. HOIST SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION. ELEVATOR APPLICATION SUBMITTED SEPARATELY
M01173578-S3
05/26/2026
Signed off — Alteration
Installation of multi-point and swing stage scaffolding as per plan and in accordance with Chapter 33 of NYC Building Code. No change in use, egress or occupancy.
M01267192-I1
05/23/2026
Violation issued (ECB, open)
Cranes and Derricks
05/23/2026
Violation issued (ECB, open)
Construction
05/14/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
05/13/2026
Permit issued — Construction Fence
M01173578-S3-FN
05/07/2026
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
04/22/2026
Filed — New Building
Plumbing work. Installation of fixtures and all related piping.
M00826434-A7
04/17/2026
Inspection — Pass-Final SP - Up to 9 Requested Floors
Pass
View inspection ↗
04/14/2026
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
03/23/2026
Permit issued — Protection and Mechanical Methods
M01173578-S1-PMM
03/20/2026
Objection resolved — Addressed
03/20/2026
Special inspection requirement — Fenestration areas
MAURICIO ANDRADE
03/20/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
MAURICIO ANDRADE
03/20/2026
Special inspection requirement — Wall Panels, Curtain Walls, and Veneers
MAURICIO ANDRADE
03/20/2026
Special inspection requirement — Fire-Resistance Rated Construction
MAURICIO ANDRADE
03/20/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
MAURICIO ANDRADE
Latest 60 of 169 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWConstruction FenceSigned-offROCKLEDGE SCAFFOLD CORP05/13/2026
DOB NOWProtection and Mechanical MethodsSigned-offROCKLEDGE SCAFFOLD CORP03/23/2026
DOB NOWSidewalk ShedSigned-offROCKLEDGE SCAFFOLD CORP03/19/2026
DOB NOWGeneral ConstructionPermit IssuedLETTIRE CONSTRUCTION CORP10/24/2025
DOB NOWMechanical SystemsSigned-offLETTIRE CONSTRUCTION CORP10/23/2025
DOB NOWConstruction FencePermit IssuedLETTIRE CONSTRUCTION CORP10/22/2025
DOB NOWStandpipeSigned-offDEMAR PLUMBING CORP09/19/2025
DOB NOWConstruction FencePermit IssuedLETTIRE CONSTRUCTION CORP09/18/2025
DOB NOWPlumbingPermit IssuedDEMAR PLUMBING CORP09/17/2025
DOB NOWGeneral ConstructionPermit IssuedLETTIRE CONSTRUCTION CORP09/12/2025
DOB NOWStandpipePermit IssuedDEMAR PLUMBING CORP09/11/2025
DOB NOWSprinklersSigned-offDEMAR PLUMBING CORP09/11/2025
DOB NOWMechanical SystemsSigned-offLETTIRE CONSTRUCTION CORP08/20/2025
DOB NOWSupported ScaffoldPermit IssuedCOSAN CONSTRUCTION08/12/2025
DOB NOWSuspended ScaffoldSigned-offCOSAN CONSTRUCTION08/08/2025
DOB NOWSupport of ExcavationSigned-offLETTIRE CONSTRUCTION CORP08/05/2025
DOB NOWConstruction FencePermit IssuedLETTIRE CONSTRUCTION CORP07/15/2025
DOB NOWFoundationSigned-offBORIS PRIME RENOVATION05/28/2025
DOB NOWProtection and Mechanical MethodsSigned-offROCKLEDGE SCAFFOLD CORP05/23/2025
DOB NOWFoundationPermit IssuedLETTIRE CONSTRUCTION CORP05/23/2025
DOB NOWStructuralSigned-offLETTIRE CONSTRUCTION CORP05/23/2025
DOB NOWConstruction FenceSigned-offROCKLEDGE SCAFFOLD CORP05/08/2025
DOB NOWProtection and Mechanical MethodsSigned-offROCKLEDGE SCAFFOLD CORP03/21/2025
DOB NOWSidewalk ShedSigned-offROCKLEDGE SCAFFOLD CORP03/21/2025
DOB NOWGeneral ConstructionPermit IssuedLETTIRE CONSTRUCTION CORP11/26/2024
DOB NOWGeneral ConstructionPermit IssuedLETTIRE CONSTRUCTION CORP11/19/2024
DOB NOWGeneral ConstructionPermit IssuedLETTIRE CONSTRUCTION CORP11/14/2024
DOB NOWSupport of ExcavationSigned-offLETTIRE CONSTRUCTION CORP09/09/2024
DOB NOWFoundationPermit IssuedLETTIRE CONSTRUCTION CORP08/30/2024
DOB NOWFoundationSigned-offLETTIRE CONSTRUCTION CORP08/30/2024
DOB NOWStructuralSigned-offLETTIRE CONSTRUCTION CORP08/30/2024
DOB NOWMechanical SystemsSigned-offLETTIRE CONSTRUCTION CORP08/26/2024
DOB NOWStandpipeSigned-offDEMAR PLUMBING CORP08/23/2024
DOB NOWSprinklersPermit IssuedDEMAR PLUMBING CORP08/22/2024
DOB NOWSprinklersSigned-offDEMAR PLUMBING CORP08/21/2024
DOB NOWPlumbingPermit IssuedDEMAR PLUMBING CORP08/21/2024
DOB NOWConstruction FencePermit IssuedLETTIRE CONSTRUCTION CORP07/18/2024
1 project · most recent 08/27/2026
Air Conditioning Systems Heating and Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
08/27/2026Permit IssuedLETTIRE CONSTRUCTION CORPAir Conditioning Systems, Heating and Air Conditioning Systems
Cooling
Mitsubishi Electric PUY-A24NHA7 24,000 BTU · Condensing Unit ×2
Heat / Cool
Aaon RQ-003-8 33,000 BTU · Rooftop Unit ×2
1 project · most recent 08/27/2026
Sprinkler System
FiledStatusContractorScope
08/27/2026Signed-offDEMAR PLUMBING CORPSprinkler System
1 project · most recent 08/27/2026
Gas Storm Water/Sanitary
FiledStatusContractorScope
08/27/2026Permit IssuedDEMAR PLUMBING CORPGas, Storm, Water/Sanitary
5 projects · most recent 02/11/2026
General Wiring
FiledStatusContractorScope
02/11/2026Permit IssuedXTREME ELECTRIC INCGeneral Wiring
06/23/2025Permit IssuedTUXEDO ELEC'L CONTR'G INC—
05/13/2025CompleteXTREME ELECTRIC INC—
03/21/2025CompleteANTHONY G FERRY INC—
11/18/2024Permit IssuedXTREME ELECTRIC INC1 meters, 1 new_meters
1 project · most recent 08/27/2026
Steel Concrete Masonry
FiledStatusContractorScope
08/27/2026Permit IssuedLETTIRE CONSTRUCTION CORPSteel, Concrete, Masonry
3 projects · most recent 12/29/2025
Fence Sidewalk Shed Scaffold
FiledStatusContractorScope
12/29/2025Signed-offROCKLEDGE SCAFFOLD CORPFence, Sidewalk Shed
08/11/2025Permit IssuedCOSAN CONSTRUCTION CORPScaffold
07/09/2024Permit IssuedLETTIRE CONSTRUCTION CORPFence
1 project · most recent 11/06/2025
Suspended Scaffold
FiledStatusContractorScope
11/06/2025Signed-offCOSAN CONSTRUCTION CORPSuspended Scaffold
1 project · most recent 11/06/2025
Suspended Scaffold (SC)
FiledStatusContractorScope
11/06/2025Signed-offCOSAN CONSTRUCTION CORPSuspended Scaffold (SC)
▾Field Inspections (DOB CAP) — 24
DateTypeResultReport
08/21/2026Pass-Final CND-Occupancy InspectionPassView ↗
08/06/2026Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
08/04/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
08/03/2026Certified Sprinkler (SP) - Booster Pump TestCertifiedView ↗
08/03/2026Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
07/15/2026Pass-Final SD - More than 10 Requested FloorsPassView ↗
07/08/2026Pass-Final SD - Fire PumpPassView ↗
06/15/2026Certified StandPipe-SD-Piping-Hydrostatic TestCertifiedView ↗
05/14/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
05/07/2026Pass-Final CND-Occupancy InspectionPassView ↗
04/17/2026Pass-Final SP - Up to 9 Requested FloorsPassView ↗
04/14/2026Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
03/05/2026Pass-Final CND-Occupancy InspectionPassView ↗
02/11/2026Pass-Final CND-Occupancy InspectionPassView ↗
12/02/2025Pass-Final CND-Occupancy InspectionPassView ↗
12/02/2025Pass-Final PL - More than 10 Requested FloorsPassView ↗
11/13/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
11/12/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
11/12/2025Certified Sprinkler - SP - RoughingCertifiedView ↗
10/23/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
10/23/2025Pass-Final PL - Up to 9 Requested FloorsPassView ↗
07/01/2025Certified StandPipe - SD - Alarm Sys 64/09 - FinishCertifiedView ↗
04/08/2025Pass-Final PL - UndergroundPassView ↗
07/30/2024Pass-Final CND-Occupancy InspectionPassView ↗
▾Special Inspection Requirements (DOB NOW) — 113
DateRequirementInspectorRole
08/26/2026Fire-Resistance Rated ConstructionMAURICIO ANDRADEprogress
08/26/2026Wall Panels, Curtain Walls, and VeneersMAURICIO ANDRADEspecial
08/26/2026Fire-Resistant Penetrations and JointsMAURICIO ANDRADEspecial
08/26/2026Air barrier continuity plan testingMAURICIO ANDRADEenergy_progress
08/26/2026Insulation placement and R valuesMAURICIO ANDRADEenergy_progress
08/26/2026Air barrier — testing MAURICIO ANDRADEenergy_progress
08/26/2026VestibulesMAURICIO ANDRADEenergy_progress
08/26/2026Fenestration and door U-factor and product ratingsMAURICIO ANDRADEenergy_progress
08/26/2026Fenestration air leakageMAURICIO ANDRADEenergy_progress
08/26/2026Protection of exposed foundation insulationMAURICIO ANDRADEenergy_progress
08/26/2026Air barrier - visual inspectionMAURICIO ANDRADEenergy_progress
08/26/2026Fenestration areasMAURICIO ANDRADEenergy_progress
08/13/2026Private On-Site Storm Water Disposal Systems-, and Detention Facilities, InstallationMAURICIO ANDRADEspecial
08/13/2026HVAC-R and service water piping design and insulationMAURICIO ANDRADEenergy_progress
08/04/2026Concrete - Cast-In-PlaceMAURICIO ANDRADEspecial
08/04/2026Footing and FoundationMAURICIO ANDRADEprogress
08/04/2026Excavations - Sheeting, Shoring, and BracingMAURICIO ANDRADEspecial
08/04/2026Subgrade InspectionsMAURICIO ANDRADEspecial
08/04/2026Structural Stability – Alterations of existing buildingsMAURICIO ANDRADEspecial
08/04/2026Post-installed AnchorsMAURICIO ANDRADEspecial
08/04/2026FinalMAURICIO ANDRADEprogress
08/04/2026Subsurface Investigations (Borings/Test Pits)THOMAS THOMANNspecial
08/04/2026Subsurface Conditions – Fill Placement & In-Place DensityMAURICIO ANDRADEspecial
07/30/2026Sprinkler SystemsMAURICIO ANDRADEspecial
07/30/2026Standpipe SystemsMAURICIO ANDRADEspecial
Latest 25 of 113.
▾Documents — 203 on file (BIS + DOB NOW)
▸Plans & Drawings38
▸DOB NOWPlans/Sketch38
08/26/2026M01075262-I1Request digital key ↗
08/24/2026M00826434-B1Request digital key ↗
08/24/2026M00826434-A8Request digital key ↗
Showing 3 of 38 on file for this type
▸Applications & Permits3
▸BISBPP-5 - Authorization to the Department of Transportation1
05/17/2024141025762Open ↗
▸BISPLAN / WORK APPROVAL APPLICATION1
05/17/2024141025762Open ↗
▸DOB NOWHPD - Permit Notice1
08/13/2026M00826434-I1Open ↗
▸Zoning, Tax Lot & Property Records7
▸DOB NOWZD1: DOB Zoning Diagram5
09/10/2026M00826434-B2Open ↗
08/17/2026M00826434-P8Open ↗
08/17/2026M00826434-I1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026M00826434-I1Open ↗
▸DOB NOWZoning Exhibit form (1-5)1
09/10/2026M00826434-B2Open ↗
▸Seals & Professional Certifications82
▸DOB NOWDPL-1: Design Professional Seal & Signature36
09/10/2026M00826434-B2Open ↗
08/26/2026M01075262-I1Open ↗
08/23/2026M01173578-I1Open ↗
Showing 3 of 36 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature22
09/23/2026M00826434-B2Open ↗
09/23/2026M00826434-A9Open ↗
09/23/2026M00826434-A9Open ↗
Showing 3 of 22 on file for this type
▸DOB NOWProgress Inspector Seal & Signature22
09/23/2026M00826434-B2Open ↗
09/23/2026M00826434-B2Open ↗
09/23/2026M00826434-B2Open ↗
Showing 3 of 22 on file for this type
▸BISAPPLICANT OWNER SIGNATURE1
05/17/2024141025762Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
05/17/2024141025762Open ↗
▸Trade Schedules & Equipment5
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)4
08/17/2026M00826434-P8Open ↗
08/17/2026M00826434-I1Open ↗
08/15/2026M00826434-P4Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWStandpipe Alarms Drawings1
08/17/2026M00826434-I1—
▸Safety & Tenant Protection7
▸DOB NOWStreet Tree Checklist5
09/10/2026M00826434-B2Open ↗
08/17/2026M00826434-P8Open ↗
08/17/2026M00826434-I1Open ↗
Showing 3 of 5 on file for this type
▸BISBPP: STREET TREES SITE PLAN1
05/17/2024141025762Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026M00826434-I1Open ↗
▸Energy Compliance1
▸DOB NOWPreliminary Commissioning Report Certification1
08/17/2026M00826434-S4Open ↗
▸Inspections & Test Reports5
▸DOB NOWSOIL REPORT4
08/17/2026M00826434-S1Open ↗
08/17/2026M00826434-P2Open ↗
08/17/2026M00826434-A9Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWTR4 Test Report and Plot Diagram1
08/13/2026M00826434-S1Open ↗
▸Approvals, Objections & Sign-offs37
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter33
09/10/2026M00826434-B2Open ↗
08/23/2026M01173578-S2Open ↗
08/23/2026M01173578-I1Open ↗
Showing 3 of 33 on file for this type
▸DOB NOWDesign Commission Approval City Owned (Exterior Work)3
08/13/2026M01075262-I1Open ↗
08/13/2026M00826434-S7Open ↗
08/13/2026M00826434-S9Open ↗
▸BISDESIGN COMM. APPROVAL: CITY-OWNED PROPERTY (EXTERIOR WORK)1
05/17/2024141025762Open ↗
▸Filing & Intake Forms2
▸BISEFILING JOB APPLICATION COVER SHEET1
05/17/2024141025762Open ↗
▸BISBPP: CHECKLIST IN LIEU OF PLANS-ALT31
05/17/2024141025762Open ↗
▸Other Documents16
▸DOB NOWSite Survey: Initial5
09/10/2026M00826434-B2Open ↗
08/17/2026M00826434-P8Open ↗
08/17/2026M00826434-I1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone5
09/10/2026M00826434-B2Open ↗
08/17/2026M00826434-P8Open ↗
08/17/2026M00826434-I1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWCalculations2
08/13/2026M01267192-P1Open ↗
08/13/2026M01267192-I1Open ↗
▸DOB NOWManufacturer's Specifications2
08/13/2026M01267192-I1Open ↗
08/13/2026M01267192-P1Open ↗
▸DOB NOWAdjoining Owners Notification1
08/13/2026M00826434-S6Open ↗
▸DOB NOWFinal Survey1
08/13/2026M00826434-I1Open ↗