| Owner | Filings | Most Recent |
|---|---|---|
| RPM | 10 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| ROGERS CALVANICO GROUP PLLC | 6 | 11/29/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| ROGERS CALVANICO GROUP | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| RAISE THE ROOF GC INC | General Contractor | 15 | 03/21/2026 |
| RITE-FLO P.H.& COOLING IN | Plumbing | 2 | 07/08/2026 |
| QUALITY PLUMBING, INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| A TECH ENGINEERING NYC, P | 6738 | 5 | 11/29/2023 |
| ROGERS CALVANICO GROUP PL | 1324 | 3 | 11/29/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | DJ PLUMBING & HEATING COR | 11/15/2023 |
| DOB NOW | Plumbing | Signed-off | QUALITY PLUMBING, INC | 04/21/2023 |
| DOB NOW | Plumbing | Signed-off | DJ PLUMBING & HEATING COR | 04/21/2023 |
| DOB NOW | Construction Fence | Signed-off | RAISE THE ROOF GC INC | 04/06/2023 |
| DOB NOW | General Construction | Signed-off | RAISE THE ROOF GC INC | 03/28/2023 |
| DOB NOW | General Construction | Permit Issued | RAISE THE ROOF GC INC | 03/28/2023 |
| DOB NOW | Structural | Signed-off | RAISE THE ROOF GC INC | 03/28/2023 |
| DOB NOW | Structural | Signed-off | RAISE THE ROOF GC INC | 03/28/2023 |
| BIS | OT | ISSUED | FICAZZOLA CONSULTING LLC | 10/23/2023 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/29/2023 | Signed-off | RITE-FLO P.H.& COOLING IN | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/20/2023 | Complete | AMBER ELECTL CONTNG INC | — |
| 06/26/2023 | Complete | FICHERA ELECTRIC, INC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/29/2023 | Signed-off | RITE-FLO P.H.& COOLING IN | Wood |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/29/2023 | Signed-off | RITE-FLO P.H.& COOLING IN | Fence |
| Date | Type | Result | Report |
|---|---|---|---|
| 12/20/2023 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 09/13/2023 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 09/13/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 08/04/2023 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 08/04/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 05/11/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 05/09/2023 | Certified Storm Drainage-ST-Fixtures-Finish | Certified | View ↗ |
| 05/05/2023 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 11/21/2023 | Mechanical Systems | anthony santoro | special |
| 11/21/2023 | Subgrade Inspections | anthony santoro | special |
| 11/21/2023 | Concrete - Cast-In-Place | anthony santoro | special |
| 11/21/2023 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | anthony santoro | special |
| 11/21/2023 | Exterior Insulation and Finish Systems (EIFS) | anthony santoro | special |
| 11/21/2023 | Subsurface Investigations (Borings/Test Pits) | anthony santoro | special |
| 11/21/2023 | Fire-Resistant Penetrations and Joints | anthony santoro | special |
| 11/21/2023 | Footing and Foundation | anthony santoro | progress |
| 11/21/2023 | Lowest Floor Elevation | anthony santoro | progress |
| 11/21/2023 | Energy Code Compliance Inspections | anthony santoro | progress |
| 11/21/2023 | Structural Wood Frame | anthony santoro | progress |
| 11/21/2023 | Final | anthony santoro | progress |
| 11/21/2023 | Duct leakage testing, insulation and design | anthony santoro | energy_progress |
| 11/21/2023 | Electric vehicle service equipment requirements | anthony santoro | energy_progress |
| 11/21/2023 | Fenestration areas | anthony santoro | energy_progress |
| 11/21/2023 | HVAC-R and service water heating system controls | anthony santoro | energy_progress |
| 11/21/2023 | Fenestration and door U-factor and product ratings | anthony santoro | energy_progress |
| 11/21/2023 | Permanent certificate | anthony santoro | energy_progress |
| 11/21/2023 | Air barrier — testing | anthony santoro | energy_progress |
| 11/21/2023 | Fenestration air leakage | anthony santoro | energy_progress |
| 11/21/2023 | Insulation placement and R values | anthony santoro | energy_progress |
| 11/21/2023 | Protection of exposed foundation insulation | anthony santoro | energy_progress |
| 11/21/2023 | Metering | anthony santoro | energy_progress |
| 11/21/2023 | HVAC-R and service water piping design and insulation | anthony santoro | energy_progress |
| 11/21/2023 | Ventilation and air distribution system | anthony santoro | energy_progress |