| Owner | Filings | Most Recent |
|---|---|---|
| H.L. GENERAL CONTRACTORS | 3 | 03/22/2026 |
| TERMINAL REALTY | 12 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| BAALBAKI&ASSOCIATES ENGINEERING, PC | 12 | 02/12/2026 |
| Representative | Filings | Most Recent |
|---|---|---|
| B A INSPECTIONS | 24 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| H.L. GENERAL CONTRACTORS | General Contractor | 8 | 07/08/2026 |
| WP CONTRACTING INC | General Contractor | 4 | 04/09/2026 |
| A&H EXPRESS PLBG&HTG CORP | Plumbing | 1 | 07/08/2026 |
| EH PLUMBING & HEATING COR | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| BAALBAKI&ASSOCIATES ENGIN | 1858 | 10 | 02/12/2026 |
| M. INT'L ENGINEERING PLLC | 3129 | 1 | 01/11/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Signed-off | WP CONTRACTING INC | 03/04/2024 |
| DOB NOW | Plumbing | Signed-off | A&H EXPRESS PLBG&HTG CORP | 02/20/2024 |
| DOB NOW | Structural | Signed-off | WP CONTRACTING INC | 02/09/2024 |
| DOB NOW | Construction Fence | Signed-off | H.L. GENERAL CONTRACTORS | 05/03/2023 |
| DOB NOW | Construction Fence | Signed-off | H.L. GENERAL CONTRACTORS | 10/05/2022 |
| DOB NOW | Plumbing | Signed-off | EH PLUMBING & HEATING COR | 06/07/2022 |
| DOB NOW | Construction Fence | Signed-off | H.L. GENERAL CONTRACTORS | 04/29/2022 |
| DOB NOW | Construction Fence | Signed-off | H.L. GENERAL CONTRACTORS | 01/11/2022 |
| DOB NOW | Construction Fence | Signed-off | H.L. GENERAL CONTRACTORS | 02/25/2021 |
| BIS | — | ISSUED | WP CONTRACTING INC | 02/08/2024 |
| BIS | — | ISSUED | H.L. GENERAL CONTRACTORS | 12/06/2023 |
| BIS | — | ISSUED | H.L. GENERAL CONTRACTORS | 05/23/2023 |
| BIS | — | ISSUED | H.L. GENERAL CONTRACTORS | 01/03/2023 |
| BIS | — | ISSUED | H.L. GENERAL CONTRACTORS | 05/02/2022 |
| BIS | — | ISSUED | H.L. GENERAL CONTRACTORS | 05/21/2021 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/17/2022 | Complete | SWITCH ELECT OF THE FIVE | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 01/08/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 12/29/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 06/08/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 05/23/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 03/06/2023 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 03/06/2023 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 03/06/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/12/2026 | Maintenance information | Mohammad Baalbaki | energy_progress |
| 03/12/2026 | Fire-Resistant Penetrations and Joints | Mohammad Baalbaki | special |
| 02/18/2026 | Final | JOHN MALVASIO | progress |
| 02/18/2026 | Mechanical Systems | Mohammad Baalbaki | special |
| 02/18/2026 | Maintenance information | Mohammad Baalbaki | energy_progress |
| 02/18/2026 | HVAC-R and service water heating equipment | Mohammad Baalbaki | energy_progress |
| 02/12/2026 | Final | JOHN MALVASIO | progress |
| 02/12/2026 | Mechanical Systems | Mohammad Baalbaki | special |
| 02/12/2026 | Maintenance information | Mohammad Baalbaki | energy_progress |
| 02/12/2026 | HVAC-R and service water heating equipment | Mohammad Baalbaki | energy_progress |
| 11/24/2023 | Fire-Resistant Penetrations and Joints | Mohammad Baalbaki | special |
| 11/24/2023 | Maintenance information | Mohammad Baalbaki | energy_progress |
| 04/25/2022 | Maintenance information | Mohammad Baalbaki | energy_progress |
| 04/25/2022 | Fire-Resistant Penetrations and Joints | Mohammad Baalbaki | special |