| Firm | Filings | Most Recent |
|---|---|---|
| SAVIN ENGINEERS | 4 | 01/10/2025 |
| TOHFAZ UDDIN PE PC | 1 | 07/20/2020 |
| Representative | Filings | Most Recent |
|---|---|---|
| WDF | 4 | 03/21/2026 |
| A1 EXPEDITING SERVICE CORP. | 2 | 03/21/2026 |
| DIRECT ACCESS EXPEDITING, INC. | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| WDF INC | General Contractor | 28 | 07/08/2026 |
| WDF INC | Plumbing | 13 | 07/08/2026 |
| KING HOIST & SCAFFOLDING | General Contractor | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| TECTONIC ENGINEERING CONS | 106 | 4 | 01/10/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Permit Issued | WDF INC | 05/28/2026 |
| DOB NOW | Plumbing | Permit Issued | WDF INC | 05/28/2026 |
| DOB NOW | Structural | Permit Issued | WDF INC | 05/28/2026 |
| DOB NOW | Plumbing | Permit Issued | WDF INC | 05/29/2025 |
| DOB NOW | Structural | Permit Issued | WDF INC | 05/28/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | WDF INC | 05/28/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | WDF INC | 03/19/2025 |
| DOB NOW | Structural | Permit Issued | WDF INC | 03/19/2025 |
| DOB NOW | Plumbing | Permit Issued | WDF INC | 10/25/2024 |
| DOB NOW | Plumbing | Permit Issued | WDF INC | 03/26/2024 |
| DOB NOW | Structural | Permit Issued | WDF INC | 03/20/2024 |
| DOB NOW | Mechanical Systems | Permit Issued | WDF INC | 03/20/2024 |
| DOB NOW | Mechanical Systems | Permit Issued | WDF INC | 06/01/2023 |
| DOB NOW | Structural | Permit Issued | WDF INC | 06/01/2023 |
| DOB NOW | Plumbing | Permit Issued | WDF INC | 04/06/2023 |
| DOB NOW | Plumbing | Permit Issued | WDF INC | 03/31/2023 |
| DOB NOW | Plumbing | Permit Issued | WDF INC | 05/31/2022 |
| DOB NOW | Plumbing | Permit Issued | WDF INC | 05/30/2022 |
| DOB NOW | Plumbing | Permit Issued | WDF INC | 05/25/2022 |
| DOB NOW | Mechanical Systems | Permit Issued | WDF INC | 05/25/2022 |
| DOB NOW | Structural | Permit Issued | WDF INC | 05/24/2022 |
| DOB NOW | Mechanical Systems | Permit Issued | WDF INC | 04/01/2022 |
| DOB NOW | Plumbing | Permit Issued | WDF INC | 04/01/2022 |
| DOB NOW | Structural | Permit Issued | WDF INC | 04/01/2022 |
| DOB NOW | Structural | Permit Issued | WDF INC | 12/29/2021 |
| DOB NOW | Plumbing | Permit Issued | WDF INC | 07/15/2021 |
| DOB NOW | Plumbing | Permit Issued | WDF INC | 06/02/2021 |
| DOB NOW | Mechanical Systems | Permit Issued | WDF INC | 05/13/2021 |
| DOB NOW | Structural | Permit Issued | WDF INC | 08/12/2020 |
| DOB NOW | Supported Scaffold | Permit Issued | KING HOIST & SCAFFOLDING | 07/21/2020 |
| DOB NOW | Mechanical Systems | Permit Issued | WDF INC | 07/16/2020 |
| DOB NOW | Plumbing | Permit Issued | WDF INC | 07/16/2020 |
| BIS | OT | ISSUED | WDF INC | 10/09/2025 |
| BIS | OT | ISSUED | WDF INC | 03/13/2025 |
| BIS | OT | ISSUED | WDF INC | 12/12/2024 |
| BIS | OT | ISSUED | WDF INC | 05/24/2024 |
| BIS | BL | ISSUED | WDF INC | 05/24/2024 |
| BIS | OT | ISSUED | WDF INC | 05/24/2024 |
| BIS | OT | ISSUED | WDF INC | 06/05/2023 |
| BIS | OT | ISSUED | WDF INC | 06/01/2023 |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 01/27/2025 | Fire-Resistant Penetrations and Joints | GEORGE GHEBRYAL | special |
| 01/27/2025 | High-Pressure Fuel-Gas Piping (Welding) | GEORGE GHEBRYAL | special |
| 01/03/2025 | High-Pressure Fuel-Gas Piping (Welding) | GEORGE GHEBRYAL | special |
| 01/03/2025 | Fire-Resistant Penetrations and Joints | GEORGE GHEBRYAL | special |
| 02/21/2020 | Heating Systems | GEORGE GHEBRYAL | special |
| 02/21/2020 | High-Pressure Fuel-Gas Piping (Welding) | GEORGE GHEBRYAL | special |
| 02/21/2020 | Chimneys and vents | GEORGE GHEBRYAL | special |
| 11/07/2019 | Post-installed Anchors | GEORGE GHEBRYAL | special |
| 11/07/2019 | Fire-Resistant Penetrations and Joints | GEORGE GHEBRYAL | special |
| 09/19/2019 | Final | GEORGE GHEBRYAL | progress |
| 09/19/2019 | Mechanical Systems | GEORGE GHEBRYAL | special |