| Owner | Filings | Most Recent |
|---|---|---|
| RSTA HOLDINGS | 24 | 07/08/2026 |
| MCCLEAN HOLDINGS | 10 | 07/08/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| TOM PETERSEN ARCHITECT, LLC | 2 | 12/17/2025 |
| GREEN RIVER ENVIRONMENTAL ENGINEERI | 1 | 09/11/2025 |
| AVID DESIGNS, INC | 10 | 04/01/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| NY State Solar LLC | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| DELTAMER, INC | General Contractor | 5 | 07/08/2026 |
| NYSS LLC | General Contractor | 1 | 04/09/2026 |
| BROOKLYN SOLAR PARTNERS | General Contractor | 1 | 04/09/2026 |
| DV PLUMBING INC | Plumbing | 1 | 07/08/2026 |
| FLOW-RIGHT PLBG & HTG COR | Plumbing | 1 | 07/08/2026 |
| QUALITY PLUMBING, INC | Plumbing | 1 | 07/08/2026 |
| WILLIAM REYNOLDS | General Contractor | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| THOMAS PETERSEN ARCHITECT | 7854 | 2 | 12/17/2025 |
| GREEN RIVER ENVIRONMENTAL | 7841 | 1 | 09/11/2025 |
| AVID DESIGNS, INC. | 453 | 10 | 04/01/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Solar | Signed-off | BROOKLYN SOLAR PARTNERS | 12/22/2025 |
| DOB NOW | Solar | Signed-off | NYSS LLC | 09/16/2025 |
| DOB NOW | Curb Cut | Signed-off | DELTAMER, INC | 12/06/2024 |
| DOB NOW | Solar | Signed-off | WILLIAM REYNOLDS | 10/09/2024 |
| DOB NOW | Plumbing | Signed-off | QUALITY PLUMBING, INC | 03/21/2024 |
| DOB NOW | Plumbing | Signed-off | DV PLUMBING INC | 03/06/2024 |
| DOB NOW | Plumbing | Signed-off | FLOW-RIGHT PLBG & HTG COR | 11/27/2023 |
| DOB NOW | General Construction | Permit Issued | DELTAMER, INC | 10/13/2023 |
| DOB NOW | Construction Fence | Signed-off | DELTAMER, INC | 05/16/2023 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 04/01/2025 | Signed-off | DELTAMER, INC | Heating and Air Conditioning Systems, Ventilation Systems |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/01/2025 | — | — | 25 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/01/2025 | Signed-off | DV PLUMBING INC | Gas, Plumbing-Sprinkler, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/15/2025 | Complete | JSP ELECTL CNTNG CORP | — |
| 09/11/2025 | Complete | NY SOLAR ELECTRICAL LLC | — |
| 08/19/2024 | Complete | JSP ELECTL CNTNG CORP | — |
| 03/18/2024 | Complete | A & R ELEC'L CONTR'G INC. | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/01/2025 | Signed-off | DELTAMER, INC | Wood |
| Date | Type | Result | Report |
|---|---|---|---|
| 03/12/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 01/30/2025 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 11/13/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 10/17/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 10/11/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 10/04/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 09/09/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 05/08/2024 | Certified Storm Drainage-ST-Fixtures-Finish | Certified | View ↗ |
| 05/06/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 05/01/2024 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 12/26/2023 | Pass-Final PL - Underground | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 12/17/2025 | Structural Stability – Alterations of existing buildings | TOM PETERSEN | special |
| 12/17/2025 | Air barrier - visual inspection | TOM PETERSEN | energy_progress |
| 12/17/2025 | Final | TOM PETERSEN | progress |
| 12/17/2025 | Energy Code Compliance Inspections | TOM PETERSEN | progress |
| 12/17/2025 | Fire-Resistant Penetrations and Joints | TOM PETERSEN | special |
| 09/11/2025 | Fire-Resistant Penetrations and Joints | ROBERT MASONE | special |
| 09/11/2025 | Air barrier - visual inspection | ROBERT MASONE | energy_progress |
| 09/11/2025 | Final | ROBERT MASONE | progress |
| 09/11/2025 | Energy Code Compliance Inspections | ROBERT MASONE | progress |
| 09/11/2025 | Structural Stability – Alterations of existing buildings | ROBERT MASONE | special |
| 04/01/2025 | Final | anthony santoro | progress |
| 04/01/2025 | Fenestration air leakage | anthony santoro | energy_progress |
| 04/01/2025 | Insulation placement and R values | anthony santoro | energy_progress |
| 04/01/2025 | Duct leakage testing, insulation and design | anthony santoro | energy_progress |
| 04/01/2025 | Electric vehicle service equipment requirements | anthony santoro | energy_progress |
| 04/01/2025 | Maintenance information | anthony santoro | energy_progress |
| 04/01/2025 | Ventilation and air distribution system | anthony santoro | energy_progress |
| 04/01/2025 | Permanent certificate | anthony santoro | energy_progress |
| 04/01/2025 | Concrete - Cast-In-Place | Jeffrey Geary | special |
| 04/01/2025 | Fire-Resistant Penetrations and Joints | Jeffrey Geary | special |
| 04/01/2025 | Mechanical Systems | Jeffrey Geary | special |
| 04/01/2025 | Subgrade Inspections | Jeffrey Geary | special |
| 04/01/2025 | Energy Code Compliance Inspections | anthony santoro | progress |
| 04/01/2025 | Fire-Resistance Rated Construction | anthony santoro | progress |
| 04/01/2025 | Footing and Foundation | anthony santoro | progress |