| Owner | Filings | Most Recent |
|---|---|---|
| BLUE WATER BUILDERS | 2 | 03/22/2026 |
| 76-78 WEST 170 STREET | 1 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 11/05/2021 | $725K | — | Private party → 76-78 WEST 170TH STREET, LLC | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| ROGERS ARCHITECTS PLLC | 2 | 06/16/2026 |
| ROJAS ENGINEERING, PLLC | 3 | 05/20/2026 |
| Representative | Filings | Most Recent |
|---|---|---|
| CORE CONSULTANTS NYC | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| DENALI ELECTRIC CORP | Electrical | 1 | 03/22/2026 |
| OM CONSTRUCTION INC | General Contractor | 1 | 07/08/2026 |
| HORBRIDGE PLUMBING & HEATING | Plumbing | 1 | 06/27/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| ROJAS ENGINEERING PLLC | 6232 | 3 | 05/20/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | HORBRIDGE PLUMBING & HEAT | 02/11/2026 |
| DOB NOW | General Construction | Permit Issued | OM CONSTRUCTION INC | 02/09/2026 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 06/16/2026 | Permit Issued | BLUE WATER BUILDERS LLC | Air Conditioning Systems, Heating and Air Conditioning Systems, Heating Systems, Ventilation Systems | Heat / Cool Mitsubishi Electric PEFY-P24NMAU 883 CFM · Vrf Indoor ×1 PFFY-P12NEMU 313 CFM · Vrf Indoor ×1 PKFY-P12NHMU 413 CFM · Vrf Indoor ×1 PKFY-PO6NBMU 210 CFM · Vrf Indoor ×1 PLFY-P12NCMU 390 CFM · Vrf Indoor ×1 PUMY-P36NHMU 36,000 BTU · Vrf Outdoor ×1 PUMY-P48NHMU 48,000 BTU · Vrf Outdoor ×1 TVAHP036B21S 48,000 BTU · Vrf Outdoor ×5 Aaon RN-015-3-0-GAAY-V0-21-000-A 4,200 CFM · Rooftop Unit ×5 Hitachi AC024DXSCCG 36,000 BTU · Vrf Indoor ×5 Johnson Controls TVAHP048B21S 48,000 BTU · Condensing Unit ×5 Ventilation Greenheck ERCH-45-30L-S-EH 165 kW · Erv ×1 AX-41-300-160-0607-M15-X/BCV-105/BCV-90 350 CFM · Exhaust Fan ×15 BCV-90 250 CFM · Exhaust Fan ×10 AX-41-300-160-0607-M15-X 1,700 CFM · Exhaust Fan ×5 Mitsubishi Electric TIDMO12B24S/TIMO24B23S/TIWMO12B21S 18,000 BTU · Fan Coil Indoor ×15 TICM015B21S/TICM012B21S 1,200 CFM · Fan Coil Indoor ×10 Broan L100E-A/L100E-A/L100E-A 75 CFM · Exhaust Fan ×15 Twin City Fan DSI-080AE 300 CFM · Exhaust Fan ×10 Cooling Samsung AS024DNADCG 24,000 BTU · Split System ×5 Heating Qmark BH-240-U1033C-T 10,200 BTU · Electric Heater ×30 931IF-F4008-N/ 931IF-F4004-N/ 931IF-F4008-N/931IF-F4008-N 13,700 BTU · Electric Heater ×20 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/16/2026 | Signed-off | FORWARD MECHANICAL CORP | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/16/2026 | Signed-off | FORWARD MECHANICAL CORP | Storm, Water/Sanitary |
| 05/20/2026 | Permit Issued | HORBRIDGE PLUMBING & HEAT | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/13/2026 | Permit Issued | ASCUATECH ELECTRICAL CORP | General Wiring |
| 11/12/2025 | Complete | DENALI ELECTRIC CORP | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/16/2026 | Signed-off | FORWARD MECHANICAL CORP | Steel, Concrete, Masonry |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/16/2026 | Signed-off | FORWARD MECHANICAL CORP | Earthwork |
| Date | Type | Result | Report |
|---|---|---|---|
| 06/03/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 06/03/2026 | Exterior Insulation and Finish Systems (EIFS) | — | special |
| 06/03/2026 | Fire-Resistant Penetrations and Joints | — | special |
| 06/03/2026 | Luminous Exit Path Markings | — | special |
| 06/03/2026 | Energy Code Compliance Inspections | — | progress |
| 06/03/2026 | Fire-Resistance Rated Construction | — | progress |
| 06/03/2026 | Protection of exposed foundation insulation | SAMI HAJJAR P.E | energy_progress |
| 06/03/2026 | Air barrier - visual inspection | SAMI HAJJAR P.E | energy_progress |
| 06/03/2026 | Fenestration areas | SAMI HAJJAR P.E | energy_progress |
| 06/03/2026 | Insulation placement and R values | SAMI HAJJAR P.E | energy_progress |
| 06/03/2026 | Fenestration air leakage | SAMI HAJJAR P.E | energy_progress |
| 06/03/2026 | Fenestration and door U-factor and product ratings | SAMI HAJJAR P.E | energy_progress |
| 05/22/2026 | Fire-Resistant Penetrations and Joints | Darlyn Alvarez | special |
| 05/22/2026 | Tenant Protection Plan Compliance | — | special |
| 02/24/2026 | Fenestration areas | SAMI HAJJAR P.E | energy_progress |
| 02/24/2026 | Fenestration air leakage | SAMI HAJJAR P.E | energy_progress |
| 02/24/2026 | Insulation placement and R values | SAMI HAJJAR P.E | energy_progress |
| 02/24/2026 | Protection of exposed foundation insulation | SAMI HAJJAR P.E | energy_progress |
| 02/24/2026 | Fenestration and door U-factor and product ratings | SAMI HAJJAR P.E | energy_progress |
| 02/24/2026 | Air barrier - visual inspection | SAMI HAJJAR P.E | energy_progress |
| 01/30/2026 | Tenant Protection Plan Compliance | Darlyn Alvarez | special |
| 01/29/2026 | Lighting controls | Darlyn Alvarez | energy_progress |
| 01/29/2026 | Interior lighting power | Darlyn Alvarez | energy_progress |
| 01/29/2026 | Final | Darlyn Alvarez | progress |
| 01/29/2026 | Fire-Resistant Penetrations and Joints | Darlyn Alvarez | special |