| Owner | Filings | Most Recent |
|---|---|---|
| PHA COOPERATIVE | 16 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| CHAPMAN ARCHITECTS | 2 | 01/27/2026 |
| NEW YORK ENGINEERING ASSOC., P.C. | 2 | 06/01/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| MUNICIPAL BUILDING CONSULTANTS | 2 | 03/21/2026 |
| NEW YORK ENGINEERING ASSOCIATES P C | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| HUB PLUMBING&HEATING CORP | Plumbing | 2 | 07/08/2026 |
| STEPHEN TATE | Electrical | 1 | 03/21/2026 |
| L & B BROTHERS CORP | General Contractor | 1 | 04/09/2026 |
| GJ PLUMBING LLC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| NEW YORK ENGINEERING ASSO | 851 | 2 | 06/01/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | TVS MECHANICAL CORP | 02/19/2026 |
| DOB NOW | General Construction | Permit Issued | L & B BROTHERS CORP | 02/10/2026 |
| DOB NOW | Plumbing | Signed-off | HUB PLUMBING&HEATING CORP | 06/07/2021 |
| DOB NOW | Boiler Equipment | Signed-off | HUB PLUMBING&HEATING CORP | 06/07/2021 |
| BIS | PL | ISSUED | DPH PLUMBING & HTG CORP | 03/31/2016 |
| BIS | OT | ISSUED | HIGH QUALITY CONSTRUCTION | 03/22/2016 |
| BIS | PL | ISSUED | ARK-POL PLUMBING CORP | 02/17/2015 |
| BIS | OT | ISSUED | LUIGI CALIENDO & SONS,INC | 01/23/2015 |
| BIS | OT | ISSUED | ACE CONTRACTING CONSULTING | 01/28/2013 |
| BIS | PL | ISSUED | TIME MECHANICALS INC. | 11/26/2012 |
| BIS | OT | ISSUED | LARRY BEDDALL INC | 11/21/2012 |
| BIS | OT | ISSUED | LARRY BEDDALL INC | 09/12/2012 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/27/2026 | Permit Issued | TVS MECHANICAL CORP | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/29/2026 | Complete | JOSEPH WEINSTEIN ELECTRIC | General Wiring |
| 08/30/2020 | Complete | NYCO ELECTRIC CORP | General Wiring |
| 07/12/2020 | Complete | BNH ELECTRICAL CORP | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/06/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 06/05/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 04/06/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/02/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 03/18/2026 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 03/18/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 02/22/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 08/04/2021 | Pass-Final Boiler Equipment Inspection | Pass | View ↗ |
| 07/27/2021 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 06/29/2021 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 01/22/2026 | Energy Code Compliance Inspections | Margaret Chapman | progress |
| 01/22/2026 | Final | Margaret Chapman | progress |
| 05/12/2021 | HVAC-R and service water heating system controls | LOUIS ARENA | energy_progress |
| 05/12/2021 | HVAC-R and service water heating equipment | LOUIS ARENA | energy_progress |
| 05/12/2021 | Fire-Resistant Penetrations and Joints | LOUIS ARENA | special |
| 05/12/2021 | Heating Systems | LOUIS ARENA | special |
| 05/12/2021 | Energy Code Compliance Inspections | LOUIS ARENA | progress |
| 05/12/2021 | Maintenance information | LOUIS ARENA | energy_progress |