← Back
Fire Department
14 EAST 18 STREET
MANHATTAN · BIN 1016141
💬 Discuss this project
1895Year Built
3Stories
Y1Building Class
M1-5MZoning
5,623 sfGross Floor Area
1Units
4 Open Violations 2 unresolved · 2 paperwork only ▸
Fire Department · Owner of record: FIRE DEPARTMENT OF NEW YORK · 1,963 sf lot · 2.86 FAR built · Flood zone X
Locations of Work
ArchitecturePlumbingCivil
Permit Issued — active, not yet Signed-off
CellarUnder Construction7p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
FDNY1407/08/2026
DEPT OF DESIGN CONSTRUCTION703/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
CAMERON ENGINEERING601/08/2026
KONOSKI ENGINEERING PLLC109/08/2025
LIRO ENGINEERS, INC.104/09/2021
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
P WOLFE CONSULTANTS203/21/2026
KUSHNER STUDIOS103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
FRANCO BELLI PLMG&HTG SONPlumbing307/08/2026
GLASS ARMOR OF NEW YORK IGeneral Contractor203/21/2026
SAMIRO SERVICES INCGeneral Contractor204/09/2026
JOHN VILLAFANEElectrical103/21/2026
JOSEPH CURCIOElectrical103/21/2026
VILLAFANE JOHNElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
KONOSKI ENGINEERING PLLC9111109/08/2025
EC SPECIAL INSPECTIONS8355106/08/2023
TECTONIC ENGINEERING CONS106104/09/2021
Building Lifecycle
All (70)Filed (8)Permit Issued (6)Signed Off (2)Violation (28)Inspection (10)Objection (8)Special Inspection (8)
09/01/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
07/27/2026
Signed off — Alteration
Filing herewith for installation of Makeup Air Unit and related ductwork
M01242942-I1
06/04/2026
Inspection — Certified Sprinkler (PL)-Sprinkler-Hydro
Certified
View inspection ↗
06/02/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
02/11/2026
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
02/03/2026
Permit issued — Plumbing
M00870266-S1-PL
01/28/2026
Permit issued — Mechanical Systems
M01242942-I1-MS
01/13/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
01/08/2026
Filed — Alteration
Addition of fire-rated walls to bring boiler room up to code.
M00870266-P3
11/14/2025
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
10/14/2025
Permit issued — Mechanical Systems
M01242942-I1-MS
10/07/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
09/19/2025
Inspection — Pass-Final Boiler Equipment Inspection
Pass
View inspection ↗
09/08/2025
Filed — Alteration
Filing herewith for installation of Makeup Air Unit and related ductwork
M01242942-I1
07/14/2025
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
07/14/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
06/18/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
06/17/2025
Special inspection requirement — Ventilation and air distribution system
christopher konoski
06/17/2025
Special inspection requirement — Final
christopher konoski
06/17/2025
Special inspection requirement — Maintenance information
christopher konoski
06/17/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
christopher konoski
06/17/2025
Special inspection requirement — Mechanical Systems
christopher konoski
06/17/2025
Special inspection requirement — Energy Code Compliance Inspections
christopher konoski
01/13/2025
Permit issued — Boiler Equipment
M00870266-I1-BE
01/08/2025
Permit issued — Plumbing
M00870266-S1-PL
02/27/2024
Signed off — Alteration
mpty,purge,clean, remove & dispose of one (1) 550-Gallon Diesel Motor Fuel AST, (1) fuel dispenser, Conc Is & veederroot. Install 'IN -KIND' one (1) new 550- Gallon field Fabricated Single-Wall Steel Diesel Motor Fuel AST, (1) FuelDispenser per plans.
M00499600-I1
10/11/2023
Filed — Alteration
Addition of fire-rated walls to bring boiler room up to code.
M00870266-P2
10/10/2023
Filed — Alteration
Addition of fire-rated walls to bring boiler room up to code.
M00870266-P1
08/18/2023
Permit issued — General Construction
M00499600-I1-GC
06/09/2023
Filed — Alteration
Addition of fire-rated walls to bring boiler room up to code.
M00870266-S2
06/09/2023
Filed — Alteration
Addition of fire-rated walls to bring boiler room up to code.
M00870266-S1
06/08/2023
Filed — Alteration
Addition of fire-rated walls to bring boiler room up to code.
M00870266-I1
05/04/2023
Special inspection requirement — Heating Systems
ABDALLAH ELCHERBINI
05/04/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
ABDALLAH ELCHERBINI
06/15/2021
Objection raised — Other
06/15/2021
Objection resolved — Addressed
04/15/2021
Objection raised — Other
04/15/2021
Objection resolved — Addressed
04/15/2021
Objection raised — Other
04/15/2021
Objection resolved — Addressed
04/15/2021
Objection raised — Other
04/15/2021
Objection resolved — Addressed
04/09/2021
Filed — Alteration
mpty,purge,clean, remove & dispose of one (1) 550-Gallon Diesel Motor Fuel AST, (1) fuel dispenser, Conc Is & veederroot. Install 'IN -KIND' one (1) new 550- Gallon field Fabricated Single-Wall Steel Diesel Motor Fuel AST, (1) FuelDispenser per plans.
M00499600-I1
05/22/2018
Violation issued (ECB, open)
Construction
05/22/2018
Violation issued (ECB, open)
Boilers
04/02/2007
Violation issued (DOB, closed)
VW*-VIOLATION - WORK W/O PERMIT DISMISSED
04/02/2007
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
10/01/2005
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
09/08/2005
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
11/19/2004
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
04/21/2004
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
09/09/2003
Violation issued (DOB, closed)
VW*-VIOLATION - WORK W/O PERMIT DISMISSED
03/21/2003
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
10/29/2002
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
02/19/2002
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
12/27/2001
Violation issued (DOB, closed)
V*-DOB VIOLATION - Resolved
09/04/2001
Violation issued (ECB, closed)
Elevators
03/08/2001
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
02/27/2001
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
03/10/2000
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
Latest 60 of 70 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingPermit IssuedFRANCO BELLI PLMG&HTG SON02/03/2026
DOB NOWMechanical SystemsSigned-offSAMIRO SERVICES INC01/28/2026
DOB NOWMechanical SystemsSigned-offSAMIRO SERVICES INC10/14/2025
DOB NOWBoiler EquipmentSigned-offFRANCO BELLI PLMG&HTG SON01/13/2025
DOB NOWPlumbingPermit IssuedFRANCO BELLI PLMG&HTG SON01/08/2025
DOB NOWGeneral ConstructionSigned-offGLASS ARMOR OF NEW YORK I08/18/2023
BISPLISSUEDPACIFIC PLBG&HTG CORP06/23/2009
BISMHISSUEDR & L HEATING AND AIR CONDITIOND03/31/2008
BISPLISSUEDPACIFIC PLBG&HTG CORP03/27/2008
BISOTISSUEDZHL GROUP INC03/11/2008
BISFPISSUEDIDEAL FIRE SYSTEMS INC12/19/2002
BISPLISSUEDS & L PLUMBING INC10/02/2000
1 project · most recent 09/08/2025
Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
09/08/2025Signed-offSAMIRO SERVICES INCVentilation Systems
Ventilation
Captiveaire SIF15DD-HE 2,295 CFM · Makeup Air ×1
1 project · most recent 01/08/2026
Gas
FiledStatusContractorScope
01/08/2026Permit IssuedFRANCO BELLI PLMG&HTG SONGas
1 project · most recent 01/08/2024
General Wiring
FiledStatusContractorScope
01/08/2024Permit IssuedLCJ ELEC'L CONTR'S INCGeneral Wiring
▾Field Inspections (DOB CAP) — 10
DateTypeResultReport
09/01/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
06/04/2026Certified Sprinkler (PL)-Sprinkler-HydroCertifiedView ↗
06/02/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
02/11/2026Fail-Final PL - Up to 3 Requested FloorsFailView ↗
01/13/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
10/07/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
09/19/2025Pass-Final Boiler Equipment InspectionPassView ↗
07/14/2025Certified Gas-Gas-Piping-RoughingCertifiedView ↗
07/14/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
06/18/2025Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 8
DateRequirementInspectorRole
06/17/2025Ventilation and air distribution systemchristopher konoskienergy_progress
06/17/2025Finalchristopher konoskiprogress
06/17/2025Maintenance informationchristopher konoskienergy_progress
06/17/2025Fire-Resistant Penetrations and Jointschristopher konoskispecial
06/17/2025Mechanical Systemschristopher konoskispecial
06/17/2025Energy Code Compliance Inspectionschristopher konoskiprogress
05/04/2023Heating SystemsABDALLAH ELCHERBINIspecial
05/04/2023Fire-Resistant Penetrations and JointsABDALLAH ELCHERBINIspecial
▾Documents — 40 on file (BIS + DOB NOW)
▸Plans & Drawings8
▸DOB NOWPlans/Sketch8
08/29/2026M00870266-P2Request digital key ↗
08/29/2026M00870266-P1Request digital key ↗
08/29/2026M00870266-P3Request digital key ↗
Showing 3 of 8 on file for this type
▸Applications & Permits2
▸DOB NOWLPC Approval/Permit2
08/15/2026M00499600-I1Open ↗
08/13/2026M01242942-I1Open ↗
▸Seals & Professional Certifications12
▸DOB NOWDPL-1: Design Professional Seal & Signature8
09/03/2026M00499600-I1Open ↗
08/13/2026M00870266-P2Open ↗
08/13/2026M00870266-S2Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature2
09/23/2026M00870266-I1Open ↗
09/23/2026M01242942-I1Open ↗
▸DOB NOWProgress Inspector Seal & Signature2
09/23/2026M01242942-I1Open ↗
09/23/2026M01242942-I1Open ↗
▸Environmental & Asbestos8
▸DOB NOWDEP ACP-5: Asbestos Assessment Report8
08/15/2026M00499600-I1Open ↗
08/13/2026M00870266-S2Open ↗
08/13/2026M01242942-I1Open ↗
Showing 3 of 8 on file for this type
▸Energy Compliance1
▸DOB NOWEN2: As Built Energy Analysis.1
08/15/2026M00499600-I1Open ↗
▸Approvals, Objections & Sign-offs9
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter8
08/15/2026M00499600-I1Open ↗
08/13/2026M00870266-P3Open ↗
08/13/2026M00870266-P2Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWDesign Commission Sign Off City Owned (Exterior Work)1
08/15/2026M00499600-I1Open ↗