1892Year Built
4Stories
C6Building Class
R8BZoning
8,440 sfGross Floor Area
4Units
Walk-up cooperative · Owner of record: WHIPPLE HOUSE INC · 2,412 sf lot · 3.5 FAR built · Flood zone X
Locations of Work
Structural
Roof1p · 1 filing · 20 docs
Floor 12p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
A.L.L. CONSTRUCTION AND DESIGN, INC.103/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
CROSS ARCHITECTURE203/16/2022
WAVIC ENGINEERING PLLC106/23/2021
GORDON KAHN PROFESSIONAL ARCHITECT103/24/2021
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
JAMES D FERRANTE ARCHITECT203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
PAUL CILLIKElectrical503/21/2026
A.L.L. CONSTRUCTION AND DGeneral Contractor207/08/2026
PRUDENT ELECTRIC INCElectrical103/22/2026
PREMIER FLOW PLBG AND HTGPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
LEO Y LEE ASSOCIATES2481203/16/2022
GORDON KAHN PROFESSIONAL3212103/24/2021
Building Lifecycle
All (38)Filed (4)Permit Issued (3)Signed Off (2)Inspection (1)Special Inspection (28)
03/14/2023
Signed off — Alteration
M00514185-I1
03/18/2022
Special inspection requirement — Lighting controls
JANET CROSS
03/18/2022
Special inspection requirement — Fenestration areas
JANET CROSS
03/18/2022
Special inspection requirement — Fenestration air leakage
JANET CROSS
03/18/2022
Special inspection requirement — Lighting in dwelling units
JANET CROSS
03/18/2022
Special inspection requirement — Fenestration and door U-factor and product ratings
JANET CROSS
03/18/2022
Special inspection requirement — Interior lighting power
JANET CROSS
03/18/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
Leo Lee
03/18/2022
Special inspection requirement — Masonry
Leo Lee
03/18/2022
Special inspection requirement — Structural Stability – Alterations of existing buildings
Leo Lee
03/18/2022
Special inspection requirement — Concrete - Cast-In-Place
Leo Lee
03/18/2022
Special inspection requirement — Final
JANET CROSS
03/16/2022
Filed — Alteration
M00514185-P2
09/27/2021
Special inspection requirement — Fenestration areas
JANET CROSS
09/27/2021
Special inspection requirement — Final
JANET CROSS
09/27/2021
Special inspection requirement — Fenestration air leakage
JANET CROSS
09/27/2021
Special inspection requirement — Fenestration and door U-factor and product ratings
JANET CROSS
09/27/2021
Special inspection requirement — Lighting controls
JANET CROSS
09/27/2021
Special inspection requirement — Lighting in dwelling units
JANET CROSS
09/27/2021
Special inspection requirement — Interior lighting power
JANET CROSS
09/27/2021
Special inspection requirement — Fire-Resistant Penetrations and Joints
Leo Lee
09/27/2021
Special inspection requirement — Masonry
Leo Lee
09/27/2021
Special inspection requirement — Structural Stability – Alterations of existing buildings
Leo Lee
09/27/2021
Special inspection requirement — Concrete - Cast-In-Place
Leo Lee
07/30/2021
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
07/02/2021
Permit issued — Plumbing
M00533631-I1-PL
06/23/2021
Filed — Alteration
Install gas piping and gas meter as per plans.
M00533631-I1
06/08/2021
Permit issued — General Construction
M00514185-I1-GC
05/27/2021
Filed — Alteration
M00514185-I1
05/27/2021
Signed off — Alteration
M00477489-I1
05/10/2021
Permit issued — General Construction
M00477489-I1-GC
03/24/2021
Filed — Alteration
M00477489-I1
03/01/2021
Special inspection requirement — Insulation placement and R values
Gordon Kahn
03/01/2021
Special inspection requirement — Air barrier - visual inspection
Gordon Kahn
03/01/2021
Special inspection requirement — Fire-Resistance Rated Construction
Gordon Kahn
03/01/2021
Special inspection requirement — Energy Code Compliance Inspections
Gordon Kahn
03/01/2021
Special inspection requirement — Final
Gordon Kahn
03/01/2021
Special inspection requirement — Fire-Resistant Penetrations and Joints
Gordon Kahn
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offGALICJA PLBG AND HTG.CORP07/02/2021
DOB NOWGeneral ConstructionSigned-offA.L.L. CONSTRUCTION AND D06/08/2021
DOB NOWGeneral ConstructionSigned-offA.L.L. CONSTRUCTION AND D05/10/2021
BISEQISSUEDEVEREST SCAFFOLDING INC06/21/2011
BISEQISSUEDEVEREST SCAFFOLDING INC06/20/2011
BISOTISSUEDROONEY CONTRACTING INC04/27/2005
BISPLISSUEDSTEPHEN MECHANICAL SERVICE CORP03/22/2005
BISOTISSUEDTHOMAS P GALLAGHER, INC03/16/2005
BIS—ISSUEDTEMPLE CONTRACTING INC.09/28/1993
BIS—ISSUEDJR GRECH CONSTRUCTION CORT10/15/1992
BIS—ISSUEDLORANCO CORP.01/24/1991
1 project · most recent 06/23/2021
Gas
FiledStatusContractorScope
06/23/2021Signed-offGALICJA PLBG AND HTG.CORPGas
1 project · most recent 07/27/2021
General Wiring
FiledStatusContractorScope
07/27/2021Permit IssuedPRUDENT ELECTRIC INCGeneral Wiring
▾Field Inspections (DOB CAP) — 1
DateTypeResultReport
07/30/2021Certified Gas-Gas-Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 28
DateRequirementInspectorRole
03/18/2022Lighting controlsJANET CROSSenergy_progress
03/18/2022Fenestration areasJANET CROSSenergy_progress
03/18/2022Fenestration air leakageJANET CROSSenergy_progress
03/18/2022Lighting in dwelling unitsJANET CROSSenergy_progress
03/18/2022Fenestration and door U-factor and product ratingsJANET CROSSenergy_progress
03/18/2022Interior lighting powerJANET CROSSenergy_progress
03/18/2022Fire-Resistant Penetrations and JointsLeo Leespecial
03/18/2022MasonryLeo Leespecial
03/18/2022Structural Stability – Alterations of existing buildingsLeo Leespecial
03/18/2022Concrete - Cast-In-PlaceLeo Leespecial
03/18/2022FinalJANET CROSSprogress
09/27/2021Fenestration areasJANET CROSSenergy_progress
09/27/2021FinalJANET CROSSprogress
09/27/2021Fenestration air leakageJANET CROSSenergy_progress
09/27/2021Fenestration and door U-factor and product ratingsJANET CROSSenergy_progress
09/27/2021Lighting controlsJANET CROSSenergy_progress
09/27/2021Lighting in dwelling unitsJANET CROSSenergy_progress
09/27/2021Interior lighting powerJANET CROSSenergy_progress
09/27/2021Fire-Resistant Penetrations and JointsLeo Leespecial
09/27/2021MasonryLeo Leespecial
09/27/2021Structural Stability – Alterations of existing buildingsLeo Leespecial
09/27/2021Concrete - Cast-In-PlaceLeo Leespecial
03/01/2021Insulation placement and R valuesGordon Kahnenergy_progress
03/01/2021Air barrier - visual inspectionGordon Kahnenergy_progress
03/01/2021Fire-Resistance Rated ConstructionGordon Kahnprogress
Latest 25 of 28.
▾Documents — 56 on file (BIS + DOB NOW)
▸Plans & Drawings4
▸DOB NOWPlans/Sketch4
09/04/2026M00477489-I1Request digital key ↗
09/03/2026M00514185-I1Request digital key ↗
09/03/2026M00514185-P2Request digital key ↗
Showing 3 of 4 on file for this type
▸Applications & Permits7
▸DOB NOWLPC Approval/Permit3
08/13/2026M00477489-I1Open ↗
08/13/2026M00514185-I1Open ↗
08/13/2026M00514185-P2Open ↗
▸BISWORK PERMIT APPLICATION2
06/23/2011120726189Open ↗
06/23/2011120729809Open ↗
▸BISPLAN / WORK APPROVAL APPLICATION2
06/22/2011120726189Open ↗
06/22/2011120729809Open ↗
▸Seals & Professional Certifications30
▸DOB NOWProgress Inspector Seal & Signature13
09/20/2026M00514185-I1Open ↗
09/20/2026M00514185-I1Open ↗
09/20/2026M00514185-I1Open ↗
Showing 3 of 13 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature9
09/20/2026M00514185-I1Open ↗
09/20/2026M00514185-I1Open ↗
09/20/2026M00514185-I1Open ↗
Showing 3 of 9 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature4
09/03/2026M00514185-I1Open ↗
09/03/2026M00514185-P2Open ↗
08/13/2026M00533631-I1Open ↗
Showing 3 of 4 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION2
06/22/2011120726189Open ↗
06/22/2011120726189Open ↗
▸BISPROFESSIONAL CERTIFIED CHECKLIST1
06/22/2011120729809Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM1
06/22/2011120729809Open ↗
▸Trade Schedules & Equipment1
▸BISSCHEDULE B - PLUMBING1
06/22/2011120726189Open ↗
▸Environmental & Asbestos7
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'3
06/22/2011120726189Open ↗
06/22/2011120726189Open ↗
06/22/2011120726189Open ↗
▸DOB NOWDEP ACP-5: Asbestos Assessment Report3
09/03/2026M00514185-I1Open ↗
09/03/2026M00514185-P2Open ↗
08/13/2026M00477489-I1Open ↗
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER1
06/22/2011120729809Open ↗
▸Energy Compliance2
▸DOB NOWEN2: As Built Energy Analysis.2
08/13/2026M00477489-I1Open ↗
08/13/2026M00514185-I1Open ↗
▸Approvals, Objections & Sign-offs3
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST2
01/11/2021120729809Open ↗
01/06/2021120726189Open ↗
▸BISADMINISTRATIVE OBJECTIONS1
06/22/2011120729809Open ↗
▸Filing & Intake Forms2
▸BISEFILING COVER SHEET2
06/22/2011120726189Open ↗
06/22/2011120729809Open ↗