| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 04/13/2026 | — | — | Heating and Air Conditioning Systems | Heat / Cool Daikin RZA18AAVJU 20,000 BTU · Heat Pump Outdoor ×4 RXTA36AAVJU 37,000 BTU · Vrf Outdoor ×2 RXTA24AAVJU 25,000 BTU · Vrf Outdoor ×1 RXTA48AAVJU 46,000 BTU · Vrf Outdoor ×1 RZA24AAVJU 27,000 BTU · Condensing Unit ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/13/2026 | — | — | Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/04/2025 | Permit Issued | UL ELECTRICAL CORP. | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/13/2026 | — | — | Concrete |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/23/2026 | — | — | Fence |
| Owner | Filings | Most Recent |
|---|---|---|
| MISRA GROUP | 17 | 08/29/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 02/02/2022 | $950K | — | Private party → OPERA NYC, INC. | $675/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| C.E.C. INC. | 2 | 04/13/2026 |
| KCE CONSULTING ENGINEERING PLLC | 2 | 04/06/2026 |
| WELLS ENGINEERING, PLLC | 3 | 03/11/2026 |
| MISRA & ASSOCIATES, P.C. | 2 | 01/23/2026 |
| Representative | Filings | Most Recent |
|---|---|---|
| LLOYD NOEL BUILDING CONSULTANT | 5 | 03/21/2026 |
| CHAMELEON EXPEDITING | 1 | 03/21/2026 |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 05/18/2026 | Subsurface Investigations (Borings/Test Pits) | — | special |
| 04/07/2026 | Construction Operations Influencing Adjacent Structures | — | special |
| 04/07/2026 | Post-installed Anchors | — | special |
| 04/07/2026 | Subgrade Inspections | — | special |
| 04/07/2026 | Subsurface Conditions – Fill Placement & In-Place Density | — | special |
| 04/07/2026 | Footing and Foundation | — | progress |
| 04/07/2026 | Final | — | progress |
| 04/07/2026 | Concrete - Cast-In-Place | — | special |
| 04/07/2026 | Concrete - Cast-In-Place | — | special |
| 04/07/2026 | Construction Operations Influencing Adjacent Structures | — | special |
| 04/07/2026 | Excavations - Sheeting, Shoring, and Bracing | — | special |
| 04/07/2026 | Post-installed Anchors | — | special |
| 04/07/2026 | Subgrade Inspections | — | special |
| 04/07/2026 | Subsurface Conditions – Fill Placement & In-Place Density | — | special |
| 04/07/2026 | Final | — | progress |
| 04/06/2026 | Subgrade Inspections | — | special |
| 04/06/2026 | Post-installed Anchors | — | special |
| 04/06/2026 | Excavations - Sheeting, Shoring, and Bracing | — | special |
| 03/05/2026 | HVAC-R and service water heating equipment | — | energy_progress |
| 03/05/2026 | HVAC-R and service water piping design and insulation | — | energy_progress |
| 03/05/2026 | Maintenance information | — | energy_progress |
| 03/05/2026 | Fire-Resistant Penetrations and Joints | — | special |
| 03/05/2026 | Energy Code Compliance Inspections | — | progress |
| 03/05/2026 | HVAC-R and service water heating system controls | — | energy_progress |
| 11/22/2025 | Maintenance information | — | energy_progress |