1931Year Built
1Stories
F5Building Class
M1-5/R8AZoning
5,316 sfGross Floor Area
2Units
Factory, light manufacturing · Owner of record: 122 BRUCKNER PARTNERS LLC · 8,700 sf lot · 0.61 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralGeneralOther
Roof6p · 1 filing · 17 docs
Bulkhead3p · 1 filing · 17 docs
Floor 241p · 1 filing · 17 docs
Floor 23
Floor 22
Floor 21
Floor 20
Floor 19
Floor 18
Floor 17
Floor 16
Floor 15
Floor 144p · 1 filing · 17 docs
Floor 134p · 1 filing · 17 docs
Floor 125p · 1 filing · 17 docs
Floor 113p · 1 filing · 17 docs
Floor 105p · 1 filing · 17 docs
Floor 96p · 1 filing · 17 docs
Floor 86p · 1 filing · 17 docs
Floor 76p · 1 filing · 17 docs
Floor 66p · 1 filing · 17 docs
Floor 56p · 1 filing · 17 docs
Floor 46p · 1 filing · 17 docs
Floor 35p · 1 filing · 17 docs
Floor 25p · 1 filing · 17 docs
Floor 17p · 1 filing · 17 docs
Cellar7p · 1 filing · 17 docs
1 job · most recent 12/17/2025
General Wiring
FiledStatusContractorScope
12/17/2025Permit IssuedHIVOLTS ELECTRICAL INCGeneral Wiring
1 job · most recent 07/16/2026
Concrete
FiledStatusContractorScope
07/16/2026——Concrete
Building Lifecycle
All (28)Filed (5)Objection (3)Special Inspection (20)
07/16/2026
Filed — New Building
SOE FILED IN CONJUNCTION WITH NB X01338741-I1.
X01338741-S8
06/06/2026
Objection raised — Other
06/06/2026
Objection raised — Other
06/02/2026
Objection raised — Other
05/15/2026
Filed — New Building
SOE FILED IN CONJUNCTION WITH NB X01338741-I1.
X01338741-S5
05/13/2026
Filed — New Building
SOE FILED IN CONJUNCTION WITH NB X01338741-I1.
X01338741-S7
05/13/2026
Filed — New Building
SOE FILED IN CONJUNCTION WITH NB X01338741-I1.
X01338741-S6
05/13/2026
Special inspection requirement — Construction Operations Influencing Adjacent Structures
05/13/2026
Special inspection requirement — Concrete - Cast-In-Place
05/13/2026
Special inspection requirement — Masonry
05/13/2026
Special inspection requirement — Post-installed Anchors
05/13/2026
Special inspection requirement — Construction Operations Influencing Adjacent Structures
05/13/2026
Special inspection requirement — Concrete - Cast-In-Place
05/13/2026
Special inspection requirement — Subsurface Conditions – Fill Placement & In-Place Density
05/13/2026
Special inspection requirement — Subgrade Inspections
04/27/2026
Filed — New Building
SOE FILED IN CONJUNCTION WITH NB X01338741-I1.
X01338741-I1
04/27/2026
Special inspection requirement — Footing and Foundation
04/27/2026
Special inspection requirement — Final
04/27/2026
Special inspection requirement — Final
03/25/2026
Special inspection requirement — Fenestration areas
03/25/2026
Special inspection requirement — Air barrier - visual inspection
03/25/2026
Special inspection requirement — Insulation placement and R values
03/25/2026
Special inspection requirement — Fenestration air leakage
03/25/2026
Special inspection requirement — Wall Panels, Curtain Walls, and Veneers
03/25/2026
Special inspection requirement — Masonry
03/25/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
03/25/2026
Special inspection requirement — Exterior Insulation and Finish Systems (EIFS)
03/25/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
ARTIST CONSTRUCTION209/15/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
S. WIEDER ARCHITECT P.C.207/16/2026
FNA ENGINEERING SERVICES PC105/15/2026
ELEVATED ENGINEERING NYC205/13/2026
Nothing on file for this building.
▾Special Inspection Requirements (DOB NOW) — 20
DateRequirementInspectorRole
05/13/2026Construction Operations Influencing Adjacent Structures—special
05/13/2026Concrete - Cast-In-Place—special
05/13/2026Masonry—special
05/13/2026Post-installed Anchors—special
05/13/2026Construction Operations Influencing Adjacent Structures—special
05/13/2026Concrete - Cast-In-Place—special
05/13/2026Subsurface Conditions – Fill Placement & In-Place Density—special
05/13/2026Subgrade Inspections—special
04/27/2026Footing and Foundation—progress
04/27/2026Final—progress
04/27/2026Final—progress
03/25/2026Fenestration areas—energy_progress
03/25/2026Air barrier - visual inspection—energy_progress
03/25/2026Insulation placement and R values—energy_progress
03/25/2026Fenestration air leakage—energy_progress
03/25/2026Wall Panels, Curtain Walls, and Veneers—special
03/25/2026Masonry—special
03/25/2026Fire-Resistant Penetrations and Joints—special
03/25/2026Exterior Insulation and Finish Systems (EIFS)—special
03/25/2026Fenestration and door U-factor and product ratings—energy_progress
▾Documents — 17 on file (BIS + DOB NOW)
▸Plans & Drawings5
▸DOB NOWPlans/Sketch5
08/16/2026X01338741-S5Request digital key ↗
08/16/2026X01338741-S8Request digital key ↗
08/15/2026X01338741-I1Request digital key ↗
Showing 3 of 5 on file for this type
▸Zoning, Tax Lot & Property Records3
▸DOB NOWZD1: DOB Zoning Diagram1
08/15/2026X01338741-I1Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/15/2026X01338741-I1Open ↗
▸DOB NOWZoning Exhibit form (1-5)1
08/15/2026X01338741-I1Open ↗
▸Seals & Professional Certifications5
▸DOB NOWDPL-1: Design Professional Seal & Signature5
08/16/2026X01338741-I1Open ↗
08/16/2026X01338741-S8Open ↗
08/16/2026X01338741-S7Open ↗
Showing 3 of 5 on file for this type
▸Safety & Tenant Protection1
▸DOB NOWStreet Tree Checklist1
08/15/2026X01338741-I1Open ↗
▸Other Documents3
▸DOB NOWProperty Ownership Certification1
08/15/2026X01338741-I1Open ↗
▸DOB NOWSite Survey: Initial1
08/15/2026X01338741-I1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone1
08/15/2026X01338741-I1Open ↗