← Back
Three families
783 DAWSON STREET
BRONX · BIN 2005325
💬 Discuss this project
1901Year Built
2Stories
C0Building Class
R7-1Zoning
2,880 sfGross Floor Area
3Units
Rent Stabilized10 Open Violations 5 unresolved · 5 paperwork only ▸
Three families · Owner of record: 783 DAWSON LLC · 2,500 sf lot · 1.15 FAR built · Flood zone X
Locations of Work
ArchitecturePlumbing
Permit Issued — active, not yet Signed-off
Floor 2Under Construction3p · 1 filing · 2 docs
Floor 1Under Construction3p · 1 filing · 2 docs
CellarUnder Construction4p · 1 filing · 2 docs
Sub-BasementUnder Construction3p · 1 filing · 2 docs
3 jobs · most recent 11/13/2025
General Wiring
FiledStatusContractorScope
11/13/2025Permit IssuedLEADER ELECTRIC CO., INCGeneral Wiring
02/08/2023Permit IssuedKJK ELECTRIC INCGeneral Wiring
10/18/2019Permit IssuedDENNISON ELECTRIC CORPGeneral Wiring
2 jobs · most recent 11/02/2023
Fence
FiledStatusContractorScope
11/02/2023Permit IssuedLLNY GROUP,LLCFence
10/05/2018——Fence
Building Lifecycle
All (67)Filed (3)Permit Issued (2)Violation (45)Inspection (9)Objection (8)
09/09/2026
Inspection — Pass-Final PL - Underground
Pass
View inspection ↗
04/30/2026
Violation issued (HPD, closed)
A
04/21/2026
Inspection — Certified Storm Drainage-ST-Piping-Underground
Certified
View inspection ↗
04/21/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
04/03/2026
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
04/03/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
03/05/2026
Violation issued (ECB, open)
Construction
02/26/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
02/11/2026
Permit issued — Plumbing
X01344715-I1-PL
02/09/2026
Filed — Alteration
SUPERSEDE PLUMBING UNDER APPLICATION 240230790. THE FULL FILING FEE WAS PAID UNDER THE ORIGINAL APPLICATION.
X01344715-I1
08/07/2025
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
08/07/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
08/07/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
06/05/2025
Violation issued (HPD, closed)
A
11/26/2024
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
11/26/2024
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
11/22/2024
Violation issued (HPD, closed)
I
04/02/2024
Violation issued (HPD, closed)
A
12/20/2023
Permit issued — Construction Fence
X00955939-I1-FN
11/16/2023
Violation issued (HPD, closed)
I
11/16/2023
Objection resolved — Addressed
11/16/2023
Objection resolved — Addressed
11/16/2023
Objection resolved — Addressed
11/16/2023
Objection resolved — Addressed
11/09/2023
Objection raised — Structural
11/09/2023
Objection raised — Scope
11/09/2023
Objection raised — Structural
11/09/2023
Objection raised — Inspections
11/02/2023
Filed — Alteration
INSTALL TEMPORARY CONSTRUCTION FENCE FOR ALT-2 JOB WITH FACADE WORK.
X00955939-I1
10/25/2023
Violation issued (ECB, open)
Construction
10/25/2023
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
03/31/2023
Violation issued (ECB, open)
Construction
03/25/2023
Violation issued (ECB, open)
Construction
03/25/2023
Violation issued (ECB, closed)
Construction
03/16/2023
Violation issued (HPD, closed)
A
11/03/2022
Violation issued (HPD, closed)
I
03/16/2022
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
02/24/2022
Violation issued (ECB, closed)
Construction
02/17/2022
Violation issued (HPD, closed)
I
02/17/2022
Violation issued (HPD, closed)
A
01/19/2022
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
12/20/2021
Violation issued (ECB, closed)
Construction
12/07/2021
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
12/07/2021
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
10/28/2021
Violation issued (ECB, closed)
Construction
04/02/2021
Violation issued (HPD, closed)
A
04/02/2021
Violation issued (HPD, closed)
I
06/30/2020
Violation issued (ECB, open)
Construction
10/25/2019
Violation issued (HPD, closed)
I
08/27/2019
Violation issued (ECB, closed)
Construction
10/10/2018
Violation issued (HPD, closed)
I
10/05/2018
Filed — Alteration
INSTALL TEMPORARY 8-FEET HIGH CONSTRUCTION FENCE IN CONJUNCTION WITH DOB ALT 2 APPLICATION #240230790
X00082528-I1
11/13/2017
Violation issued (HPD, closed)
I
10/28/2016
Violation issued (HPD, closed)
I
10/02/2015
Violation issued (HPD, closed)
I
02/04/2015
Violation issued (HPD, closed)
I
12/03/2014
Violation issued (HPD, closed)
C
02/10/2014
Violation issued (HPD, closed)
C
02/10/2014
Violation issued (HPD, closed)
C
02/10/2014
Violation issued (HPD, closed)
C
Latest 60 of 67 events.
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
DEAN RESIDENCE 751 LLC503/22/2026
783 DAWSON1003/22/2026
PM MECHANICAL GROUP103/22/2026
KJK ELECTRIC INC103/22/2026
718 DEVELOPMENT GROUP203/21/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
09/08/2025$1.8M—783 DAWSON LLC → BRONX RISE LLC$619/sf building
09/08/2017$150K—Private party → 783 DAWSON LLC$52/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
NEW YORK ENGINEERING ASSOC., P.C.102/09/2026
THOMAS C. TUNG, P.E.111/02/2023
L & C ASSOCIATES110/05/2018
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
FIVE BORO CONSULTING EXPEDITING203/21/2026
NEW YORK ENGINEERING103/21/2026
WM ARCH203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
LLNY GROUP,LLCGeneral Contractor303/21/2026
BENJAMIN BELOTElectrical103/21/2026
DENNISON ELECTRIC CORPElectrical103/22/2026
STEVEN DENNISONElectrical103/21/2026
TIDAL PLUMBING & HTG LLCPlumbing107/08/2026
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingPermit IssuedTIDAL PLUMBING & HTG LLC02/11/2026
DOB NOWConstruction FencePermit IssuedLLNY GROUP,LLC12/20/2023
BISOTISSUEDA & L CORNER STONE ASSOC02/18/2026
BISOTISSUEDPM MECHANICAL GROUP CORP09/25/2023
BISMHISSUEDPM MECHANICAL GROUP CORP09/20/2023
BISPLISSUEDTRI CITY MECHANICAL GROUP CORP09/11/2023
BISOTISSUEDPM MECHANICAL GROUP CORP07/16/2021
BISPLISSUEDTRI CITY MECHANICAL GROUP CORP06/18/2020
BISOTISSUEDPM MECHANICAL GROUP CORP06/09/2020
BISOTISSUEDPM MECHANICAL GROUP CORP04/01/2019
BISOTISSUEDPM MECHANICAL GROUP CORP08/24/2018
BISPLISSUEDMEJ PLUMBING LLC08/03/2018
▾Field Inspections (DOB CAP) — 9
DateTypeResultReport
09/09/2026Pass-Final PL - UndergroundPassView ↗
04/21/2026Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
04/21/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
04/03/2026Certified Gas-Gas-Piping-RoughingCertifiedView ↗
04/03/2026Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
02/26/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
08/07/2025Certified Gas-Gas-Piping-RoughingCertifiedView ↗
08/07/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
08/07/2025Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Documents — 48 on file (BIS + DOB NOW)
▸Plans & Drawings3
▸DOB NOWPlans/Sketch3
08/26/2026X00082528-I1Request digital key ↗
08/22/2026X00955939-I1Request digital key ↗
08/17/2026X01344715-I1Request digital key ↗
▸Applications & Permits19
▸BISPLAN / WORK APPROVAL APPLICATION11
11/28/2025240230790Open ↗
11/25/2025240230790Open ↗
11/14/2025240230790Open ↗
Showing 3 of 11 on file for this type
▸BISWORK PERMIT APPLICATION8
09/26/2023240230790Open ↗
09/22/2023240230790Open ↗
09/13/2023240230790Open ↗
Showing 3 of 8 on file for this type
▸Seals & Professional Certifications8
▸DOB NOWDPL-1: Design Professional Seal & Signature3
08/26/2026X00082528-I1Open ↗
08/22/2026X00955939-I1Open ↗
08/13/2026X01344715-I1Open ↗
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION2
03/24/2020240230790Open ↗
02/20/2020240230790Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
07/27/2018240230790Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
07/27/2018240230790Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
07/27/2018240230790Open ↗
▸Trade Schedules & Equipment1
▸BISSCHEDULE B - PLUMBING1
07/27/2018240230790Open ↗
▸Environmental & Asbestos1
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
07/27/2018240230790Open ↗
▸Energy Compliance3
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY2
08/03/2018240230790Open ↗
07/27/2018240230790Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
07/27/2018240230790Open ↗
▸Inspections & Test Reports2
▸BISTECHNICAL REPORT: RESPONSIBILITY2
08/03/2018240230790Open ↗
07/27/2018240230790Open ↗
▸Approvals, Objections & Sign-offs2
▸BISSUPERSEDING LETTER1
06/18/2020240230790Open ↗
▸BISLANDMARKS APPROVAL1
07/27/2018240230790Open ↗
▸Cost, Insurance & Ownership1
▸BISCOST AFFIDAVIT1
07/27/2018240230790Open ↗
▸Filing & Intake Forms8
▸BISBOROUGH INTAKE FORM4
09/26/2023240230790Open ↗
09/13/2023240230790Open ↗
05/05/2023240230790Open ↗
Showing 3 of 4 on file for this type
▸BISADDITIONAL INFORMATION3
11/28/2025240230790Open ↗
10/01/2020240230790Open ↗
03/24/2020240230790Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
07/27/2018240230790Open ↗