| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/14/2026 | — | — | Steel, Concrete, Masonry |
| Owner | Filings | Most Recent |
|---|---|---|
| L R G CONTRACTORS | 1 | 09/01/2026 |
| 1300 SOUTHERN BLVD INC | 3 | 03/22/2026 |
| SOUTHERN BLVD, LLC. 1300 | 1 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| BADALY ARCHITECTS | 4 | 08/20/2026 |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/18/2026 | Structural Stability – Alterations of existing Buildings | — | special |
| 08/18/2026 | Demolition | — | special |
| 06/23/2026 | Energy Code Compliance Inspections | — | progress |
| 06/23/2026 | Fire-Resistance Rated Construction | — | progress |
| 06/23/2026 | Lighting controls | — | energy_progress |
| 06/23/2026 | Electrical motors and elevators | — | energy_progress |
| 06/23/2026 | Fenestration areas | — | energy_progress |
| 06/23/2026 | Air barrier - visual inspection | — | energy_progress |
| 06/23/2026 | Exterior lighting power | — | energy_progress |
| 06/23/2026 | Lighting in dwelling units | — | energy_progress |
| 06/23/2026 | Insulation placement and R values | — | energy_progress |
| 06/23/2026 | Maintenance information | — | energy_progress |
| 06/23/2026 | Interior lighting power | — | energy_progress |
| 06/23/2026 | Fenestration air leakage | — | energy_progress |
| 06/23/2026 | Air barrier — testing | — | energy_progress |
| 06/23/2026 | Metering | — | energy_progress |
| 06/23/2026 | Protection of exposed foundation insulation | — | energy_progress |
| 06/23/2026 | Fenestration and door U-factor and product ratings | — | energy_progress |
| 06/23/2026 | Vestibules | — | energy_progress |
| 06/23/2026 | Concrete - Cast-In-Place | — | special |
| 06/23/2026 | Subgrade Inspections | — | special |
| 06/23/2026 | Subsurface Investigations (Borings/Test Pits) | — | special |
| 06/23/2026 | Final | — | progress |
| 06/23/2026 | Fire-Resistant Penetrations and Joints | — | special |
| 06/23/2026 | Footing and Foundation | — | progress |