| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/01/2021 | Permit Issued | AMPERE ELECL SERVICES COR | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/10/2026 | — | — | Steel, Concrete, Masonry |
| Owner | Filings | Most Recent |
|---|---|---|
| FRS CONSTRUCTION | 12 | 04/09/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| BADALY ARCHITECTS | 3 | 03/10/2026 |
| RMM DESIGN STUDIO | 1 | 10/22/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| KC EXPEDITING | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| DANIEL YOMTOBIAN CORP | General Contractor | 1 | 03/21/2026 |
| FRSS GROUP CORP | General Contractor | 1 | 04/09/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Construction Fence | Permit Issued | FRSS GROUP | 10/22/2025 |
| BIS | OT | ISSUED | DANIEL YOMTOBIAN CORP | 11/29/2021 |
| Date | Type | Result | Report |
|---|---|---|---|
| 02/13/2026 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 06/26/2026 | Subsurface Investigations (Borings/Test Pits) | — | special |
| 03/03/2026 | Subgrade Inspections | — | special |
| 03/03/2026 | Final | — | progress |
| 03/03/2026 | Footing and Foundation | JEFFREY BELL | progress |
| 03/03/2026 | Fire-Resistant Penetrations and Joints | — | special |
| 03/03/2026 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | — | special |
| 03/03/2026 | Energy Code Compliance Inspections | — | progress |
| 03/03/2026 | Fire-Resistance Rated Construction | — | progress |
| 03/03/2026 | Maintenance information | — | energy_progress |
| 03/03/2026 | Vestibules | — | energy_progress |
| 03/03/2026 | Interior lighting power | — | energy_progress |
| 03/03/2026 | Lighting controls | — | energy_progress |
| 03/03/2026 | Air barrier - visual inspection | — | energy_progress |
| 03/03/2026 | Metering | — | energy_progress |
| 03/03/2026 | Lighting in dwelling units | — | energy_progress |
| 03/03/2026 | Fenestration air leakage | — | energy_progress |
| 03/03/2026 | Air barrier — testing | — | energy_progress |
| 03/03/2026 | Fenestration and door U-factor and product ratings | — | energy_progress |
| 03/03/2026 | Electrical motors and elevators | — | energy_progress |
| 03/03/2026 | Fenestration areas | — | energy_progress |
| 03/03/2026 | Insulation placement and R values | — | energy_progress |
| 03/03/2026 | Protection of exposed foundation insulation | — | energy_progress |
| 03/03/2026 | Concrete - Cast-In-Place | — | special |
| 03/03/2026 | Exterior lighting power | — | energy_progress |