Electrical
Roof1 filing · 6 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
JAMES A CLANCY106/17/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
ARC DESIGN AND CONSULTING LLC203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
RIVERTOWN SOLAR LLCGeneral Contractor303/21/2026
AMBER ELECTL CONTNG INCElectrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
JAMES A CLANCY9176106/17/2025
Building Lifecycle
All (7)Filed (1)Permit Issued (1)Special Inspection (5)
06/24/2025
Permit issued — Solar
X01241575-I1-SL
06/17/2025
Filed — Alteration
Installation of PV System on existing roof top. No changes to the use egress or occupancy.
X01241575-I1
06/15/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
James Clancy
06/15/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
James Clancy
06/15/2025
Special inspection requirement — Energy Code Compliance Inspections
James Clancy
06/15/2025
Special inspection requirement — Final
James Clancy
06/15/2025
Special inspection requirement — Air barrier - visual inspection
James Clancy
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarPermit IssuedRIVERTOWN SOLAR LLC06/24/2025
1 project · most recent 06/12/2025
FiledStatusContractorScope
06/12/2025CompleteAMBER ELECTL CONTNG INC—
1 project · most recent 06/17/2025
FiledStatusContractorScope
06/17/2025Permit IssuedRIVERTOWN SOLAR LLC8 panels, 4.44 kw, 222.48 roof_area_sqft
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
06/15/2025Fire-Resistant Penetrations and JointsJames Clancyspecial
06/15/2025Structural Stability – Alterations of existing buildingsJames Clancyspecial
06/15/2025Energy Code Compliance InspectionsJames Clancyprogress
06/15/2025FinalJames Clancyprogress
06/15/2025Air barrier - visual inspectionJames Clancyenergy_progress
▾Documents — 6 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/19/2026X01241575-I1Request digital key ↗
▸Seals & Professional Certifications4
▸DOB NOWProgress Inspector Seal & Signature2
08/22/2026X01241575-I1Open ↗
08/22/2026X01241575-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/19/2026X01241575-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
08/22/2026X01241575-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/19/2026X01241575-I1Open ↗