← Back
Two family frame
1661 GARFIELD STREET
BRONX · BIN 2042775
💬 Discuss this project
1899Year Built
2Stories
B2Building Class
R5Zoning
2,116 sfGross Floor Area
2Units
1 Open Violation 0 unresolved · 1 paperwork only ▸
Two family frame · 2,500 sf lot · 0.85 FAR built · Flood zone X
Locations of Work
Architecture
Floor 21p · 1 filing · 8 docs
Floor 1
Cellar1p · 1 filing · 8 docs
2 jobs · most recent 10/31/2024
General Wiring
FiledStatusContractorScope
10/31/2024CompleteAMOR ELECTRIC CORPGeneral Wiring
11/23/2018CompleteACE ELEC'L CONSTRUCTION—
Building Lifecycle
All (44)Filed (4)Permit Issued (3)Signed Off (3)Violation (2)Inspection (4)Objection (10)Special Inspection (18)
02/25/2026
Signed off — Alteration
Repair and replace all fire/water damaged building components at the rear portion of the dwelling at second and roof areas as per plans submitted here in. No change to use, egress or occupancy.
X01016957-I1
02/02/2026
Signed off — Alteration
plumbing renovation on cellar thru second floor.
X01080039-I1
02/02/2026
Signed off — Alteration
plumbing renovation on cellar thru second floor.
X01080039-S1
12/19/2025
Permit issued — Mechanical Systems
X01080039-S1-MS
11/22/2025
Objection resolved — Addressed
11/22/2025
Objection resolved — Addressed
11/22/2025
Objection resolved — Addressed
09/24/2025
Filed — Alteration
Repair and replace all fire/water damaged building components at the rear portion of the dwelling at second and roof areas as per plans submitted here in. No change to use, egress or occupancy.
X01016957-P1
09/24/2025
Special inspection requirement — Insulation placement and R values
Hackjong Choi
09/24/2025
Special inspection requirement — Final
Hackjong Choi
09/24/2025
Special inspection requirement — Fire-Resistance Rated Construction
Hackjong Choi
09/24/2025
Special inspection requirement — Fenestration areas
Hackjong Choi
09/24/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
Hackjong Choi
09/24/2025
Special inspection requirement — Air barrier - visual inspection
Hackjong Choi
09/24/2025
Special inspection requirement — Interior lighting power
Hackjong Choi
09/24/2025
Special inspection requirement — Fenestration air leakage
Hackjong Choi
09/24/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Hackjong Choi
09/24/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
Hackjong Choi
09/24/2025
Special inspection requirement — Energy Code Compliance Inspections
Hackjong Choi
04/18/2025
Objection raised — Mechanical
04/18/2025
Objection raised — Cost
04/18/2025
Objection raised — Zoning
04/14/2025
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
04/10/2025
Filed — Alteration
plumbing renovation on cellar thru second floor.
X01080039-S1
10/17/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
09/19/2024
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
09/19/2024
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
09/05/2024
Permit issued — Plumbing
X01080039-I1-PL
08/21/2024
Objection resolved — Addressed
08/21/2024
Objection resolved — Addressed
08/21/2024
Special inspection requirement — HVAC-R and service water heating equipment
Hackjong Choi
08/21/2024
Special inspection requirement — HVAC-R and service water heating system controls
Hackjong Choi
08/21/2024
Special inspection requirement — Maintenance information
Hackjong Choi
08/21/2024
Special inspection requirement — HVAC-R and service water piping design and insulation
Hackjong Choi
08/09/2024
Objection raised — Other
08/09/2024
Objection raised — Other
07/12/2024
Filed — Alteration
plumbing renovation on cellar thru second floor.
X01080039-I1
07/12/2024
Special inspection requirement — Mechanical Systems
Hackjong Choi
07/12/2024
Special inspection requirement — Final
Hackjong Choi
07/12/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
Hackjong Choi
06/24/2024
Permit issued — General Construction
X01016957-I1-GC
03/14/2024
Filed — Alteration
Repair and replace all fire/water damaged building components at the rear portion of the dwelling at second and roof areas as per plans submitted here in. No change to use, egress or occupancy.
X01016957-I1
02/21/2006
Violation issued (ECB, closed)
Quality of Life
02/21/2006
Violation issued (ECB, open)
Quality of Life
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
HC ARCHITECT, PC409/24/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
CH CORNERSTONE DESIGN403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
AN AMERICAN COMPANY, INCGeneral Contractor404/09/2026
INFINITI ESC PLUMBING CORPlumbing407/08/2026
JEANNETTE GONZALEZElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
BEYOND ARCH LLC3600409/24/2025
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsSigned-offAN AMERICAN COMPANY, INC12/19/2025
DOB NOWPlumbingSigned-offINFINITI ESC PLUMBING COR09/05/2024
DOB NOWGeneral ConstructionSigned-offAN AMERICAN COMPANY, INC06/24/2024
BISOTISSUEDAMERGY SOLAR INC10/24/2018
▾Field Inspections (DOB CAP) — 4
DateTypeResultReport
04/14/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
10/17/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
09/19/2024Certified Gas-Gas-Piping-RoughingCertifiedView ↗
09/19/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 18
DateRequirementInspectorRole
09/24/2025Insulation placement and R valuesHackjong Choienergy_progress
09/24/2025FinalHackjong Choiprogress
09/24/2025Fire-Resistance Rated ConstructionHackjong Choiprogress
09/24/2025Fenestration areasHackjong Choienergy_progress
09/24/2025Fenestration and door U-factor and product ratingsHackjong Choienergy_progress
09/24/2025Air barrier - visual inspectionHackjong Choienergy_progress
09/24/2025Interior lighting powerHackjong Choienergy_progress
09/24/2025Fenestration air leakageHackjong Choienergy_progress
09/24/2025Fire-Resistant Penetrations and JointsHackjong Choispecial
09/24/2025Structural Stability – Alterations of existing buildingsHackjong Choispecial
09/24/2025Energy Code Compliance InspectionsHackjong Choiprogress
08/21/2024HVAC-R and service water heating equipmentHackjong Choienergy_progress
08/21/2024HVAC-R and service water heating system controlsHackjong Choienergy_progress
08/21/2024Maintenance informationHackjong Choienergy_progress
08/21/2024HVAC-R and service water piping design and insulationHackjong Choienergy_progress
07/12/2024Mechanical SystemsHackjong Choispecial
07/12/2024FinalHackjong Choiprogress
07/12/2024Fire-Resistant Penetrations and JointsHackjong Choispecial
▾Documents — 37 on file (BIS + DOB NOW)
▸Plans & Drawings4
▸DOB NOWPlans/Sketch4
08/21/2026X01016957-I1Contact architect ↗
08/21/2026X01016957-P1Contact architect ↗
08/21/2026X01080039-S1Contact architect ↗
Showing 3 of 4 on file for this type
▸Applications & Permits2
▸BISPLAN / WORK APPROVAL APPLICATION1
10/23/2018240241216Open ↗
▸BISWORK PERMIT APPLICATION1
10/24/2018240241216Open ↗
▸Zoning, Tax Lot & Property Records1
▸DOB NOWRestrictive Declaration/Easement 11
08/13/2026X01080039-I1Open ↗
▸Seals & Professional Certifications12
▸DOB NOWDPL-1: Design Professional Seal & Signature4
08/21/2026X01016957-I1Open ↗
08/21/2026X01016957-P1Open ↗
08/21/2026X01080039-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWProgress Inspector Seal & Signature4
09/02/2026X01080039-S1Open ↗
09/01/2026X01080039-I1Open ↗
08/23/2026X01016957-P1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature3
09/02/2026X01080039-S1Open ↗
09/01/2026X01080039-I1Open ↗
08/23/2026X01016957-P1Open ↗
▸BISAPPLICANT OWNER SIGNATURE1
10/23/2018240241216Open ↗
▸Safety & Tenant Protection1
▸BISTENANT PROTECTION PLAN AND NOTES1
10/23/2018240241216Open ↗
▸Environmental & Asbestos4
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form3
08/21/2026X01016957-I1Open ↗
08/21/2026X01080039-I1Open ↗
08/21/2026X01080039-S1Open ↗
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
10/23/2018240241216Open ↗
▸Energy Compliance5
▸BISSOLAR TAX ABATEMENT APPLICATION2
02/11/2019240241216Open ↗
10/23/2018240241216Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY2
02/11/2019240241216Open ↗
10/23/2018240241216Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
02/11/2019240241216Open ↗
▸Inspections & Test Reports2
▸BISTECHNICAL REPORT: RESPONSIBILITY2
02/11/2019240241216Open ↗
10/23/2018240241216Open ↗
▸Approvals, Objections & Sign-offs3
▸BISLETTERS - SUPPORTING DOCUMENTATION1
10/23/2018240241216Open ↗
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
02/11/2019240241216Open ↗
▸BISUtility Company PV System Interconnection Acknowledgement Letter1
02/11/2019240241216Open ↗
▸Cost, Insurance & Ownership2
▸BISCOST AFFIDAVIT2
02/11/2019240241216Open ↗
10/23/2018240241216Open ↗
▸Filing & Intake Forms1
▸BISEFILING JOB APPLICATION COVER SHEET1
10/23/2018240241216Open ↗