| Owner | Filings | Most Recent |
|---|---|---|
| AV GROUP | 11 | 09/25/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| BADALY ARCHITECTS | 7 | 08/17/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| ZEFI & CO. LLC | General Contractor | 3 | 09/25/2026 |
| MALEK & RAKSHAN ASS | General Contractor | 1 | 07/14/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Foundation | Permit Issued | ZEFI & CO. LLC | 09/24/2026 |
| DOB NOW | Full Demolition | Signed-off | ZEFI & CO. LLC | 05/26/2026 |
| DOB NOW | Construction Fence | Signed-off | ZEFI & CO. LLC | 05/14/2026 |
| DOB NOW | Construction Fence | Signed-off | MALEK & RAKSHAN ASS | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/17/2026 | Permit Issued | ZEFI & CO. LLC | 1 scope_items |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/17/2026 | Permit Issued | ZEFI & CO. LLC | Fence |
| 03/26/2026 | Signed-off | ZEFI & CO. LLC | Fence |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/30/2026 | Fire-Resistant Penetrations and Joints | — | special |
| 07/30/2026 | HVAC-R and service water piping design and insulation | — | energy_progress |
| 07/30/2026 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | — | special |
| 04/15/2026 | Concrete - Cast-In-Place | — | special |
| 04/15/2026 | Subgrade Inspections | — | special |
| 04/15/2026 | Subsurface Investigations (Borings/Test Pits) | — | special |
| 03/12/2026 | Demolition | MOHAMMAD BADALY | special |
| 01/16/2026 | Sprinkler Systems | — | special |
| 01/16/2026 | Footing and Foundation | — | progress |
| 01/16/2026 | Final | — | progress |
| 01/12/2026 | Fenestration areas | — | energy_progress |
| 01/12/2026 | Exterior lighting power | — | energy_progress |
| 01/12/2026 | Lighting controls | — | energy_progress |
| 01/12/2026 | Fire-Resistant Penetrations and Joints | — | special |
| 01/12/2026 | Lighting in dwelling units | — | energy_progress |
| 01/12/2026 | Insulation placement and R values | — | energy_progress |
| 01/12/2026 | Air barrier - visual inspection | — | energy_progress |
| 01/12/2026 | Metering | — | energy_progress |
| 01/12/2026 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | — | special |
| 01/12/2026 | Energy Code Compliance Inspections | — | progress |
| 01/12/2026 | Fire-Resistance Rated Construction | — | progress |
| 01/12/2026 | Fenestration air leakage | — | energy_progress |
| 01/12/2026 | Air barrier — testing | — | energy_progress |
| 01/12/2026 | Maintenance information | — | energy_progress |
| 01/12/2026 | Fenestration and door U-factor and product ratings | — | energy_progress |