← Back
Two family frame
2732 FISH AVENUE
BRONX · BIN 2054351
💬 Discuss this project
1925Year Built
2Stories
B2Building Class
R4Zoning
2,028 sfGross Floor Area
2Units
Two family frame · 5,000 sf lot · 0.41 FAR built · Flood zone X
Locations of Work
Electrical
Roof1 filing · 8 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
MOMENTUM SOLAR107/31/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
MXV SIA LLC9281107/31/2026
Building Lifecycle
All (9)Filed (1)Permit Issued (1)Special Inspection (7)
08/06/2026
Permit issued — Solar
X01439052-I1-SL
07/31/2026
Filed — Alteration
Installation of solar panels, rooftop, grid tied, railed, 14 modules, 5.74 KW
X01439052-I1
07/31/2026
Special inspection requirement — Post-installed Anchors
Mina Makar
07/31/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
Mina Makar
07/31/2026
Special inspection requirement — Air barrier - visual inspection
Mina Makar
07/31/2026
Special inspection requirement — Adhesive-Based Solar Pedestal Bonding Systems
Mina Makar
07/30/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Mina Makar
07/30/2026
Special inspection requirement — Energy Code Compliance Inspections
Mina Makar
07/30/2026
Special inspection requirement — Final
Mina Makar
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarPermit IssuedMOMENTUM SOLAR08/06/2026
1 project · most recent 07/31/2026
FiledStatusContractorScope
07/31/2026Permit IssuedISLAND ELECTRIC CORP—
1 project · most recent 07/31/2026
FiledStatusContractorScope
07/31/2026Permit IssuedMOMENTUM SOLAR28 panels, 11.48 kw, 5,000 roof_area_sqft
▾Special Inspection Requirements (DOB NOW) — 7
DateRequirementInspectorRole
07/31/2026Post-installed AnchorsMina Makarspecial
07/31/2026Structural Stability – Alterations of existing buildingsMina Makarspecial
07/31/2026Air barrier - visual inspectionMina Makarenergy_progress
07/31/2026Adhesive-Based Solar Pedestal Bonding SystemsMina Makarspecial
07/30/2026Fire-Resistant Penetrations and JointsMina Makarspecial
07/30/2026Energy Code Compliance InspectionsMina Makarprogress
07/30/2026FinalMina Makarprogress
▾Documents — 8 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/16/2026X01439052-I1Request digital key ↗
▸Seals & Professional Certifications6
▸DOB NOWSpecial Inspector Seal & Signature3
08/24/2026X01439052-I1Open ↗
08/24/2026X01439052-I1Open ↗
08/24/2026X01439052-I1Open ↗
▸DOB NOWProgress Inspector Seal & Signature2
08/24/2026X01439052-I1Open ↗
08/24/2026X01439052-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/16/2026X01439052-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/16/2026X01439052-I1Open ↗