← Back
Two family brick
738 EAST 239 STREET
BRONX · BIN 2070761
💬 Discuss this project
1960Year Built
2Stories
B1Building Class
R5Zoning
2,683 sfGross Floor Area
2Units
Two family brick · 2,150 sf lot · 1.25 FAR built · Flood zone X
Locations of Work
ArchitectureGeneral
Roof3p · 1 filing · 9 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
TOM PETERSEN ARCHITECT, LLC103/24/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
KCM PLUMBING & HEATING COPlumbing203/22/2026
CENTURION SOLAR ENERGYGeneral Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
THOMAS PETERSEN ARCHITECT7854103/24/2026
Building Lifecycle
All (13)Filed (1)Permit Issued (1)Signed Off (1)Objection (5)Special Inspection (5)
06/08/2026
Signed off — Alteration
SCOPE OF WORK IS SOLELY FOR THE INSTALLATION OF THE SOLAR ELECTRONIC GENERATING SYSTEM. ALL OTHER WORK IS NOT TO BE RELIED UPON AS BEING APPROVED AND/OR PERMITTED BY THE NYC DEPARTMENT OF BUILDINGS. NO CHANGE TO USE, EGRESS OROCCUPANCY.
X01371696-I1
06/04/2026
Permit issued — Solar
X01371696-I1-SL
04/09/2026
Objection raised — Other
04/09/2026
Objection raised — Other
04/09/2026
Objection raised — Inspections
04/09/2026
Objection raised — Other
04/09/2026
Objection raised — Electrical
03/24/2026
Filed — Alteration
SCOPE OF WORK IS SOLELY FOR THE INSTALLATION OF THE SOLAR ELECTRONIC GENERATING SYSTEM. ALL OTHER WORK IS NOT TO BE RELIED UPON AS BEING APPROVED AND/OR PERMITTED BY THE NYC DEPARTMENT OF BUILDINGS. NO CHANGE TO USE, EGRESS OROCCUPANCY.
X01371696-I1
03/13/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
TOM PETERSEN
03/13/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
TOM PETERSEN
03/13/2026
Special inspection requirement — Energy Code Compliance Inspections
TOM PETERSEN
03/13/2026
Special inspection requirement — Final
TOM PETERSEN
03/13/2026
Special inspection requirement — Air barrier - visual inspection
TOM PETERSEN
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offCENTURION SOLAR ENERGY06/04/2026
BISOTISSUEDCENTURION SOLAR ENERGY08/14/2023
1 project · most recent 08/16/2023
FiledStatusContractorScope
08/16/2023CompleteBERGER QUALITY ELEC'L CON—
1 project · most recent 03/24/2026
FiledStatusContractorScope
03/24/2026Signed-offCENTURION SOLAR ENERGY15 panels, 6 kw, 288.83 roof_area_sqft
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
03/13/2026Fire-Resistant Penetrations and JointsTOM PETERSENspecial
03/13/2026Structural Stability – Alterations of existing buildingsTOM PETERSENspecial
03/13/2026Energy Code Compliance InspectionsTOM PETERSENprogress
03/13/2026FinalTOM PETERSENprogress
03/13/2026Air barrier - visual inspectionTOM PETERSENenergy_progress
▾Documents — 23 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/17/2026X01371696-I1Request digital key ↗
▸Applications & Permits3
▸BISPLAN / WORK APPROVAL APPLICATION2
04/03/2024240352765Open ↗
08/10/2023240352765Open ↗
▸BISWORK PERMIT APPLICATION1
08/14/2023240352765Open ↗
▸Seals & Professional Certifications7
▸DOB NOWProgress Inspector Seal & Signature3
09/01/2026X01371696-I1Open ↗
09/01/2026X01371696-I1Open ↗
09/01/2026X01371696-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
09/01/2026X01371696-I1Open ↗
09/01/2026X01371696-I1Open ↗
▸BISAPPLICANT OWNER SIGNATURE1
08/10/2023240352765Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/17/2026X01371696-I1Open ↗
▸Safety & Tenant Protection1
▸BISTPP1: TENANT PROTECTION PLAN1
08/14/2023240352765Open ↗
▸Environmental & Asbestos2
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
08/10/2023240352765Open ↗
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/17/2026X01371696-I1Open ↗
▸Energy Compliance3
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY2
08/10/2023240352765Open ↗
08/10/2023240352765Open ↗
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (PRELIMINARY)1
08/10/2023240352765Open ↗
▸Inspections & Test Reports2
▸BISTECHNICAL REPORT: RESPONSIBILITY2
08/10/2023240352765Open ↗
08/10/2023240352765Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/17/2026X01371696-I1Open ↗
▸Cost, Insurance & Ownership1
▸BISCOST AFFIDAVIT1
08/10/2023240352765Open ↗
▸Filing & Intake Forms1
▸BISEFILING JOB APPLICATION COVER SHEET1
08/10/2023240352765Open ↗
▸Other Documents1
▸BISCONSTRUCTION - SUPPORTING DOCUMENTATION1
08/10/2023240352765Open ↗