| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/27/2026 | — | — | Wood |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 08/22/2025 | $840K | — | — → Private party | $423/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| AAAA CONSULTING CORP. | 1 | 08/27/2026 |
| CHK PLUS INC | 1 | 09/19/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| ARC-HI-TECT ASSOCIATE | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| PADMA CONTRACTING CORP | General Contractor | 1 | 04/09/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| ARC-HI-TECH ASSOCIATES IN | 6963 | 1 | 09/19/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | PADMA CONTRACTING CORP | 11/18/2025 |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/24/2026 | Wood – Seismic Resistance | — | special |
| 08/24/2026 | Exterior Insulation and Finish Systems (EIFS) | Mohammad Islam | special |
| 08/24/2026 | Fire-Resistant Penetrations and Joints | — | special |
| 08/24/2026 | Structural Stability – Alterations of existing buildings | — | special |
| 08/24/2026 | Tenant Protection Plan Compliance | — | special |
| 08/24/2026 | Maintenance information | — | energy_progress |
| 08/24/2026 | Fenestration and door U-factor and product ratings | — | energy_progress |
| 08/24/2026 | Insulation placement and R values | — | energy_progress |
| 08/24/2026 | Air barrier - visual inspection | — | energy_progress |
| 08/24/2026 | Lighting in dwelling units | — | energy_progress |
| 08/24/2026 | Fenestration air leakage | — | energy_progress |
| 07/30/2026 | Final | Mohammad Islam | progress |
| 07/30/2026 | Footing and Foundation | Mohammad Islam | progress |