| Owner | Filings | Most Recent |
|---|---|---|
| GALAXY GEN CONTRACTING | 15 | 07/08/2026 |
| 752 LOGAN AVENUE | 5 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 05/22/2024 | $949K | — | 752 LOGAN AVENUE LLC → Private party | $455/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| PARKER AND WEST ENGINEERING, PLLC | 1 | 10/22/2025 |
| GEORGIOS G GEORGOPOULOS, R.A. | 4 | 06/20/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| SUNRUN | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| GALAXY GENERAL CONTRACTIN | General Contractor | 5 | 07/08/2026 |
| AJC PLUMBING & HTG CORP | Plumbing | 3 | 07/08/2026 |
| SUNRUN INSTALLATION SVC | General Contractor | 1 | 04/09/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| PARKER AND WEST ENGINEERI | 5272 | 1 | 10/22/2025 |
| H2 CONSULTING PE PC | 835 | 2 | 06/20/2023 |
| GEORGIOS G. GEORGOPOULOS, | 1192 | 3 | 06/01/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Solar | Signed-off | SUNRUN INSTALLATION SVC | 10/28/2025 |
| DOB NOW | Structural | Signed-off | GALAXY GENERAL CONTRACTIN | 07/14/2023 |
| DOB NOW | Plumbing | Signed-off | AJC PLUMBING & HTG CORP | 06/29/2023 |
| DOB NOW | General Construction | Signed-off | GALAXY GENERAL CONTRACTIN | 01/12/2023 |
| DOB NOW | General Construction | Signed-off | GALAXY GENERAL CONTRACTIN | 11/17/2021 |
| BIS | PL | ISSUED | DPH PLUMBING & HTG CORP | 03/29/2013 |
| BIS | — | ISSUED | GALAXY GENERAL CONSTRACTING CORP | 12/06/2012 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/22/2025 | Complete | SUNRUN SOLAR ELECTL CORP | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 01/29/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 01/25/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 01/25/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 08/29/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 08/28/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 08/09/2023 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 07/20/2023 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 10/21/2025 | Air barrier - visual inspection | Walid Abdulla | energy_progress |
| 10/21/2025 | Structural Stability – Alterations of existing buildings | Walid Abdulla | special |
| 10/21/2025 | Fire-Resistant Penetrations and Joints | Walid Abdulla | special |
| 10/21/2025 | Energy Code Compliance Inspections | Walid Abdulla | progress |
| 10/21/2025 | Final | Walid Abdulla | progress |
| 05/25/2023 | Fire-Resistant Penetrations and Joints | Georgios Georgopoulos | special |
| 03/30/2023 | Structural Stability – Alterations of existing buildings | — | special |
| 03/30/2023 | Energy Code Compliance Inspections | Georgios Georgopoulos | progress |
| 03/30/2023 | Fire-Resistance Rated Construction | Georgios Georgopoulos | progress |
| 03/30/2023 | Insulation placement and R values | Georgios Georgopoulos | energy_progress |
| 03/30/2023 | Air barrier - visual inspection | Georgios Georgopoulos | energy_progress |
| 03/30/2023 | Fenestration air leakage | Georgios Georgopoulos | energy_progress |
| 03/30/2023 | Fenestration and door U-factor and product ratings | Georgios Georgopoulos | energy_progress |
| 03/30/2023 | Fenestration areas | Georgios Georgopoulos | energy_progress |
| 03/30/2023 | Fire-Resistant Penetrations and Joints | Georgios Georgopoulos | special |
| 09/29/2022 | Final | Georgios Georgopoulos | progress |