← Back
One story retail building
2650 DAVIDSON AVENUE
BRONX · BIN 2094677
💬 Discuss this project
1930Year Built
1Stories
K1Building Class
R6Zoning
12,060 sfGross Floor Area
4Units
1 Open Violation 0 unresolved · 1 paperwork only ▸
One story retail building · Owner of record: DAITCH-KINGSBRIDGE, LLC · 12,850 sf lot · 0.94 FAR built · Flood zone X
Locations of Work
ArchitectureGeneral
Floor 11p · 1 filing · 4 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
JP 99 EXPRESS INC.903/22/2026
DAITCH KINGSBRIDGE LLC203/22/2026
LOGIL MANAGEMENT703/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
SKYPEAK LLC209/23/2025
SU ARCHITECT, P.C.204/26/2021
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
INSHA BUILDING CONSULTANTS403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
SPLEN CONSTRUCTION INCGeneral Contractor303/21/2026
WHITESTONE PLUMBING CORPPlumbing207/08/2026
GREENER COUNTYGeneral Contractor104/09/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
SU ARCHITECT PC6857204/26/2021
Building Lifecycle
All (45)Filed (4)Permit Issued (3)Signed Off (3)Violation (5)Inspection (8)Objection (12)Special Inspection (10)
12/08/2025
Signed off — Alteration
CONVERTING EX CORNER RETAIL SPACE USE GROUP#6 INTO (EATING & DRINKING ESTABLISHMENT) USE GROUP 6 WITH LESS THAN 74 OCCUPANCY LOAD. ALL WORK PREVIOUSLY DONE UNDER BIS JOB# 220700258 & JOB# X08040559. NO ADDITIONAL WORK TO BE DONE. EX PLANS TO BE SUBMITTED.
X01257833-I1
12/04/2025
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
10/09/2025
Inspection — Fail-Final General Construction Non-Directive 14
Fail
View inspection ↗
09/23/2025
Filed — Alteration
CONVERTING EX CORNER RETAIL SPACE USE GROUP#6 INTO (EATING & DRINKING ESTABLISHMENT) USE GROUP 6 WITH LESS THAN 74 OCCUPANCY LOAD. ALL WORK PREVIOUSLY DONE UNDER BIS JOB# 220700258 & JOB# X08040559. NO ADDITIONAL WORK TO BE DONE. EX PLANS TO BE SUBMITTED.
X01257833-P1
09/11/2025
Inspection — Fail-Final General Construction Non-Directive 14
Fail
View inspection ↗
08/28/2025
Inspection — Fail-Final General Construction Non-Directive 14
Fail
View inspection ↗
08/13/2025
Permit issued — General Construction
X01257833-I1-GC
08/11/2025
Filed — Alteration
CONVERTING EX CORNER RETAIL SPACE USE GROUP#6 INTO (EATING & DRINKING ESTABLISHMENT) USE GROUP 6 WITH LESS THAN 74 OCCUPANCY LOAD. ALL WORK PREVIOUSLY DONE UNDER BIS JOB# 220700258 & JOB# X08040559. NO ADDITIONAL WORK TO BE DONE. EX PLANS TO BE SUBMITTED.
X01257833-I1
06/29/2022
Signed off — Alteration
INTERIOR RENOVATION AT FIRST FLOOR FOR EXISTING STORE WITH GENERAL CONSTRUCTION AS PER PLAN FILLED HEREWITH. NO CHANGE OF USE, EGRESS OR CERTIFICATE OF OCCUPANCY.
X00449157-I1
11/17/2021
Signed off — Alteration
TO PROPOSE PLUMBING WORK FOR EX. STORE IN CONJUNCTION WITH ALT-2 JOB X00449157-I1 AS PER PLAN FILLED HEREWITH. NO CHANGE OF USE, EGRESS OR CERTIFICATE OF OCCUPANCY.
X00510217-I1
06/09/2021
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
06/05/2021
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
06/05/2021
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
06/03/2021
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
05/12/2021
Permit issued — Plumbing
X00510217-I1-PL
04/30/2021
Permit issued — General Construction
X00449157-I1-GC
04/26/2021
Filed — Alteration
TO PROPOSE PLUMBING WORK FOR EX. STORE IN CONJUNCTION WITH ALT-2 JOB X00449157-I1 AS PER PLAN FILLED HEREWITH. NO CHANGE OF USE, EGRESS OR CERTIFICATE OF OCCUPANCY.
X00510217-I1
04/26/2021
Special inspection requirement — Fire-Resistant Penetrations and Joints
QIANG SU
04/26/2021
Special inspection requirement — Energy Code Compliance Inspections
QIANG SU
04/26/2021
Special inspection requirement — HVAC-R and service water piping design and insulation
QIANG SU
03/16/2021
Objection raised — Other
03/16/2021
Objection resolved — Addressed
01/29/2021
Objection raised — Other
01/29/2021
Objection resolved — Addressed
01/29/2021
Objection raised — Other
01/29/2021
Objection resolved — Addressed
01/29/2021
Objection raised — Other
01/29/2021
Objection resolved — Addressed
01/29/2021
Objection raised — Other
01/29/2021
Objection resolved — Addressed
01/29/2021
Objection raised — Other
01/29/2021
Objection resolved — Addressed
01/21/2021
Filed — Alteration
INTERIOR RENOVATION AT FIRST FLOOR FOR EXISTING STORE WITH GENERAL CONSTRUCTION AS PER PLAN FILLED HEREWITH. NO CHANGE OF USE, EGRESS OR CERTIFICATE OF OCCUPANCY.
X00449157-I1
01/18/2021
Special inspection requirement — Fire-Resistant Penetrations and Joints
QIANG SU
01/18/2021
Special inspection requirement — Energy Code Compliance Inspections
QIANG SU
01/18/2021
Special inspection requirement — Air barrier - visual inspection
QIANG SU
01/18/2021
Special inspection requirement — Fenestration air leakage
QIANG SU
01/18/2021
Special inspection requirement — Fenestration and door U-factor and product ratings
QIANG SU
01/18/2021
Special inspection requirement — Insulation placement and R values
QIANG SU
01/18/2021
Special inspection requirement — Fenestration areas
QIANG SU
02/20/2020
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
12/28/2016
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
12/28/2016
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
10/05/2016
Violation issued (ECB, closed)
Construction
10/05/2016
Violation issued (ECB, closed)
Construction
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionSigned-offGREENER COUNTY.CONSTR INC08/13/2025
DOB NOWPlumbingSigned-offWHITESTONE PLUMBING CORP05/12/2021
DOB NOWGeneral ConstructionSigned-offSPLEN CONSTRUCTION INC04/30/2021
BISOTISSUEDTHOMAS MAINTENANCE INC09/14/2021
BISOTISSUEDTHOMAS MAINTENANCE INC05/14/2021
BISPLISSUEDL.L.G. PLBG & HTG INC06/24/2019
BISOTISSUEDMARCOS GENERAL CONTRACTOR05/01/2019
BISOTISSUEDKM POSIDON CORP01/17/2018
BISOTISSUEDRELIABLE H.I. INC02/27/2009
BISPLISSUEDMAIN LINE PLUMBING02/08/1996
BISSPISSUEDCAPITOL FIRE SPKL CO,INC07/28/1995
Nothing on file for this building.
▾Field Inspections (DOB CAP) — 8
DateTypeResultReport
12/04/2025Pass-Final General Construction Non-Directive 14PassView ↗
10/09/2025Fail-Final General Construction Non-Directive 14FailView ↗
09/11/2025Fail-Final General Construction Non-Directive 14FailView ↗
08/28/2025Fail-Final General Construction Non-Directive 14FailView ↗
06/09/2021Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
06/05/2021Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
06/05/2021Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
06/03/2021Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 10
DateRequirementInspectorRole
04/26/2021Fire-Resistant Penetrations and JointsQIANG SUspecial
04/26/2021Energy Code Compliance InspectionsQIANG SUprogress
04/26/2021HVAC-R and service water piping design and insulationQIANG SUenergy_progress
01/18/2021Fire-Resistant Penetrations and JointsQIANG SUspecial
01/18/2021Energy Code Compliance InspectionsQIANG SUprogress
01/18/2021Air barrier - visual inspectionQIANG SUenergy_progress
01/18/2021Fenestration air leakageQIANG SUenergy_progress
01/18/2021Fenestration and door U-factor and product ratingsQIANG SUenergy_progress
01/18/2021Insulation placement and R valuesQIANG SUenergy_progress
01/18/2021Fenestration areasQIANG SUenergy_progress
▾Documents — 116 on file (BIS + DOB NOW)
▸Plans & Drawings4
▸DOB NOWPlans/Sketch3
08/25/2026X00510217-I1Request digital key ↗
08/18/2026X01257833-P1Request digital key ↗
08/18/2026X01257833-I1Request digital key ↗
▸DOB NOWPlans/Sketch - General Construction1
08/25/2026X00449157-I1Request digital key ↗
▸Applications & Permits15
▸BISPLAN / WORK APPROVAL APPLICATION10
02/07/2023220698902Open ↗
03/05/2020220700258Open ↗
07/08/2019220700258Open ↗
Showing 3 of 10 on file for this type
▸BISWORK PERMIT APPLICATION5
09/15/2021220698902Open ↗
06/25/2019220700258Open ↗
05/01/2019220700258Open ↗
Showing 3 of 5 on file for this type
▸Seals & Professional Certifications32
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION9
03/05/2020220700258Open ↗
04/26/2019220700258Open ↗
04/26/2019220700258Open ↗
Showing 3 of 9 on file for this type
▸DOB NOWProgress Inspector Seal & Signature8
08/26/2026X00449157-I1Open ↗
08/26/2026X00449157-I1Open ↗
08/26/2026X00449157-I1Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature4
08/25/2026X00510217-I1Open ↗
08/18/2026X01257833-I1Open ↗
08/13/2026X00449157-I1Open ↗
Showing 3 of 4 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST3
03/05/2020220700258Open ↗
04/26/2019220700258Open ↗
02/24/2009210120947Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT3
03/05/2020220700258Open ↗
04/26/2019220700258Open ↗
12/21/2017240209207Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
08/26/2026X00449157-I1Open ↗
08/22/2026X00510217-I1Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
12/21/2017240209207Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
12/21/2017240209207Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM1
02/24/2009210120947Open ↗
▸Trade Schedules & Equipment3
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE3
07/08/2019220700258Open ↗
04/26/2019220700258Open ↗
01/03/2019220684098Open ↗
▸Safety & Tenant Protection4
▸BISTenant Protection Plan and Notes2
04/26/2019220700258Open ↗
01/03/2019220684098Open ↗
▸BISSTREET TREE CHECKLIST2
12/21/2017240209207Open ↗
02/24/2009210120947Open ↗
▸Environmental & Asbestos7
▸BISASBESTOS: CERTIFICATION (DEP ACP5)3
04/26/2019220700258Open ↗
01/03/2019220684098Open ↗
12/21/2017240209207Open ↗
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/25/2026X00510217-I1Open ↗
08/13/2026X00449157-I1Open ↗
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER1
02/24/2009210120947Open ↗
▸BISDEP ASBESTOS PROJECT COMPLETION FORM1
04/01/2021220698902Open ↗
▸Energy Compliance15
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS5
03/05/2020220700258Open ↗
04/26/2019220700258Open ↗
04/16/2019220698902Open ↗
Showing 3 of 5 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY5
07/25/2023220698902Open ↗
06/28/2023220698902Open ↗
04/16/2021220698902Open ↗
Showing 3 of 5 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS (EN2)2
06/28/2023220698902Open ↗
06/29/2021220700258Open ↗
▸DOB NOWEN2: As Built Energy Analysis.2
08/13/2026X00449157-I1Open ↗
08/13/2026X00510217-I1Open ↗
▸BISFENESTRATION AREAS1
06/29/2021220700258Open ↗
▸Inspections & Test Reports5
▸BISTECHNICAL REPORT: RESPONSIBILITY4
07/25/2023220698902Open ↗
06/28/2023220698902Open ↗
04/05/2021220698902Open ↗
Showing 3 of 4 on file for this type
▸BISFIRE-RESISTANT PENETRATIONS AND JOINTS (FIRESTOP)1
06/29/2021220700258Open ↗
▸Approvals, Objections & Sign-offs9
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST5
07/27/2023220698902Open ↗
06/29/2021220700258Open ↗
04/11/2018240209207Open ↗
Showing 3 of 5 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION1
09/22/2009210120947Open ↗
▸BISFINAL1
06/29/2021220700258Open ↗
▸BISADMINISTRATIVE OBJECTIONS1
02/24/2009210120947Open ↗
▸BISSCHEDULE A - OCCUPANCY / USE1
01/03/2019220684098Open ↗
▸Cost, Insurance & Ownership9
▸BISCOST AFFIDAVIT7
04/26/2019220700258Open ↗
04/16/2019220698902Open ↗
01/03/2019220684098Open ↗
Showing 3 of 7 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW32
06/28/2023220698902Open ↗
06/29/2021220700258Open ↗
▸Filing & Intake Forms12
▸BISADDITIONAL INFORMATION6
03/06/2023220698902Open ↗
04/01/2021220698902Open ↗
03/05/2020220700258Open ↗
Showing 3 of 6 on file for this type
▸BISEFILING COVER SHEET4
04/26/2019220700258Open ↗
04/16/2019220698902Open ↗
01/03/2019220684098Open ↗
Showing 3 of 4 on file for this type
▸BISBOROUGH INTAKE FORM1
03/30/2018240209207Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
12/21/2017240209207Open ↗
▸Other Documents1
▸BISPLOT DIAGRAM1
01/03/2019220684098Open ↗