| Firm | Filings | Most Recent |
|---|---|---|
| F.P.VILLANO CONSULTING ENGINEER LLC | 2 | 07/26/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| AC BUILDING CONSULTANTS | 2 | 03/21/2026 |
| DAY72 BUILDING CONSULTANT | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| CELTIC CONSTRUCTION II | General Contractor | 1 | 07/08/2026 |
| BES MECHANICAL LLC | Plumbing | 1 | 07/08/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | L AND I MECH. CONTRS. INC | 09/09/2022 |
| DOB NOW | General Construction | Signed-off | CELTIC CONSTRUCTION II | 07/20/2022 |
| BIS | OT | ISSUED | N/A | 01/26/1996 |
| BIS | OT | RE-ISSUED | N/A | 01/20/1995 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/30/2022 | Complete | DEFALCO AND SONS ELCT INC | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 09/21/2022 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/31/2022 | Final | FRANK VILLANO | progress |