← Back
Single or multiple dwelling with stores or offices
667 MORRIS PARK AVENUE
BRONX · BIN 2098271
💬 Discuss this project
1925Year Built
3Stories
S9Building Class
R5Zoning
10,000 sfGross Floor Area
10Units
1 Open Violation 0 unresolved · 1 paperwork only ▸
Single or multiple dwelling with stores or offices · Owner of record: VAN NEST PROPERTIES LLC · 7,750 sf lot · 1.29 FAR built · Flood zone X
Locations of Work
Architecture
Roof1p · 1 filing · 20 docs
Floor 11p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
URENA CONSTRUCTION & DESIGN1304/11/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
03/21/2014$725K—JAY AN WIL LLC → VAN NEST PROPERTIES LLC$72/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
SOTIR ASSOCIATES605/13/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
URENA CONST & DESIGN INCGeneral Contractor204/11/2026
INFINITI ESC PLUMBING CORPlumbing207/08/2026
DEFALCO AND SONS ELCT INCElectrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
ENGINEERING CONSULTING SE2050605/13/2026
Building Lifecycle
All (57)Filed (6)Permit Issued (4)Signed Off (2)Violation (1)Inspection (10)Objection (20)Special Inspection (14)
07/07/2026
Signed off — Alteration
PLUMBING WORK IN CONJUNCTION WITH INTERIOR RENOVATIONS TO REPAIR FIRE DAMAGE FILED UNDER X01066343-I1.
X01066343-S1
06/01/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
PAUL MARINO
05/13/2026
Filed — Alteration
PLUMBING WORK IN CONJUNCTION WITH INTERIOR RENOVATIONS TO REPAIR FIRE DAMAGE FILED UNDER X01066343-I1.
X01066343-P4
05/12/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
PAUL MARINO
04/27/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
04/22/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
04/15/2026
Objection resolved — Addressed
04/15/2026
Objection resolved — Addressed
04/13/2026
Signed off — Alteration
PLUMBING WORK IN CONJUNCTION WITH INTERIOR RENOVATIONS TO REPAIR FIRE DAMAGE FILED UNDER X01066343-I1.
X01066343-I1
04/08/2026
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
04/06/2026
Objection raised — Scope
04/06/2026
Objection raised — Cost
03/26/2026
Permit issued — Plumbing
X01066343-S1-PL
03/23/2026
Filed — Alteration
PLUMBING WORK IN CONJUNCTION WITH INTERIOR RENOVATIONS TO REPAIR FIRE DAMAGE FILED UNDER X01066343-I1.
X01066343-P3
03/23/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
PAUL MARINO
02/27/2026
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
12/29/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
12/15/2025
Filed — Alteration
PLUMBING WORK IN CONJUNCTION WITH INTERIOR RENOVATIONS TO REPAIR FIRE DAMAGE FILED UNDER X01066343-I1.
X01066343-P1
12/02/2025
Filed — Alteration
PLUMBING WORK IN CONJUNCTION WITH INTERIOR RENOVATIONS TO REPAIR FIRE DAMAGE FILED UNDER X01066343-I1.
X01066343-P2
11/19/2025
Inspection — Fail-Final General Construction Non-Directive 14
Fail
View inspection ↗
11/19/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
PAUL MARINO
11/19/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
PAUL MARINO
11/19/2025
Special inspection requirement — Energy Code Compliance Inspections
PAUL MARINO
11/19/2025
Special inspection requirement — Fire-Resistance Rated Construction
PAUL MARINO
11/19/2025
Special inspection requirement — Air barrier - visual inspection
PAUL MARINO
11/19/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
PAUL MARINO
11/19/2025
Special inspection requirement — Fenestration air leakage
PAUL MARINO
11/19/2025
Special inspection requirement — Fenestration areas
PAUL MARINO
11/19/2025
Special inspection requirement — Lighting in dwelling units
PAUL MARINO
11/19/2025
Special inspection requirement — Insulation placement and R values
PAUL MARINO
11/19/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
PAUL MARINO
08/20/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
07/03/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
05/29/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
04/02/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
03/20/2025
Permit issued — General Construction
X01066343-I1-GC
02/18/2025
Permit issued — Plumbing
X01066343-S1-PL
08/30/2024
Permit issued — General Construction
X01066343-I1-GC
08/27/2024
Objection resolved — Addressed
08/27/2024
Objection resolved — Addressed
08/27/2024
Objection resolved — Addressed
08/22/2024
Objection raised — Admin
08/16/2024
Objection raised — Admin
08/16/2024
Objection raised — Energy
08/14/2024
Filed — Alteration
PLUMBING WORK IN CONJUNCTION WITH INTERIOR RENOVATIONS TO REPAIR FIRE DAMAGE FILED UNDER X01066343-I1.
X01066343-S1
08/12/2024
Objection resolved — Addressed
08/06/2024
Objection resolved — Addressed
07/22/2024
Objection resolved — Addressed
07/22/2024
Objection resolved — Addressed
07/10/2024
Objection resolved — Addressed
06/28/2024
Objection raised — Admin
06/28/2024
Objection raised — Admin
06/28/2024
Objection raised — Cost
06/28/2024
Objection raised — Energy
06/27/2024
Objection raised — Admin
06/20/2024
Filed — Alteration
PLUMBING WORK IN CONJUNCTION WITH INTERIOR RENOVATIONS TO REPAIR FIRE DAMAGE FILED UNDER X01066343-I1.
X01066343-I1
03/16/2013
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offINFINITI ESC PLUMBING COR03/26/2026
DOB NOWGeneral ConstructionSigned-offURENA CONST & DESIGN INC03/20/2025
DOB NOWPlumbingSigned-offINFINITI ESC PLUMBING COR02/18/2025
DOB NOWGeneral ConstructionSigned-offURENA CONST & DESIGN INC08/30/2024
1 project · most recent 05/13/2026
Gas Water/Sanitary
FiledStatusContractorScope
05/13/2026Signed-offINFINITI ESC PLUMBING CORGas, Water/Sanitary
4 projects · most recent 07/17/2026
General Wiring HVAC Wiring
FiledStatusContractorScope
07/17/2026CompleteSAMMY ELECTRIC SVCS CORPGeneral Wiring
03/17/2026CompleteSAMMY ELECTRIC SVCS CORPHVAC Wiring
05/05/2025Permit IssuedDEFALCO AND SONS ELCT INCHVAC Wiring
03/26/2025Permit IssuedNEW TECH ELECTRIC INCGeneral Wiring
▾Field Inspections (DOB CAP) — 10
DateTypeResultReport
04/27/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
04/22/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
04/08/2026Pass-Final General Construction Non-Directive 14PassView ↗
02/27/2026Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
12/29/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
11/19/2025Fail-Final General Construction Non-Directive 14FailView ↗
08/20/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
07/03/2025Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
05/29/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
04/02/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 14
DateRequirementInspectorRole
06/01/2026Fire-Resistant Penetrations and JointsPAUL MARINOspecial
05/12/2026Fire-Resistant Penetrations and JointsPAUL MARINOspecial
03/23/2026Fire-Resistant Penetrations and JointsPAUL MARINOspecial
11/19/2025Fire-Resistant Penetrations and JointsPAUL MARINOspecial
11/19/2025Structural Stability – Alterations of existing buildingsPAUL MARINOspecial
11/19/2025Energy Code Compliance InspectionsPAUL MARINOprogress
11/19/2025Fire-Resistance Rated ConstructionPAUL MARINOprogress
11/19/2025Air barrier - visual inspectionPAUL MARINOenergy_progress
11/19/2025Fenestration and door U-factor and product ratingsPAUL MARINOenergy_progress
11/19/2025Fenestration air leakagePAUL MARINOenergy_progress
11/19/2025Fenestration areasPAUL MARINOenergy_progress
11/19/2025Lighting in dwelling unitsPAUL MARINOenergy_progress
11/19/2025Insulation placement and R valuesPAUL MARINOenergy_progress
11/19/2025Fire-Resistant Penetrations and JointsPAUL MARINOspecial
▾Documents — 25 on file (BIS + DOB NOW)
▸Plans & Drawings6
▸DOB NOWPlans/Sketch6
08/17/2026X01066343-P1Request digital key ↗
08/17/2026X01066343-P4Request digital key ↗
08/17/2026X01066343-P3Request digital key ↗
Showing 3 of 6 on file for this type
▸Seals & Professional Certifications13
▸DOB NOWDPL-1: Design Professional Seal & Signature6
08/17/2026X01066343-P3Open ↗
08/17/2026X01066343-P4Open ↗
08/13/2026X01066343-P2Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature5
09/01/2026X01066343-S1Open ↗
08/29/2026X01066343-P1Open ↗
08/27/2026X01066343-P2Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWProgress Inspector Seal & Signature2
08/29/2026X01066343-P1Open ↗
08/29/2026X01066343-P1Open ↗
▸Environmental & Asbestos6
▸DOB NOWDEP ACP-5: Asbestos Assessment Report6
08/17/2026X01066343-P4Open ↗
08/17/2026X01066343-P3Open ↗
08/13/2026X01066343-S1Open ↗
Showing 3 of 6 on file for this type