| Owner | Filings | Most Recent |
|---|---|---|
| CITY | 4 | 07/08/2026 |
| CITY OF NEW YORK | 3 | 03/22/2026 |
| DEP | 1 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| HAZEN AND SAWYER | 7 | 05/04/2026 |
| PATUXENT ENGINEERING LLC | 2 | 11/06/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| HAZEN & SAWYER, P.C. | 12 | 03/21/2026 |
| PATUXENT ENGINEERING | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| JETT INDUSTRIES INC | General Contractor | 6 | 07/22/2026 |
| GILSTON ELEC'L CONTNG LLC | Electrical | 2 | 03/22/2026 |
| CRAIG GILSTON | Electrical | 1 | 03/21/2026 |
| FRANK MERESHENSKY | Electrical | 1 | 03/21/2026 |
| JOHN DICAPUA | Electrical | 1 | 03/21/2026 |
| ADVANCED SCAFFOLD SER.LLC | General Contractor | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| COLE TECHNOLOGIES/CONTROL | 1290 | 7 | 05/04/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | JETT INDUSTRIES INC | 07/21/2026 |
| DOB NOW | General Construction | Permit Issued | JETT INDUSTRIES INC | 04/13/2026 |
| DOB NOW | General Construction | Permit Issued | JETT INDUSTRIES INC | 04/13/2026 |
| DOB NOW | General Construction | Permit Issued | JETT INDUSTRIES INC | 04/13/2026 |
| DOB NOW | General Construction | Permit Issued | JETT INDUSTRIES INC | 04/13/2026 |
| DOB NOW | General Construction | Permit Issued | JETT INDUSTRIES INC | 04/13/2026 |
| DOB NOW | Supported Scaffold | Permit Issued | ADVANCED SCAFFOLD SER.LLC | 10/02/2025 |
| BIS | OT | ISSUED | AECOM USA INC | 03/28/2024 |
| BIS | OT | ISSUED | AECOM USA INC | 04/06/2023 |
| BIS | OT | ISSUED | AECOM USA INC | 04/12/2022 |
| BIS | OT | ISSUED | AECOM USA INC | 04/05/2021 |
| BIS | OT | ISSUED | AECOM USA INC | 01/26/2021 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/11/2026 | Permit Issued | RNH ELECTRIC COMPANY INC | General Wiring |
| 06/11/2026 | Permit Issued | RNH ELECTRIC COMPANY INC | General Wiring |
| 06/11/2026 | Permit Issued | RNH ELECTRIC COMPANY INC | General Wiring |
| 06/11/2026 | Permit Issued | RNH ELECTRIC COMPANY INC | General Wiring |
| 04/30/2026 | Permit Issued | GILSTON ELEC'L CONTNG LLC | — |
| 09/18/2025 | Permit Issued | MECO ELECTRIC CO. INC. | General Wiring |
| 10/02/2024 | Permit Issued | CAPUTEK ELEC'L SERVICES, | — |
| 08/29/2023 | Complete | GILSTON ELEC'L CONTNG LLC | General Wiring |
| 07/25/2023 | Complete | P & M ELECT'L CONTR. CORP | General Wiring |
| 06/22/2023 | Permit Issued | ARK SYSTEMS ELEC. CORP | General Wiring |
| 04/11/2023 | Permit Issued | GILSTON ELEC'L CONTNG LLC | 1 meters, 1 new_meters |
| 07/28/2022 | Permit Issued | GILSTON ELEC'L CONTNG LLC | General Wiring |
| 07/15/2022 | Permit Issued | GILSTON ELEC'L CONTNG LLC | 1 meters, 1 new_meters |
| 07/08/2022 | Permit Issued | A TECH ELEC ENTERPRISES | General Wiring |
| 05/09/2022 | Permit Issued | ARK SYSTEMS ELEC. CORP | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/06/2025 | Permit Issued | ADVANCED SCAFFOLD SER.LLC | Scaffold |
| Date | Type | Result | Report |
|---|---|---|---|
| 09/03/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 05/04/2026 | Final | GEORGE ANDERSEN | progress |
| 05/04/2026 | Post-installed Anchors | GEORGE ANDERSEN | special |
| 05/04/2026 | Fire-Resistant Penetrations and Joints | GEORGE ANDERSEN | special |
| 04/27/2026 | Fire-Resistant Penetrations and Joints | GEORGE ANDERSEN | special |
| 04/27/2026 | Final | GEORGE ANDERSEN | progress |
| 04/27/2026 | Post-installed Anchors | GEORGE ANDERSEN | special |
| 11/11/2024 | Concrete - Cast-In-Place | GEORGE ANDERSEN | special |
| 11/11/2024 | Post-installed Anchors | GEORGE ANDERSEN | special |
| 11/11/2024 | Final | GEORGE ANDERSEN | progress |
| 10/31/2024 | Concrete - Cast-In-Place | GEORGE ANDERSEN | special |
| 10/31/2024 | Post-installed Anchors | GEORGE ANDERSEN | special |
| 10/31/2024 | Final | GEORGE ANDERSEN | progress |
| 10/23/2024 | Fire-Resistant Penetrations and Joints | GEORGE ANDERSEN | special |
| 10/23/2024 | Concrete - Cast-In-Place | GEORGE ANDERSEN | special |
| 10/23/2024 | Fire-Resistant Penetrations and Joints | GEORGE ANDERSEN | special |
| 10/23/2024 | Post-installed Anchors | GEORGE ANDERSEN | special |
| 10/23/2024 | Final | GEORGE ANDERSEN | progress |
| 10/23/2024 | Final | GEORGE ANDERSEN | progress |
| 10/23/2024 | Concrete - Cast-In-Place | GEORGE ANDERSEN | special |
| 10/23/2024 | Post-installed Anchors | GEORGE ANDERSEN | special |