← Back
Miscellaneous asylum / home
536 WALES AVENUE
BRONX · BIN 2129611
💬 Discuss this project
1999Year Built
1Stories
N9Building Class
R7-1Zoning
4,285 sfGross Floor Area
1Units
0 Open Violations
Miscellaneous asylum / home · Owner of record: RESOURCE CENTER FORTHE DEVELOPMENTALLY D ISABLED · 8,300 sf lot · 0.52 FAR built · Flood zone X
Locations of Work
ArchitectureMechanicalPlumbing
Permit Issued — active, not yet Signed-off
Roof1p · 1 filing · 18 docs
Floor 1Under Construction3p · 2 filings · 20 docs
CellarUnder Construction3p · 2 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
FORTUNE209/15/2026
IOCOVELLO & SONS BUILDERS403/22/2026
C&J CONSTRUCTION AND PAIN803/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
VINCENT J. LIOTTA P.E.108/27/2026
JOSHUA BRANDFONBRENER ARCHITECT108/10/2026
OMFPE CONSULTING PLLC207/27/2023
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
ALBA CONSULTANTS403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
SANG CHEUNGElectrical603/21/2026
AL-LECTRIC ELECTL CONTRG 002065General Contractor503/22/2026
IOCOVELLO & SONS BUILDERSGeneral Contractor203/22/2026
FRANK PUGLIESEElectrical103/21/2026
EVEREST REALTY HOLDINGS IGeneral Contractor108/16/2026
WHITESTONE PLUMBING CORPPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
VINCENT J. LIOTTA P. E.1974108/27/2026
BEYOND ARCH LLC3600108/10/2026
MASTROGIACOMO ENGINEERING4237207/27/2023
Building Lifecycle
All (108)Filed (4)Permit Issued (2)Signed Off (1)Violation (60)Inspection (3)Objection (14)Special Inspection (24)
09/15/2026
Objection resolved — Addressed
09/15/2026
Objection resolved — Addressed
09/15/2026
Objection resolved — Addressed
09/15/2026
Objection resolved — Addressed
09/15/2026
Objection resolved — Addressed
09/15/2026
Objection resolved — Addressed
09/15/2026
Objection resolved — Addressed
09/04/2026
Objection raised — Other
09/04/2026
Objection raised — Other
09/04/2026
Objection raised — Other
09/04/2026
Objection raised — Other
09/04/2026
Objection raised — Other
09/04/2026
Objection raised — Other
09/04/2026
Objection raised — Cost
08/27/2026
Filed — Alteration
INSTALLATION OF A 8 TON CAPACITY SPLIT SYSTEM ON FLOOR 001 AND LOW ROOF. NO CHANGE TO EGRESS, USE, OR OCCUPANCY.
X01451554-I1
08/27/2026
Special inspection requirement — HVAC-R and service water heating equipment
Vincent Liotta
08/27/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
Vincent Liotta
08/27/2026
Special inspection requirement — Maintenance information
Vincent Liotta
08/27/2026
Special inspection requirement — HVAC-R and service water heating system controls
Vincent Liotta
08/26/2026
Special inspection requirement — Final
Vincent Liotta
08/26/2026
Special inspection requirement — Mechanical Systems
Vincent Liotta
08/14/2026
Permit issued — General Construction
X01434788-I1-GC
08/10/2026
Filed — Alteration
FILING HEREWITH INTERIOR PARTITION RENOVATION AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
X01434788-I1
08/06/2026
Special inspection requirement — Interior lighting power
josh brandfonbrener
08/06/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Hackjong Choi
08/06/2026
Special inspection requirement — Energy Code Compliance Inspections
josh brandfonbrener
08/06/2026
Special inspection requirement — Fire-Resistance Rated Construction
josh brandfonbrener
08/06/2026
Special inspection requirement — Lighting controls
josh brandfonbrener
07/22/2026
Special inspection requirement — Final
josh brandfonbrener
11/14/2025
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
11/14/2025
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
12/18/2024
Signed off — Alteration
installation of (2) New Boilers at the Cellar floor.
X00783050-I1
12/01/2023
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
11/08/2023
Inspection — Pass-Final Boiler Equipment Inspection
Pass
View inspection ↗
11/02/2023
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
08/07/2023
Inspection — Fail-Final Boiler Equipment Inspection
Fail
View inspection ↗
08/02/2023
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
08/01/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
MICHAEL MASTROGIACOMO
08/01/2023
Special inspection requirement — Heating Systems
MICHAEL MASTROGIACOMO
08/01/2023
Special inspection requirement — HVAC-R and service water heating equipment
MICHAEL MASTROGIACOMO
08/01/2023
Special inspection requirement — HVAC-R and service water piping design and insulation
MICHAEL MASTROGIACOMO
08/01/2023
Special inspection requirement — Maintenance information
MICHAEL MASTROGIACOMO
08/01/2023
Special inspection requirement — HVAC-R and service water heating system controls
MICHAEL MASTROGIACOMO
07/27/2023
Filed — Alteration
installation of (2) New Boilers at the Cellar floor.
X00783050-P1
07/24/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
MICHAEL MASTROGIACOMO
07/24/2023
Special inspection requirement — Heating Systems
MICHAEL MASTROGIACOMO
07/24/2023
Special inspection requirement — HVAC-R and service water heating equipment
MICHAEL MASTROGIACOMO
07/24/2023
Special inspection requirement — Maintenance information
MICHAEL MASTROGIACOMO
07/24/2023
Special inspection requirement — HVAC-R and service water heating system controls
MICHAEL MASTROGIACOMO
07/24/2023
Special inspection requirement — HVAC-R and service water piping design and insulation
MICHAEL MASTROGIACOMO
07/10/2023
Inspection — No Access-Final Boiler Equipment Inspection
No Access
View inspection ↗
05/15/2023
Permit issued — Boiler Equipment
X00783050-I1-BE
05/02/2023
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
01/11/2023
Violation issued (ECB, closed)
Construction
01/11/2023
Violation issued (ECB, closed)
Unknown
01/11/2023
Violation issued (ECB, closed)
Construction
08/25/2022
Violation issued (ECB, closed)
Construction
08/25/2022
Violation issued (ECB, closed)
Construction
08/12/2022
Filed — Alteration
installation of (2) New Boilers at the Cellar floor.
X00783050-I1
01/19/2022
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
Latest 60 of 108 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedEVEREST REALTY HOLDINGS I08/14/2026
DOB NOWBoiler EquipmentSigned-offWHITESTONE PLUMBING CORP05/15/2023
BISPLISSUEDWHITESTONE PLUMBING CORP08/08/2023
BISPLISSUEDWHITESTONE PLUMBING CORP07/27/2023
BIS—RE-ISSUEDIOCOVELLO & SONS BUILDERS06/26/2023
BIS—ISSUEDIOCOVELLO & SONS BUILDERS08/11/2022
BISSDISSUEDALLSTATE SPRINKLER LLC07/29/2022
BISPLISSUEDWHITESTONE PLUMBING CORP07/07/2022
BIS—ISSUEDIOCOVELLO & SONS BUILDERS06/17/2022
BISPLISSUEDGJ PLUMBING LLC01/24/2022
BISEQISSUEDC & J CONST AND PAINTING12/07/2021
BISPLISSUEDGJ PLUMBING LLC02/08/2021
BISEQISSUEDC & J CONST AND PAINTING12/07/2020
BISSDISSUEDALLSTATE SPRINKLER LLC08/27/2020
BIS—ISSUEDC & J CONST AND PAINTING06/05/2020
BIS—ISSUEDC & J CONST AND PAINTING05/06/2020
BISEQISSUEDC & J CONST AND PAINTING02/27/2020
BIS—ISSUEDC & J CONST AND PAINTING02/27/2020
BIS—ISSUEDC & J CONST AND PAINTING02/27/2020
BIS—ISSUEDC & J CONST AND PAINTING03/29/2019
BISEQISSUEDC & J CONST AND PAINTING03/29/2019
BIS—ISSUEDC & J CONST AND PAINTING03/29/2019
BISPLISSUEDEXPERT PLUMBING CORP03/12/2019
BISEQISSUEDC & J CONST AND PAINTING04/17/2018
BIS—ISSUEDC & J CONST AND PAINTING04/17/2018
BIS—ISSUEDC & J CONST AND PAINTING04/17/2018
BISEQISSUEDC & J CONST AND PAINTING03/12/2018
BIS—ISSUEDC & J CONST AND PAINTING03/12/2018
BIS—ISSUEDC & J CONST AND PAINTING03/12/2018
BIS—ISSUEDS.S. ELBA CORP/BELTP PAVING02/10/1997
BIS—ISSUEDS.S.ELBA CORP/BELTOP PAVING CO02/10/1997
1 project · most recent 08/27/2026
Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
08/27/2026——Air Conditioning Systems
Cooling
Daikin FXAA12AAVJU 1 tons · Vrf Indoor ×1
FXMA96AAVJU 8 tons · Vrf Indoor ×1
RXYA96AATJA 8 tons · Vrf Outdoor ×1
4 projects · most recent 04/10/2026
General Wiring
FiledStatusContractorScope
04/10/2026CompletePATRIOT ELECTRIC CORPGeneral Wiring
01/15/2026CompletePATRIOT ELECTRIC CORPGeneral Wiring
11/21/2024CompleteAL-LECTRIC ELECT'L CONTRGGeneral Wiring
03/28/2023CompletePATRIOT ELECTRIC CORP6 meters, 6 new_meters
▾Field Inspections (DOB CAP) — 3
DateTypeResultReport
11/08/2023Pass-Final Boiler Equipment InspectionPassView ↗
08/07/2023Fail-Final Boiler Equipment InspectionFailView ↗
07/10/2023No Access-Final Boiler Equipment InspectionNo AccessView ↗
▾Special Inspection Requirements (DOB NOW) — 24
DateRequirementInspectorRole
08/27/2026HVAC-R and service water heating equipmentVincent Liottaenergy_progress
08/27/2026HVAC-R and service water piping design and insulationVincent Liottaenergy_progress
08/27/2026Maintenance informationVincent Liottaenergy_progress
08/27/2026HVAC-R and service water heating system controlsVincent Liottaenergy_progress
08/26/2026FinalVincent Liottaprogress
08/26/2026Mechanical SystemsVincent Liottaspecial
08/06/2026Interior lighting powerjosh brandfonbrenerenergy_progress
08/06/2026Fire-Resistant Penetrations and JointsHackjong Choispecial
08/06/2026Energy Code Compliance Inspectionsjosh brandfonbrenerprogress
08/06/2026Fire-Resistance Rated Constructionjosh brandfonbrenerprogress
08/06/2026Lighting controlsjosh brandfonbrenerenergy_progress
07/22/2026Finaljosh brandfonbrenerprogress
08/01/2023Fire-Resistant Penetrations and JointsMICHAEL MASTROGIACOMOspecial
08/01/2023Heating SystemsMICHAEL MASTROGIACOMOspecial
08/01/2023HVAC-R and service water heating equipmentMICHAEL MASTROGIACOMOenergy_progress
08/01/2023HVAC-R and service water piping design and insulationMICHAEL MASTROGIACOMOenergy_progress
08/01/2023Maintenance informationMICHAEL MASTROGIACOMOenergy_progress
08/01/2023HVAC-R and service water heating system controlsMICHAEL MASTROGIACOMOenergy_progress
07/24/2023Fire-Resistant Penetrations and JointsMICHAEL MASTROGIACOMOspecial
07/24/2023Heating SystemsMICHAEL MASTROGIACOMOspecial
07/24/2023HVAC-R and service water heating equipmentMICHAEL MASTROGIACOMOenergy_progress
07/24/2023Maintenance informationMICHAEL MASTROGIACOMOenergy_progress
07/24/2023HVAC-R and service water heating system controlsMICHAEL MASTROGIACOMOenergy_progress
07/24/2023HVAC-R and service water piping design and insulationMICHAEL MASTROGIACOMOenergy_progress
▾Documents — 150 on file (BIS + DOB NOW)
▸Plans & Drawings4
▸DOB NOWPlans/Sketch4
09/15/2026X01451554-I1Request digital key ↗
08/24/2026X00783050-I1Request digital key ↗
08/24/2026X00783050-P1Request digital key ↗
Showing 3 of 4 on file for this type
▸Applications & Permits44
▸BISPLAN / WORK APPROVAL APPLICATION23
11/15/2024200305026Open ↗
02/08/2024220539022Open ↗
12/15/2023220539022Open ↗
Showing 3 of 23 on file for this type
▸BISWORK PERMIT APPLICATION20
08/08/2023220549510Open ↗
06/27/2023220539022Open ↗
08/12/2022220539022Open ↗
Showing 3 of 20 on file for this type
▸BISCERTIFICATE OF OCCUPANCY: APPLICATION1
09/20/2023220539022Open ↗
▸Zoning, Tax Lot & Property Records5
▸BISTAX LOT: TENTATIVE LOT NUMBER ISSUED2
08/17/2022220575296Open ↗
06/08/2017220539022Open ↗
▸BISZONING DIAGRAM1
04/16/2019220539022Open ↗
▸BISZONING EXHIBIT I: CERTIFICATION1
06/08/2017220539022Open ↗
▸BISZONING EXHIBIT III:DESC. & OWNRSHP.STMNT1
06/08/2017220539022Open ↗
▸Seals & Professional Certifications33
▸DOB NOWProgress Inspector Seal & Signature15
09/27/2026X00783050-P1Open ↗
09/27/2026X00783050-P1Open ↗
09/27/2026X00783050-P1Open ↗
Showing 3 of 15 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION8
09/13/2023220549510Open ↗
09/13/2023220539022Open ↗
02/18/2020220539022Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature6
09/27/2026X00783050-P1Open ↗
09/27/2026X00783050-P1Open ↗
09/23/2026X01451554-I1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature4
09/15/2026X01451554-I1Open ↗
08/24/2026X00783050-P1Open ↗
08/24/2026X00783050-I1Open ↗
Showing 3 of 4 on file for this type
▸Trade Schedules & Equipment9
▸BISSEWER CONNECTION: DEP SD1 & SD22
08/22/2017220539022Open ↗
06/12/2017220539022Open ↗
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE2
05/12/2023220539022Open ↗
09/12/2016220549510Open ↗
▸BISDETECTOR:SMOKE-CERT. OF INSTALLATION1
03/15/2024220539022Open ↗
▸BISDETECTOR:CARBON MONOXIDE-CERT.OF INSTALL1
03/15/2024220539022Open ↗
▸BISSPRINKLER INSP REPORT : FP-851
11/09/2016220549510Open ↗
▸BISSCHEDULE B - PLUMBING1
05/11/2023220539022Open ↗
▸BISRPZ/DDCV TEST REPORT : GEN215B1
08/22/2017220539022Open ↗
▸Safety & Tenant Protection4
▸BISSTREET TREE CHECKLIST2
10/25/2022220575296Open ↗
06/27/2016220539022Open ↗
▸BISEXCAVATION OR DEMOLITION: 5-DAY NOTICE1
03/13/2018220539022Open ↗
▸BISBPP: STREET TREES SITE PLAN1
08/17/2022220575296Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/16/2026X01434788-I1Open ↗
▸Energy Compliance7
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS4
09/13/2023220539022Open ↗
02/18/2020220539022Open ↗
02/18/2020220539022Open ↗
Showing 3 of 4 on file for this type
▸BISPRELIMINARY COMMISSIONING REPORT CERTIFICATION1
12/13/2024220539022Open ↗
▸DOB NOWPreliminary Commissioning Report Certification1
08/13/2026X00783050-I1Open ↗
▸DOB NOWEN2: As Built Energy Analysis1
08/13/2026X00783050-I1Open ↗
▸Inspections & Test Reports4
▸BISTECHNICAL REPORT: CONCRETE DESIGN MIX2
10/30/2020220539022Open ↗
10/02/2019220539022Open ↗
▸BISTR3: CONCRETE DESIGN MIX TECHNICAL REPORT1
11/19/2018220539022Open ↗
▸BISTR2: CONCRETE TEST CYLINDERS TECHNICAL REPORT1
11/19/2018220539022Open ↗
▸Approvals, Objections & Sign-offs13
▸BISSCHEDULE A - OCCUPANCY / USE3
02/08/2024220539022Open ↗
12/15/2023220539022Open ↗
06/27/2016220539022Open ↗
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST3
05/29/2024220549510Open ↗
10/30/2020220539022Open ↗
10/29/2020220539022Open ↗
▸BISSUPERSEDING LETTER2
07/12/2022220539022Open ↗
02/08/2021220539022Open ↗
▸BISLETTERS - SUPPORTING DOCUMENTATION2
03/29/2019220539022Open ↗
07/26/2017220539022Open ↗
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter2
09/15/2026X01451554-I1Open ↗
08/16/2026X01434788-I1Open ↗
▸BISCONSTRUCTION CODE DETERMINATION1
07/26/2017220539022Open ↗
▸Cost, Insurance & Ownership5
▸BISPROJECT-SPECIFIC GL INSURANCE4
08/12/2022220539022Open ↗
03/29/2019220539022Open ↗
04/17/2018220539022Open ↗
Showing 3 of 4 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW31
05/24/2024220549510Open ↗
▸Filing & Intake Forms15
▸BISEFILING COVER SHEET8
02/18/2020220539022Open ↗
12/22/2016220575296Open ↗
09/12/2016220549510Open ↗
Showing 3 of 8 on file for this type
▸BISADDITIONAL INFORMATION6
04/16/2019220539022Open ↗
01/24/2019220539022Open ↗
12/05/2018220539022Open ↗
Showing 3 of 6 on file for this type
▸BISBPP: CHECKLIST IN LIEU OF PLANS-ALT31
08/17/2022220575296Open ↗
▸Other Documents6
▸BISBPP: PHOTOS-SIGNED/SEALED BY APPLICANT1
08/17/2022220575296Open ↗
▸BISBPP: NOTES REQUIRED ON PLAN1
10/25/2022220575296Open ↗
▸BISRECORDS MGMT FEE PAYMENT RECEIPT1
08/17/2022220575296Open ↗
▸BISPLOT DIAGRAM1
06/27/2016220539022Open ↗
▸BISSEISMIC ISOLATION SYSTEMS1
05/24/2024220549510Open ↗
▸BISBPP: TOPOGRAPHIC SURVEY1
08/17/2022220575296Open ↗