| Owner | Filings | Most Recent |
|---|---|---|
| ZEFI | 3 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| BADALY ARCHITECTS | 5 | 08/19/2026 |
| ASR ENGINEERING PC | 1 | 01/31/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| ADVANCED BUILDERS SERVICES | 1 | 03/21/2026 |
| KC EXPEDITING | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| ZEFI & CO. LLC | General Contractor | 4 | 07/08/2026 |
| RICHARD NEU | Electrical | 1 | 03/22/2026 |
| DNA PLUMBING CONTR. INC | Fire Protection | 1 | 07/08/2026 |
| PRIME PIPING & HEATING IN | Fire Protection | 1 | 06/28/2026 |
| TOPLINE NYC INC | General Contractor | 1 | 04/09/2026 |
| HORBRIDGE PLUMBING & HEATING | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| BADALY ARCHITECT PLLC | 7137 | 4 | 08/19/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Curb Cut | Signed-off | ZEFI & CO. LLC | 07/06/2026 |
| DOB NOW | Mechanical Systems | Signed-off | ZEFI & CO. LLC | 07/06/2026 |
| DOB NOW | Sprinklers | Signed-off | A M B MECHANICAL INC | 03/03/2026 |
| DOB NOW | General Construction | Permit Issued | ZEFI & CO. LLC | 10/21/2025 |
| DOB NOW | Sidewalk Shed | Signed-off | TOPLINE NYC INC | 02/04/2025 |
| DOB NOW | Plumbing | Signed-off | DNA PLUMBING CONTR. INC | 01/15/2025 |
| DOB NOW | Sprinklers | Signed-off | HORBRIDGE PLUMBING & HEAT | 01/14/2025 |
| DOB NOW | Structural | Permit Issued | ZEFI & CO. LLC | 10/10/2024 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 08/19/2026 | Signed-off | ZEFI & CO. LLC | Heating and Air Conditioning Systems, Ventilation Systems | Heat / Cool Amana ×12 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/19/2026 | Signed-off | HORBRIDGE PLUMBING & HEAT | Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/05/2025 | Complete | RICHARD NEU | — |
| 01/02/2025 | Complete | AV GROUP ELECTRICAL LLC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/19/2026 | Signed-off | ZEFI & CO. LLC | Masonry, Wood |
| Date | Type | Result | Report |
|---|---|---|---|
| 07/20/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 07/14/2026 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 04/27/2026 | Certified Storm Drainage-ST-Fixtures-Finish | Certified | View ↗ |
| 03/09/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 03/05/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 02/27/2026 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 06/11/2025 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 06/11/2025 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 03/06/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 01/30/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/19/2026 | Air barrier - visual inspection | MOHAMMAD BADALY | energy_progress |
| 08/19/2026 | Chimneys and vents | MOHAMMAD BADALY | special |
| 08/19/2026 | Fenestration and door U-factor and product ratings | MOHAMMAD BADALY | energy_progress |
| 08/19/2026 | Insulation placement and R values | MOHAMMAD BADALY | energy_progress |
| 08/19/2026 | Electric vehicle service equipment requirements | MOHAMMAD BADALY | energy_progress |
| 08/19/2026 | Permanent certificate | MOHAMMAD BADALY | energy_progress |
| 08/19/2026 | Fenestration areas | MOHAMMAD BADALY | energy_progress |
| 08/19/2026 | Metering | MOHAMMAD BADALY | energy_progress |
| 08/19/2026 | Air barrier — testing | MOHAMMAD BADALY | energy_progress |
| 08/19/2026 | Maintenance information | MOHAMMAD BADALY | energy_progress |
| 08/19/2026 | Fenestration air leakage | MOHAMMAD BADALY | energy_progress |
| 08/19/2026 | Interior lighting power | MOHAMMAD BADALY | energy_progress |
| 08/19/2026 | Footing and Foundation | MOHAMMAD BADALY | progress |
| 08/19/2026 | Fire-Resistance Rated Construction | MOHAMMAD BADALY | progress |
| 08/19/2026 | Final | MOHAMMAD BADALY | progress |
| 08/19/2026 | Energy Code Compliance Inspections | MOHAMMAD BADALY | progress |
| 08/19/2026 | Wood – Seismic Resistance | — | special |
| 08/19/2026 | Subsurface Investigations (Borings/Test Pits) | Paul Raymond | special |
| 08/19/2026 | Subgrade Inspections | MOHAMMAD BADALY | special |
| 08/19/2026 | Structural Steel - Welding | MOHAMMAD BADALY | special |
| 08/19/2026 | Structural Steel - High Strength Bolting | MOHAMMAD BADALY | special |
| 08/19/2026 | Structural Steel - Details | MOHAMMAD BADALY | special |
| 08/19/2026 | Structural Cold-Formed Steel | MOHAMMAD BADALY | special |
| 08/19/2026 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | MOHAMMAD BADALY | special |
| 08/19/2026 | Masonry | MOHAMMAD BADALY | special |