← Back
Three families
291 BALTIC STREET
BROOKLYN · BIN 3006340
💬 Discuss this project
1899Year Built
2.75Stories
C0Building Class
R6BZoning
3,036 sfGross Floor Area
3Units
Three families · 2,500 sf lot · 1.21 FAR built · Flood zone X
Locations of Work
Architecture
Floor 41p · 1 filing · 9 docs
Floor 3
Floor 21p · 1 filing · 9 docs
Floor 1
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
YANG ENGINEERING LLC108/06/2026
Building Lifecycle
All (57)Filed (1)Objection (39)Special Inspection (17)
09/18/2026
Objection raised — Cost
09/17/2026
Objection raised — Scope
09/17/2026
Objection raised — Zoning
09/17/2026
Objection raised — Other
09/17/2026
Objection raised — Inspections
09/08/2026
Objection resolved — Addressed
09/08/2026
Objection resolved — Addressed
09/08/2026
Objection resolved — Addressed
09/08/2026
Objection resolved — Addressed
09/08/2026
Objection resolved — Addressed
09/08/2026
Objection resolved — Addressed
09/08/2026
Objection resolved — Addressed
09/08/2026
Objection resolved — Addressed
09/08/2026
Objection resolved — Addressed
09/08/2026
Objection resolved — Addressed
09/08/2026
Objection resolved — Addressed
09/08/2026
Objection resolved — Addressed
09/08/2026
Objection resolved — Resolved
09/08/2026
Objection resolved — Addressed
09/08/2026
Objection resolved — Resolved
09/08/2026
Objection resolved — Resolved
09/08/2026
Objection resolved — Resolved
08/27/2026
Objection raised — Zoning
08/27/2026
Objection raised — Scope
08/27/2026
Objection raised — Scope
08/27/2026
Objection raised — Zoning
08/27/2026
Objection raised — Scope
08/27/2026
Objection raised — Scope
08/27/2026
Objection raised — Scope
08/27/2026
Objection raised — Scope
08/27/2026
Objection raised — Scope
08/27/2026
Objection raised — Scope
08/27/2026
Objection raised — Scope
08/27/2026
Objection raised — Zoning
08/27/2026
Objection raised — Zoning
08/26/2026
Objection raised — Scope
08/26/2026
Objection raised — Scope
08/26/2026
Objection raised — Zoning
08/26/2026
Objection raised — Cost
08/06/2026
Filed — ALT-CO - New Building with Existing Elements to Remain
PROPOSED VERTICAL AND HORIZONTAL ENLARGEMENT OF AN EXISTING 2-STORY 2-FAMILY BUILDING WITH BASEMENT AND CELLAR TO A 4-STORY 2-FAMILY BUILDING WITH CELLAR AS PER PLAN. OBTAIN NEW CERTIFICATE OF OCCUPANCY.
B01436153-I1
07/30/2026
Special inspection requirement — Maintenance information
07/30/2026
Special inspection requirement — Exterior Insulation and Finish Systems (EIFS)
07/30/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
07/30/2026
Special inspection requirement — Concrete - Cast-In-Place
07/30/2026
Special inspection requirement — Energy Code Compliance Inspections
07/30/2026
Special inspection requirement — Fire-Resistance Rated Construction
07/30/2026
Special inspection requirement — Fenestration areas
07/30/2026
Special inspection requirement — Fenestration air leakage
07/30/2026
Special inspection requirement — Air barrier - visual inspection
07/30/2026
Special inspection requirement — Interior lighting power
07/30/2026
Special inspection requirement — Insulation placement and R values
07/30/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
07/30/2026
Special inspection requirement — Exterior lighting power
07/30/2026
Special inspection requirement — Lighting controls
07/30/2026
Special inspection requirement — Lighting in dwelling units
07/30/2026
Special inspection requirement — Metering
07/24/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
Nothing on file for this building.
1 project · most recent 08/06/2026
Sprinkler System
FiledStatusContractorScope
08/06/2026——Sprinkler System
▾Special Inspection Requirements (DOB NOW) — 17
DateRequirementInspectorRole
07/30/2026Maintenance information—energy_progress
07/30/2026Exterior Insulation and Finish Systems (EIFS)—special
07/30/2026Fire-Resistant Penetrations and Joints—special
07/30/2026Concrete - Cast-In-Place—special
07/30/2026Energy Code Compliance Inspections—progress
07/30/2026Fire-Resistance Rated Construction—progress
07/30/2026Fenestration areas—energy_progress
07/30/2026Fenestration air leakage—energy_progress
07/30/2026Air barrier - visual inspection—energy_progress
07/30/2026Interior lighting power—energy_progress
07/30/2026Insulation placement and R values—energy_progress
07/30/2026Fenestration and door U-factor and product ratings—energy_progress
07/30/2026Exterior lighting power—energy_progress
07/30/2026Lighting controls—energy_progress
07/30/2026Lighting in dwelling units—energy_progress
07/30/2026Metering—energy_progress
07/24/2026Structural Stability – Alterations of existing buildings—special
▾Documents — 9 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/16/2026B01436153-I1Request digital key ↗
▸Zoning, Tax Lot & Property Records2
▸DOB NOWZD1: DOB Zoning Diagram1
08/16/2026B01436153-I1Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/16/2026B01436153-I1Open ↗
▸Seals & Professional Certifications1
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/16/2026B01436153-I1Open ↗
▸Safety & Tenant Protection1
▸DOB NOWStreet Tree Checklist1
08/16/2026B01436153-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/16/2026B01436153-I1Open ↗
▸Other Documents3
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone1
08/16/2026B01436153-I1Open ↗
▸DOB NOWProperty Ownership Certification1
08/16/2026B01436153-I1Open ↗
▸DOB NOWSite Survey: Initial1
08/16/2026B01436153-I1Open ↗