← Back
Miscellaneous two family
738 43 STREET
BROOKLYN · BIN 3011006
💬 Discuss this project
1920Year Built
2Stories
B9Building Class
R6BZoning
2,048 sfGross Floor Area
2Units
8 Open Violations 5 unresolved · 3 paperwork only ▸FDNY Report ↗
Miscellaneous two family · 2,003 sf lot · 1.02 FAR built · Flood zone X
Locations of Work
No floor-level scope or drawing coverage on file for this building.
1 job · most recent 02/25/2026
Gas Water/Sanitary
FiledStatusContractorScope
02/25/2026——Gas, Water/Sanitary
Building Lifecycle
All (85)Filed (4)Violation (9)Objection (42)Special Inspection (30)
09/17/2026
Objection raised — Scope
09/17/2026
Objection raised — Scope
09/17/2026
Objection raised — Scope
09/17/2026
Objection raised — Scope
09/17/2026
Objection raised — Scope
09/17/2026
Objection raised — Scope
09/17/2026
Objection raised — Scope
09/17/2026
Objection raised — Scope
09/17/2026
Objection raised — Scope
09/14/2026
Objection raised — Inspections
09/14/2026
Objection raised — Scope
09/14/2026
Objection raised — Scope
09/14/2026
Objection raised — Cost
09/14/2026
Objection raised — Scope
09/14/2026
Objection raised — Scope
09/14/2026
Objection raised — Scope
09/14/2026
Objection raised — Zoning
09/14/2026
Objection raised — Admin
09/14/2026
Objection raised — Scope
09/14/2026
Objection raised — Scope
09/14/2026
Objection raised — Scope
09/14/2026
Objection raised — Scope
09/14/2026
Objection raised — Scope
09/14/2026
Objection raised — Scope
09/14/2026
Objection raised — Scope
09/14/2026
Objection raised — Structural
09/14/2026
Objection raised — Other
09/14/2026
Objection raised — Other
08/20/2026
Filed — Alteration
TO RESOLVE WWP VIOLATION 35685758X,39161408Y BY REMOVE ILLEGAL PARTITIONS FOR 2-FAMILY HOUSE AND ILLEGAL STAIRS TO CELLAR WITH GENERAL CONSTRUCTION AND HORIZONTAL EXTENSION AS PER PLAN FILED HEREWITH. NO CHANGE IN USE, EGRESS AND OCCUPANCY.
B01447091-I1
08/18/2026
Special inspection requirement — Lighting in dwelling units
TONY ONYEAGORO
08/18/2026
Special inspection requirement — Fire-Resistance Rated Construction
TONY ONYEAGORO
08/18/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
TONY ONYEAGORO
08/18/2026
Special inspection requirement — Air barrier - visual inspection
TONY ONYEAGORO
08/18/2026
Special inspection requirement — Fenestration areas
TONY ONYEAGORO
08/18/2026
Special inspection requirement — Air barrier — testing
TONY ONYEAGORO
08/18/2026
Special inspection requirement — Fenestration air leakage
TONY ONYEAGORO
08/18/2026
Special inspection requirement — Energy Code Compliance Inspections
TONY ONYEAGORO
08/17/2026
Special inspection requirement — Exterior Insulation and Finish Systems (EIFS)
TONY ONYEAGORO
08/17/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
TONY ONYEAGORO
08/17/2026
Special inspection requirement — Masonry
TONY ONYEAGORO
08/17/2026
Special inspection requirement — Subgrade Inspections
TONY ONYEAGORO
08/17/2026
Special inspection requirement — Final
TONY ONYEAGORO
08/17/2026
Special inspection requirement — Concrete - Cast-In-Place
TONY ONYEAGORO
05/20/2026
Objection raised — Scope
05/20/2026
Objection raised — Scope
05/20/2026
Objection raised — Scope
05/20/2026
Objection raised — Scope
05/20/2026
Objection resolved — Resolved
05/20/2026
Objection raised — Scope
05/20/2026
Objection raised — Scope
05/20/2026
Objection raised — Other
05/20/2026
Objection resolved — Resolved
05/19/2026
Objection raised — Admin
05/19/2026
Objection raised — Structural
05/19/2026
Objection raised — Inspections
05/19/2026
Objection raised — Scope
05/19/2026
Objection raised — Scope
05/14/2026
Filed — Alteration
TO RESOLVE WWP VIOLATION 35685758X,39161408Y BY REMOVE ILLEGAL PARTITIONS FOR 2-FAMILY HOUSE AND ILLEGAL STAIRS TO BASEMENT WITH GENERAL CONSTRUCTION AS PER PLAN FILED HEREWITH. NO CHANGE IN USE, EGRESS AND OCCUPANCY.
B01402415-I1
05/14/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
QIANG SU
05/14/2026
Special inspection requirement — Final
Latest 60 of 85 events.
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
03/17/2014$748K—— → —$365/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
BUILDING CONSULTING ENGINEERING108/20/2026
SU ARCHITECT, P.C.305/14/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
BUILDING CONSULTING ENGIN1034108/20/2026
SU ARCHITECT PC6857305/14/2026
Nothing on file for this building.
▾Special Inspection Requirements (DOB NOW) — 30
DateRequirementInspectorRole
08/18/2026Lighting in dwelling unitsTONY ONYEAGOROenergy_progress
08/18/2026Fire-Resistance Rated ConstructionTONY ONYEAGOROprogress
08/18/2026Fenestration and door U-factor and product ratingsTONY ONYEAGOROenergy_progress
08/18/2026Air barrier - visual inspectionTONY ONYEAGOROenergy_progress
08/18/2026Fenestration areasTONY ONYEAGOROenergy_progress
08/18/2026Air barrier — testing TONY ONYEAGOROenergy_progress
08/18/2026Fenestration air leakageTONY ONYEAGOROenergy_progress
08/18/2026Energy Code Compliance InspectionsTONY ONYEAGOROprogress
08/17/2026Exterior Insulation and Finish Systems (EIFS)TONY ONYEAGOROspecial
08/17/2026Fire-Resistant Penetrations and JointsTONY ONYEAGOROspecial
08/17/2026MasonryTONY ONYEAGOROspecial
08/17/2026Subgrade InspectionsTONY ONYEAGOROspecial
08/17/2026FinalTONY ONYEAGOROprogress
08/17/2026Concrete - Cast-In-PlaceTONY ONYEAGOROspecial
05/14/2026Fenestration and door U-factor and product ratingsQIANG SUenergy_progress
05/14/2026Final—progress
05/14/2026Air barrier — testing QIANG SUenergy_progress
05/14/2026Fenestration areasQIANG SUenergy_progress
05/14/2026Lighting in dwelling unitsQIANG SUenergy_progress
05/14/2026Fenestration air leakageQIANG SUenergy_progress
05/14/2026Air barrier - visual inspectionQIANG SUenergy_progress
05/14/2026Fire-Resistant Penetrations and JointsQIANG SUspecial
05/14/2026Energy Code Compliance InspectionsQIANG SUprogress
05/14/2026Fire-Resistance Rated ConstructionQIANG SUprogress
02/04/2026Final—progress
Latest 25 of 30.
▾Documents — 29 on file (BIS + DOB NOW)
▸Plans & Drawings4
▸DOB NOWPlans/Sketch4
08/21/2026B01447091-I1Request digital key ↗
08/19/2026B01324945-S1Request digital key ↗
08/15/2026B01402415-I1Request digital key ↗
Showing 3 of 4 on file for this type
▸Zoning, Tax Lot & Property Records1
▸DOB NOWZD1: DOB Zoning Diagram1
08/21/2026B01447091-I1Open ↗
▸Seals & Professional Certifications17
▸DOB NOWProgress Inspector Seal & Signature10
08/28/2026B01402415-I1Open ↗
08/28/2026B01402415-I1Open ↗
08/28/2026B01402415-I1Open ↗
Showing 3 of 10 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature4
08/21/2026B01447091-I1Open ↗
08/19/2026B01324945-S1Open ↗
08/19/2026B01324945-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature3
08/28/2026B01402415-I1Open ↗
08/25/2026B01324945-I1Open ↗
08/25/2026B01324945-I1Open ↗
▸Environmental & Asbestos4
▸DOB NOWDEP ACP-5: Asbestos Assessment Report4
08/21/2026B01447091-I1Open ↗
08/19/2026B01324945-S1Open ↗
08/15/2026B01402415-I1Open ↗
Showing 3 of 4 on file for this type
▸Other Documents3
▸DOB NOWSite Survey: Initial1
08/21/2026B01447091-I1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone1
08/21/2026B01447091-I1Open ↗
▸DOB NOWPlot Diagram1
08/21/2026B01447091-I1Open ↗