← Back
Miscellaneous two family
735 46 STREET
BROOKLYN · BIN 3011753
💬 Discuss this project
1925Year Built
2Stories
B9Building Class
R6BZoning
2,288 sfGross Floor Area
2Units
Miscellaneous two family · 2,003 sf lot · 1.14 FAR built · Flood zone X
Locations of Work
ArchitectureElectricalPlumbing
Basement5p · 1 filing · 18 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
AARON MCDONALD ARCHITECT303/13/2026
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
BASIC GROUPS603/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
CUBE BUILDERS GROUP NYGeneral Contractor104/09/2026
PIPESTYLISTS, INCPlumbing107/08/2026
W.R. PLBG AND HTG CORPPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
NIC DESIGN INC9758103/13/2026
AARON MCDONALD ARCHITECT5118208/28/2025
Building Lifecycle
All (28)Filed (3)Permit Issued (3)Signed Off (2)Inspection (4)Special Inspection (16)
07/08/2026
Signed off — Alteration
Install and replace gas and plumbing fixtures in the existing 2 story building. Plumbing works as per plan. No change in egress , use, or occupancy.
B01252155-S1
07/08/2026
Signed off — Alteration
Install and replace gas and plumbing fixtures in the existing 2 story building. Plumbing works as per plan. No change in egress , use, or occupancy.
B01252155-I1
03/20/2026
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
03/17/2026
Special inspection requirement — Energy Code Compliance Inspections
Aaron McDonald
03/17/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
Aaron McDonald
03/17/2026
Special inspection requirement — HVAC-R and service water heating equipment
Aaron McDonald
03/17/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Aaron McDonald
03/17/2026
Special inspection requirement — HVAC-R and service water heating system controls
Aaron McDonald
03/13/2026
Filed — Alteration
Install and replace gas and plumbing fixtures in the existing 2 story building. Plumbing works as per plan. No change in egress , use, or occupancy.
B01252155-P1
03/11/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
Eric Sun
03/11/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Eric Sun
03/11/2026
Special inspection requirement — Energy Code Compliance Inspections
Eric Sun
03/11/2026
Special inspection requirement — HVAC-R and service water heating system controls
Eric Sun
03/11/2026
Special inspection requirement — HVAC-R and service water heating equipment
Eric Sun
02/03/2026
Permit issued — Plumbing
B01252155-S1-PL
11/24/2025
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
11/24/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
10/28/2025
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
08/28/2025
Filed — Alteration
Install and replace gas and plumbing fixtures in the existing 2 story building. Plumbing works as per plan. No change in egress , use, or occupancy.
B01252155-S1
08/28/2025
Permit issued — Plumbing
B01252155-S1-PL
08/26/2025
Permit issued — General Construction
B01252155-I1-GC
08/15/2025
Filed — Alteration
Install and replace gas and plumbing fixtures in the existing 2 story building. Plumbing works as per plan. No change in egress , use, or occupancy.
B01252155-I1
08/14/2025
Special inspection requirement — Energy Code Compliance Inspections
Aaron McDonald
08/14/2025
Special inspection requirement — Fire-Resistance Rated Construction
Aaron McDonald
08/14/2025
Special inspection requirement — Interior lighting power
Aaron McDonald
08/14/2025
Special inspection requirement — Insulation placement and R values
Aaron McDonald
07/07/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Aaron McDonald
07/07/2025
Special inspection requirement — Final
Aaron McDonald
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offW.R. PLBG AND HTG CORP02/03/2026
DOB NOWPlumbingSigned-offT & T PLUMBING INC08/28/2025
DOB NOWGeneral ConstructionSigned-offCUBE BUILDERS GROUP NY08/26/2025
BISPLISSUEDQMB PLUMBING & HEATING INC07/17/2008
BISCCISSUEDWAI KEE CONSTRUCTION INC06/24/2008
1 project · most recent 03/13/2026
Gas Water/Sanitary
FiledStatusContractorScope
03/13/2026Signed-offW.R. PLBG AND HTG CORPGas, Water/Sanitary
▾Field Inspections (DOB CAP) — 4
DateTypeResultReport
03/20/2026Pass-Final PL - Up to 3 Requested FloorsPassView ↗
11/24/2025Certified Gas-Gas-Piping-RoughingCertifiedView ↗
11/24/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
10/28/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 16
DateRequirementInspectorRole
03/17/2026Energy Code Compliance InspectionsAaron McDonaldprogress
03/17/2026HVAC-R and service water piping design and insulationAaron McDonaldenergy_progress
03/17/2026HVAC-R and service water heating equipmentAaron McDonaldenergy_progress
03/17/2026Fire-Resistant Penetrations and JointsAaron McDonaldspecial
03/17/2026HVAC-R and service water heating system controlsAaron McDonaldenergy_progress
03/11/2026HVAC-R and service water piping design and insulationEric Sunenergy_progress
03/11/2026Fire-Resistant Penetrations and JointsEric Sunspecial
03/11/2026Energy Code Compliance InspectionsEric Sunprogress
03/11/2026HVAC-R and service water heating system controlsEric Sunenergy_progress
03/11/2026HVAC-R and service water heating equipmentEric Sunenergy_progress
08/14/2025Energy Code Compliance InspectionsAaron McDonaldprogress
08/14/2025Fire-Resistance Rated ConstructionAaron McDonaldprogress
08/14/2025Interior lighting powerAaron McDonaldenergy_progress
08/14/2025Insulation placement and R valuesAaron McDonaldenergy_progress
07/07/2025Fire-Resistant Penetrations and JointsAaron McDonaldspecial
07/07/2025FinalAaron McDonaldprogress
▾Documents — 46 on file (BIS + DOB NOW)
▸Plans & Drawings3
▸DOB NOWPlans/Sketch3
08/18/2026B01252155-S1Request digital key ↗
08/18/2026B01252155-I1Request digital key ↗
08/18/2026B01252155-P1Request digital key ↗
▸Applications & Permits6
▸BISWORK PERMIT APPLICATION3
07/17/2008310154230Open ↗
06/24/2008310154230Open ↗
06/24/2008310168519Open ↗
▸BISPLAN / WORK APPROVAL APPLICATION3
05/05/2009310154230Open ↗
06/23/2008310168519Open ↗
06/12/2008310154230Open ↗
▸Seals & Professional Certifications20
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION6
12/15/2009310168519Open ↗
08/04/2009310154230Open ↗
06/23/2008310168519Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWProgress Inspector Seal & Signature6
09/01/2026B01252155-S1Open ↗
09/01/2026B01252155-S1Open ↗
08/31/2026B01252155-P1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature3
08/18/2026B01252155-S1Open ↗
08/13/2026B01252155-I1Open ↗
08/13/2026B01252155-P1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature3
09/01/2026B01252155-S1Open ↗
08/31/2026B01252155-P1Open ↗
08/31/2026B01252155-I1Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM1
06/23/2008310168519Open ↗
▸BISPROFESSIONAL CERTIFIED CHECKLIST1
06/24/2008310168519Open ↗
▸Trade Schedules & Equipment1
▸BISSCHEDULE B - PLUMBING1
06/12/2008310154230Open ↗
▸Environmental & Asbestos5
▸DOB NOWDEP ACP-5: Asbestos Assessment Report3
08/18/2026B01252155-S1Open ↗
08/13/2026B01252155-I1Open ↗
08/13/2026B01252155-P1Open ↗
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER2
06/23/2008310168519Open ↗
06/12/2008310154230Open ↗
▸Approvals, Objections & Sign-offs5
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST3
12/15/2009310168519Open ↗
08/25/2009310168519Open ↗
08/04/2009310154230Open ↗
▸BISADMINISTRATIVE OBJECTIONS2
06/23/2008310168519Open ↗
06/12/2008310154230Open ↗
▸Cost, Insurance & Ownership4
▸BISCOST AFFIDAVIT4
08/04/2009310154230Open ↗
07/17/2008310154230Open ↗
06/24/2008310154230Open ↗
Showing 3 of 4 on file for this type
▸Filing & Intake Forms2
▸BISEFILING COVER SHEET2
06/23/2008310168519Open ↗
06/12/2008310154230Open ↗