← Back
Office with commercial, 1-6 stories
296 20 STREET
BROOKLYN · BIN 3017394
💬 Discuss this project
1930Year Built
2Stories
O5Building Class
R6BZoning
1,875 sfGross Floor Area
1Units
0 Open ViolationsFDNY Report ↗
Office with commercial, 1-6 stories · Owner of record: JIT ENTERPRISES LLC · 2,500 sf lot · 0.75 FAR built · Flood zone X
Locations of Work
Architecture
Basement2p · 1 filing · 3 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
PRODIGY CONSTRUCTION804/09/2026
JIT ENTERPRISES603/22/2026
FOUNDATION ASSOCIATES603/22/2026
OWNER OF 294 20 STREET103/22/2026
OWNER OF PROPERTY 294103/22/2026
FOUNDATION ASSOCIATION103/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
FRANK PETRUSO ARCHITECT PC112/29/2025
STEFANO MORISI R.A.111/26/2024
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
JUST ARCHITECTURE103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
PRODIGY CONSTRUCTION INCGeneral Contractor304/09/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
DYO DESIGN OFFICE LLC6701111/26/2024
Building Lifecycle
All (90)Filed (2)Permit Issued (2)Signed Off (1)Violation (23)Objection (43)Special Inspection (19)
08/10/2026
Objection resolved — Resolved
08/10/2026
Objection resolved — Resolved
08/10/2026
Objection resolved — Resolved
07/29/2026
Objection resolved — Addressed
07/27/2026
Objection resolved — Resolved
07/27/2026
Objection resolved — Resolved
07/27/2026
Objection resolved — Addressed
07/27/2026
Objection resolved — Addressed
07/27/2026
Objection resolved — Resolved
07/27/2026
Objection resolved — Resolved
07/27/2026
Objection resolved — Addressed
07/27/2026
Objection resolved — Addressed
07/27/2026
Objection resolved — Addressed
06/25/2026
Objection raised — Scope
06/25/2026
Objection raised — Scope
06/25/2026
Objection raised — Scope
06/25/2026
Objection raised — Scope
06/25/2026
Objection raised — Scope
06/25/2026
Objection raised — Scope
06/25/2026
Objection raised — Scope
06/25/2026
Objection raised — Scope
06/25/2026
Objection raised — Scope
06/14/2026
Objection resolved — Addressed
06/14/2026
Objection resolved — Addressed
06/14/2026
Objection resolved — Addressed
06/14/2026
Objection resolved — Addressed
06/14/2026
Objection resolved — Addressed
06/14/2026
Objection resolved — Addressed
06/14/2026
Objection resolved — Addressed
04/06/2026
Special inspection requirement — Lighting in dwelling units
04/06/2026
Special inspection requirement — Maintenance information
04/06/2026
Special inspection requirement — Air barrier — testing
04/06/2026
Special inspection requirement — Metering
04/06/2026
Special inspection requirement — Protection of exposed foundation insulation
04/03/2026
Special inspection requirement — Air barrier - visual inspection
04/03/2026
Special inspection requirement — Insulation placement and R values
04/02/2026
Special inspection requirement — Lighting controls
04/02/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
04/02/2026
Special inspection requirement — Exterior lighting power
04/02/2026
Special inspection requirement — Fenestration areas
04/02/2026
Special inspection requirement — Fenestration air leakage
04/02/2026
Special inspection requirement — Interior lighting power
01/05/2026
Objection raised — Cost
01/05/2026
Objection raised — Plumbing
01/05/2026
Objection raised — Fire_Protection
01/05/2026
Objection raised — Zoning
01/05/2026
Objection raised — Structural
01/05/2026
Objection raised — Structural
01/05/2026
Objection raised — Structural
01/05/2026
Objection raised — Structural
01/05/2026
Objection raised — Admin
01/05/2026
Objection raised — Scope
01/05/2026
Objection raised — Zoning
01/05/2026
Objection raised — Plumbing
01/05/2026
Objection raised — Plumbing
12/31/2025
Objection raised — Energy
12/29/2025
Filed — Alteration CO
CONSTRUCT FRONT 2 STORY & 4 STORY HORIZONTIAL ADDITION. CONSTRUCT 2ND & 3RD FLOOR VERTICAL ADDITION. CONVERT INTO MULTIPLE DWELLING.
B01338220-I1
12/22/2025
Special inspection requirement — Masonry
12/22/2025
Special inspection requirement — Fire-Resistance Rated Construction
12/22/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Latest 60 of 90 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionSigned-offPRODIGY CONSTRUCTION INC09/24/2025
DOB NOWGeneral ConstructionSigned-offPRODIGY CONSTRUCTION INC02/26/2025
BISMHISSUEDDYNAMIC SHEET METAL LTD03/05/2012
BISBLISSUEDZ.W. PLBG & HTG CORP11/12/2002
BISPLISSUEDZ.W. PLBG & HTG CORP11/12/2002
BISPLISSUEDADVANCED PLUMBING MECH04/28/1995
BIS—ISSUEDFOUNDATION CONSTR. CONS.10/05/1994
3 projects · most recent 06/25/2026
General Wiring
FiledStatusContractorScope
06/25/2026Permit IssuedHIGH QUALITY ELEC.OF NYC—
06/19/2026Permit IssuedA&L ELECTRIC & AUTOMATIONGeneral Wiring
05/15/2025Permit IssuedE & M ELECTRICAL NY CORPGeneral Wiring
▾Special Inspection Requirements (DOB NOW) — 19
DateRequirementInspectorRole
04/06/2026Lighting in dwelling units—energy_progress
04/06/2026Maintenance information—energy_progress
04/06/2026Air barrier — testing —energy_progress
04/06/2026Metering—energy_progress
04/06/2026Protection of exposed foundation insulation—energy_progress
04/03/2026Air barrier - visual inspection—energy_progress
04/03/2026Insulation placement and R values—energy_progress
04/02/2026Lighting controls—energy_progress
04/02/2026Fenestration and door U-factor and product ratings—energy_progress
04/02/2026Exterior lighting power—energy_progress
04/02/2026Fenestration areas—energy_progress
04/02/2026Fenestration air leakage—energy_progress
04/02/2026Interior lighting power—energy_progress
12/22/2025Masonry—special
12/22/2025Fire-Resistance Rated Construction—progress
12/22/2025Fire-Resistant Penetrations and Joints—special
12/22/2025Energy Code Compliance Inspections—progress
12/22/2025Exterior Insulation and Finish Systems (EIFS)—special
12/20/2025Structural Stability – Alterations of existing buildings—special
▾Documents — 25 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/23/2026B01146764-I1Request digital key ↗
▸Applications & Permits2
▸BISPLAN / WORK APPROVAL APPLICATION1
07/12/2011320337140Open ↗
▸BISWORK PERMIT APPLICATION1
03/09/2012320337140Open ↗
▸Zoning, Tax Lot & Property Records1
▸DOB NOWZD1: DOB Zoning Diagram1
08/13/2026B01338220-I1Open ↗
▸Seals & Professional Certifications4
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION2
04/19/2012320337140Open ↗
07/12/2011320337140Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature2
08/23/2026B01146764-I1Open ↗
08/13/2026B01338220-I1Open ↗
▸Trade Schedules & Equipment3
▸BISEQUIPMENT USE APPLICATION/PERMIT2
05/01/2012320337140Open ↗
07/12/2011320337140Open ↗
▸BISEQUIPMENT USE PERMITS1
05/01/2012320337140Open ↗
▸Environmental & Asbestos3
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/23/2026B01146764-I1Open ↗
08/13/2026B01338220-I1Open ↗
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'1
07/12/2011320337140Open ↗
▸Energy Compliance4
▸BISTECHNICAL REPORT: ENERGY3
05/01/2012320337140Open ↗
05/01/2012320337140Open ↗
07/12/2011320337140Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
04/19/2012320337140Open ↗
▸Approvals, Objections & Sign-offs3
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST2
05/01/2012320337140Open ↗
04/19/2012320337140Open ↗
▸BISADMINISTRATIVE OBJECTIONS1
07/12/2011320337140Open ↗
▸Cost, Insurance & Ownership2
▸BISCOST AFFIDAVIT2
04/19/2012320337140Open ↗
07/12/2011320337140Open ↗
▸Filing & Intake Forms1
▸BISEFILING COVER SHEET1
07/12/2011320337140Open ↗
▸Other Documents1
▸DOB NOWSite Survey: Initial1
08/13/2026B01338220-I1Open ↗