| Firm | Filings | Most Recent |
|---|---|---|
| PACS ARCHITECTURE | 4 | 01/11/2024 |
| ANZ CONSULTING ENGINEERING, PLLC | 1 | 05/15/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| PROCESS WERKSHOP | 10 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| CMP CONTRACTING INC | General Contractor | 3 | 07/08/2026 |
| BENT MECHANICAL CORP | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| GRAND INSPECTION & CONSUL | 6792 | 3 | 01/11/2024 |
| ANZ CONSULTING ENGINEERIN | 3946 | 2 | 05/15/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Signed-off | CMP CONTRACTING | 09/25/2024 |
| DOB NOW | Plumbing | Signed-off | BENT MECHANICAL CORP | 01/05/2024 |
| DOB NOW | General Construction | Signed-off | CMP CONTRACTING | 10/05/2023 |
| DOB NOW | General Construction | Signed-off | CMP CONTRACTING | 08/28/2023 |
| BIS | PL | ISSUED | SCARPONI&SON PLBG&HTG COR | 01/09/2013 |
| BIS | OT | ISSUED | GOODRICH WORKS, LLC | 01/08/2013 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/27/2023 | Complete | N.Z. PILGRIM ELECTRIC INC | General Wiring |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 02/05/2024 | Structural Stability – Alterations of existing buildings | RUWAN RAJAPAKSE | special |
| 02/05/2024 | Fire-Resistant Penetrations and Joints | RUWAN RAJAPAKSE | special |
| 02/05/2024 | Construction Operations Influencing Adjacent Structures | RUWAN RAJAPAKSE | special |
| 02/05/2024 | Fire-Resistance Rated Construction | PAUL CAPECE | progress |
| 02/05/2024 | Final | PAUL CAPECE | progress |
| 02/05/2024 | Energy Code Compliance Inspections | PAUL CAPECE | progress |
| 02/05/2024 | Fenestration areas | PAUL CAPECE | energy_progress |
| 02/05/2024 | Lighting in dwelling units | PAUL CAPECE | energy_progress |
| 02/05/2024 | Insulation placement and R values | PAUL CAPECE | energy_progress |
| 02/05/2024 | Air barrier - visual inspection | PAUL CAPECE | energy_progress |
| 01/09/2024 | Construction Operations Influencing Adjacent Structures | RUWAN RAJAPAKSE | special |
| 01/09/2024 | Fire-Resistant Penetrations and Joints | RUWAN RAJAPAKSE | special |
| 01/09/2024 | Structural Stability – Alterations of existing buildings | RUWAN RAJAPAKSE | special |
| 01/09/2024 | Energy Code Compliance Inspections | PAUL CAPECE | progress |
| 01/09/2024 | Final | PAUL CAPECE | progress |
| 01/09/2024 | Fire-Resistance Rated Construction | PAUL CAPECE | progress |
| 01/09/2024 | Fenestration areas | PAUL CAPECE | energy_progress |
| 01/09/2024 | Insulation placement and R values | PAUL CAPECE | energy_progress |
| 01/09/2024 | Lighting in dwelling units | PAUL CAPECE | energy_progress |
| 01/09/2024 | Air barrier - visual inspection | PAUL CAPECE | energy_progress |
| 05/31/2023 | Fire-Resistant Penetrations and Joints | ALBERT ZIRINO | special |
| 03/15/2023 | Concrete - Cast-In-Place | RUWAN RAJAPAKSE | special |
| 03/15/2023 | Masonry | RUWAN RAJAPAKSE | special |
| 03/15/2023 | Structural Steel - Details | RUWAN RAJAPAKSE | special |
| 03/15/2023 | Structural Steel - High Strength Bolting | RUWAN RAJAPAKSE | special |