← Back
Walk-up cooperative
822 PRESIDENT STREET
BROOKLYN · BIN 3024734
💬 Discuss this project
1889Year Built
4Stories
C6Building Class
R6AZoning
4,056 sfGross Floor Area
4Units
Rent Stabilized3 Open Violations ▸FDNY Report ↗
Walk-up cooperative · Owner of record: PR 822 OWNERS CORP · 1,800 sf lot · 2.25 FAR built · Flood zone X
Locations of Work
ArchitectureStructural
Roof1p · 1 filing · 18 docs
Bulkhead2p · 1 filing · 13 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
PR 822 OWNERS CORP103/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
ZAIDI CHRISTO DESIGN202/16/2022
GILSANZ MURRAY STEFICEK LLP208/27/2021
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
FOURTH STREET DESIGN BUILD803/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
DEMETRIOS ILIOPOULOSElectrical303/21/2026
DESIGN TECH CONSTRUCT CORGeneral Contractor307/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
PROJECT TACTICAL SOLUTION5859202/16/2022
GILSANZ MURRAY STEFICEK240208/27/2021
Building Lifecycle
All (60)Filed (4)Permit Issued (2)Signed Off (2)Violation (12)Objection (10)Special Inspection (30)
06/10/2025
Violation issued (HPD, closed)
A
04/11/2024
Violation issued (HPD, closed)
A
03/24/2023
Violation issued (HPD, closed)
A
11/03/2022
Signed off — Alteration
EXTERIOR WORK ON ROOF. NO CHANGE IN USE, OCCUPANCY OR EGRESS.
B00513580-I1
10/25/2022
Signed off — Alteration
INTERIOR AND EXTERIOR RENOVATION AT 4TH FLOOR AND ROOF. ALL WORK AS PER PLAN. NO CHANGE IN USE, OCCUPANCY OR EGRESS.
B00513276-I1
03/30/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
Max Lee
03/30/2022
Special inspection requirement — Energy Code Compliance Inspections
Max Lee
03/30/2022
Special inspection requirement — Fire-Resistance Rated Construction
Max Lee
03/30/2022
Special inspection requirement — Final
ROBERT CHRISTO
03/30/2022
Special inspection requirement — Lighting in dwelling units
Max Lee
03/30/2022
Special inspection requirement — Fenestration areas
Max Lee
03/30/2022
Special inspection requirement — Fenestration air leakage
Max Lee
03/30/2022
Special inspection requirement — Lighting controls
Max Lee
03/30/2022
Special inspection requirement — Insulation placement and R values
Max Lee
03/30/2022
Special inspection requirement — Interior lighting power
Max Lee
03/30/2022
Special inspection requirement — Fenestration and door U-factor and product ratings
Max Lee
03/30/2022
Special inspection requirement — Metering
Max Lee
03/30/2022
Special inspection requirement — Exterior lighting power
Max Lee
03/30/2022
Special inspection requirement — Air barrier - visual inspection
Max Lee
03/23/2022
Objection resolved — Addressed
03/23/2022
Objection resolved — Addressed
03/23/2022
Objection resolved — Addressed
03/16/2022
Objection raised — Structural
03/01/2022
Violation issued (HPD, closed)
I
03/01/2022
Violation issued (HPD, closed)
A
02/28/2022
Objection raised — Admin
02/28/2022
Objection raised — Scope
02/22/2022
Objection resolved — Addressed
02/22/2022
Objection resolved — Addressed
02/19/2022
Objection raised — Scope
02/19/2022
Objection raised — Energy
02/16/2022
Filed — Alteration
INTERIOR AND EXTERIOR RENOVATION AT 4TH FLOOR AND ROOF. ALL WORK AS PER PLAN. NO CHANGE IN USE, OCCUPANCY OR EGRESS.
B00513276-P1
02/14/2022
Special inspection requirement — Metering
Max Lee
02/14/2022
Special inspection requirement — Insulation placement and R values
Max Lee
02/14/2022
Special inspection requirement — Fenestration and door U-factor and product ratings
Max Lee
02/14/2022
Special inspection requirement — Interior lighting power
Max Lee
02/14/2022
Special inspection requirement — Fenestration areas
Max Lee
02/14/2022
Special inspection requirement — Lighting controls
Max Lee
02/14/2022
Special inspection requirement — Fenestration air leakage
Max Lee
02/14/2022
Special inspection requirement — Lighting in dwelling units
Max Lee
02/14/2022
Special inspection requirement — Air barrier - visual inspection
Max Lee
02/14/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
Max Lee
02/14/2022
Special inspection requirement — Energy Code Compliance Inspections
Max Lee
02/14/2022
Special inspection requirement — Final
ROBERT CHRISTO
02/14/2022
Special inspection requirement — Fire-Resistance Rated Construction
Max Lee
02/14/2022
Special inspection requirement — Exterior lighting power
Max Lee
10/18/2021
Permit issued — Structural
B00513580-I1-ST
08/27/2021
Filed — Alteration
EXTERIOR WORK ON ROOF. NO CHANGE IN USE, OCCUPANCY OR EGRESS.
B00513580-P1
08/23/2021
Special inspection requirement — Post-installed Anchors
Philip Murray
08/23/2021
Special inspection requirement — Structural Stability – Alterations of existing buildings
Philip Murray
08/22/2021
Permit issued — General Construction
B00513276-I1-GC
06/02/2021
Filed — Alteration
EXTERIOR WORK ON ROOF. NO CHANGE IN USE, OCCUPANCY OR EGRESS.
B00513580-I1
05/03/2021
Filed — Alteration
INTERIOR AND EXTERIOR RENOVATION AT 4TH FLOOR AND ROOF. ALL WORK AS PER PLAN. NO CHANGE IN USE, OCCUPANCY OR EGRESS.
B00513276-I1
10/31/2019
Violation issued (HPD, closed)
I
11/28/2017
Violation issued (HPD, closed)
I
10/13/2015
Violation issued (HPD, closed)
I
02/24/2015
Violation issued (HPD, closed)
I
06/19/1985
Violation issued (HPD, open)
A
06/19/1985
Violation issued (HPD, open)
A
09/22/1982
Violation issued (HPD, open)
A
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWStructuralSigned-offDESIGN TECH CONSTRUCT COR10/18/2021
DOB NOWGeneral ConstructionSigned-offDESIGN TECH CONSTRUCT COR08/22/2021
1 project · most recent 05/17/2022
General Wiring HVAC Wiring
FiledStatusContractorScope
05/17/2022CompleteSUNBIRD ELECTRICAL CONTRGeneral Wiring, HVAC Wiring
▾Special Inspection Requirements (DOB NOW) — 36
DateRequirementInspectorRole
03/30/2022Fire-Resistant Penetrations and JointsMax Leespecial
03/30/2022Energy Code Compliance InspectionsMax Leeprogress
03/30/2022Fire-Resistance Rated ConstructionMax Leeprogress
03/30/2022FinalROBERT CHRISTOprogress
03/30/2022Lighting in dwelling unitsMax Leeenergy_progress
03/30/2022Fenestration areasMax Leeenergy_progress
03/30/2022Fenestration air leakageMax Leeenergy_progress
03/30/2022Lighting controlsMax Leeenergy_progress
03/30/2022Insulation placement and R valuesMax Leeenergy_progress
03/30/2022Interior lighting powerMax Leeenergy_progress
03/30/2022Fenestration and door U-factor and product ratingsMax Leeenergy_progress
03/30/2022MeteringMax Leeenergy_progress
03/30/2022Exterior lighting powerMax Leeenergy_progress
03/30/2022Air barrier - visual inspectionMax Leeenergy_progress
02/14/2022MeteringMax Leeenergy_progress
02/14/2022Insulation placement and R valuesMax Leeenergy_progress
02/14/2022Fenestration and door U-factor and product ratingsMax Leeenergy_progress
02/14/2022Interior lighting powerMax Leeenergy_progress
02/14/2022Fenestration areasMax Leeenergy_progress
02/14/2022Lighting controlsMax Leeenergy_progress
02/14/2022Fenestration air leakageMax Leeenergy_progress
02/14/2022Lighting in dwelling unitsMax Leeenergy_progress
02/14/2022Air barrier - visual inspectionMax Leeenergy_progress
02/14/2022Fire-Resistant Penetrations and JointsMax Leespecial
02/14/2022Energy Code Compliance InspectionsMax Leeprogress
Latest 25 of 36.
▾Documents — 31 on file (BIS + DOB NOW)
▸Plans & Drawings4
▸DOB NOWPlans/Sketch4
09/01/2026B00513276-I1Request digital key ↗
09/01/2026B00513580-P1Request digital key ↗
09/01/2026B00513580-I1Request digital key ↗
Showing 3 of 4 on file for this type
▸Seals & Professional Certifications24
▸DOB NOWProgress Inspector Seal & Signature12
08/31/2026B00513580-P1Open ↗
08/31/2026B00513580-P1Open ↗
08/27/2026B00513276-P1Open ↗
Showing 3 of 12 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature8
08/31/2026B00513580-P1Open ↗
08/31/2026B00513580-P1Open ↗
08/31/2026B00513580-P1Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature4
09/01/2026B00513276-P1Open ↗
09/01/2026B00513276-I1Open ↗
09/01/2026B00513580-I1Open ↗
Showing 3 of 4 on file for this type
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form2
09/01/2026B00513276-I1Open ↗
09/01/2026B00513580-I1Open ↗
▸Energy Compliance1
▸DOB NOWEN2: As Built Energy Analysis.1
09/01/2026B00513276-I1Open ↗