| Owner | Filings | Most Recent |
|---|---|---|
| MEMORIAL BAPTIST CHURCH | 8 | 07/08/2026 |
| HPD | 6 | 07/08/2026 |
| MARK CONTRACTING NY | 1 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| KEMS ENGINEERING AND CONSTRUCTION | 4 | 01/05/2026 |
| ENTHINK ENGINEERS LLC | 1 | 06/02/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| LEWSAN CONSULTANTS | 8 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| MARK CONTRACTING NY INC | General Contractor | 6 | 07/08/2026 |
| PETRI PBG & HTG INC | Plumbing | 2 | 07/08/2026 |
| RICHARD NEU | Electrical | 1 | 03/22/2026 |
| PETRI PLUMBING & HEATING | General Contractor | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| EC SPECIAL INSPECTIONS | 8355 | 4 | 01/05/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Signed-off | PETRI PLUMBING & HEATING | 10/06/2025 |
| DOB NOW | Boiler Equipment | Signed-off | PETRI PBG & HTG INC | 10/06/2025 |
| DOB NOW | Plumbing | Signed-off | PETRI PBG & HTG INC | 10/06/2025 |
| DOB NOW | Sidewalk Shed | Permit Issued | MARK CONTRACTING NY INC | 04/15/2024 |
| DOB NOW | Sidewalk Shed | Permit Issued | MARK CONTRACTING NY INC | 02/08/2024 |
| DOB NOW | Sidewalk Shed | Permit Issued | MARK CONTRACTING NY INC | 02/10/2023 |
| DOB NOW | Sidewalk Shed | Permit Issued | MARK CONTRACTING NY INC | 08/17/2021 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/10/2021 | Permit Issued | RICHARD NEU | — |
| 07/22/2019 | Complete | WILLDAN ELECTRICAL OF NY | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 01/20/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 01/07/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 01/07/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 12/09/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 11/25/2025 | Pass-Final Boiler Equipment Inspection | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 01/06/2026 | Fire-Resistant Penetrations and Joints | ABDALLAH ELCHERBINI | special |
| 12/11/2025 | Fire-Resistant Penetrations and Joints | ABDALLAH ELCHERBINI | special |
| 09/26/2025 | Heating Systems | ABDALLAH ELCHERBINI | special |
| 09/26/2025 | Fire-Resistant Penetrations and Joints | ABDALLAH ELCHERBINI | special |
| 09/26/2025 | Maintenance information | Steven Bendoraitis | energy_progress |
| 09/26/2025 | Fire-Resistant Penetrations and Joints | ABDALLAH ELCHERBINI | special |
| 09/25/2025 | HVAC-R and service water heating equipment | Steven Bendoraitis | energy_progress |
| 09/25/2025 | HVAC-R and service water piping design and insulation | Steven Bendoraitis | energy_progress |
| 09/25/2025 | HVAC-R and service water heating system controls | Steven Bendoraitis | energy_progress |
| 09/23/2025 | Final | Steven Bendoraitis | progress |