| Owner | Filings | Most Recent |
|---|---|---|
| 621 VANDERBILT LLC | 2 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 05/13/2024 | $2.6M | — | Private party → 621 VANDERBILT LLC | $650/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| RISE ARCHITECTURE | 3 | 10/09/2024 |
| RISE ARCHITECTURE NJ LLC | 2 | 06/24/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| JACK JAFFA & ASSOCIATES | 10 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| BEE CONSTRUCTIONS LLC | General Contractor | 5 | 07/08/2026 |
| WATSON'S PLBG, HTG, & BDG | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| BIZ DESIGNS LLC | 6312 | 5 | 10/09/2024 |
| AZ PROFESSIONAL ENGINEERI | 766 | 3 | 07/29/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Signed-off | BEE CONSTRUCTIONS LLC | 10/15/2024 |
| DOB NOW | Plumbing | Signed-off | WATSON'S PLBG, HTG, & BDG | 08/14/2024 |
| DOB NOW | General Construction | Signed-off | BEE CONSTRUCTIONS LLC | 06/05/2024 |
| DOB NOW | General Construction | Signed-off | BEE CONSTRUCTIONS LLC | 04/26/2024 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/22/2024 | Complete | CRESCO ELECTRICAL CORP | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 01/05/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 08/30/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 08/30/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 08/28/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/12/2024 | Fire-Resistant Penetrations and Joints | Jeff Akerman | special |
| 08/12/2024 | Structural Stability – Alterations of existing buildings | VIJAY KUMAR | special |
| 08/12/2024 | Final | SHIMON GREENEBAUM | progress |
| 08/12/2024 | Fire-Resistance Rated Construction | Jeff Akerman | progress |
| 08/12/2024 | Energy Code Compliance Inspections | Jeff Akerman | progress |
| 08/12/2024 | Lighting in dwelling units | Jeff Akerman | energy_progress |
| 08/12/2024 | Fenestration and door U-factor and product ratings | Jeff Akerman | energy_progress |
| 08/12/2024 | Air barrier - visual inspection | Jeff Akerman | energy_progress |
| 08/12/2024 | Lighting controls | Jeff Akerman | energy_progress |
| 08/12/2024 | Fenestration air leakage | Jeff Akerman | energy_progress |
| 08/12/2024 | Interior lighting power | Jeff Akerman | energy_progress |
| 08/12/2024 | Insulation placement and R values | Jeff Akerman | energy_progress |
| 07/29/2024 | Fire-Resistant Penetrations and Joints | Jeff Akerman | special |
| 07/29/2024 | Structural Stability – Alterations of existing buildings | VIJAY KUMAR | special |
| 07/29/2024 | Energy Code Compliance Inspections | Jeff Akerman | progress |
| 07/29/2024 | Final | SHIMON GREENEBAUM | progress |
| 07/29/2024 | Fire-Resistance Rated Construction | Jeff Akerman | progress |
| 07/29/2024 | Fenestration air leakage | Jeff Akerman | energy_progress |
| 07/29/2024 | Insulation placement and R values | Jeff Akerman | energy_progress |
| 07/29/2024 | Lighting in dwelling units | Jeff Akerman | energy_progress |
| 07/29/2024 | Fenestration and door U-factor and product ratings | Jeff Akerman | energy_progress |
| 07/29/2024 | Air barrier - visual inspection | Jeff Akerman | energy_progress |
| 07/29/2024 | Interior lighting power | Jeff Akerman | energy_progress |
| 07/29/2024 | Lighting controls | Jeff Akerman | energy_progress |
| 06/17/2024 | Fire-Resistant Penetrations and Joints | Jeff Akerman | special |