| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 12/29/2023 | — | — | Air Conditioning Systems, Heating Systems | Cooling Daikin RXS15LVJU 15,000 BTU · Heat Pump Outdoor ×6 RK09NMVJU 9,000 BTU · Heat Pump Outdoor ×2 RXS09LVJU 9,000 BTU · Heat Pump Outdoor ×1 RZQ30PVJU 30,000 BTU · Vrf Outdoor ×1 Heating Daikin RXS15LVJU 15,000 BTU · Heat Pump Outdoor ×6 RXS09LNJU 9,000 BTU · Heat Pump Outdoor ×1 RZQ30PVJU 34,000 BTU · Vrf Outdoor ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/29/2023 | — | — | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/02/2025 | Permit Issued | POWER DIRECT ELECTRIC INC | General Wiring |
| 12/02/2025 | Permit Issued | POWER DIRECT ELECTRIC INC | — |
| Owner | Filings | Most Recent |
|---|---|---|
| 819 MAZEL MIT BRUCHA LLC | 1 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| ADROIT ENGINEERING PLLC | 1 | 11/14/2024 |
| BAOBAB ARCHITECTS P.C. | 2 | 12/29/2023 |
| CHOSEN MEP, CORP. | 3 | 07/13/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| ELLIPSES DESIGN | 5 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| POWER DIRECT ELECTRIC INC | Electrical | 1 | 03/22/2026 |
| JSB WORKS INC | General Contractor | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| ADROIT ENGINEERING PLLC | 8885 | 1 | 11/14/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Full Demolition | Signed-off | JSB WORKS INC | 12/23/2024 |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 12/27/2023 | Air barrier - visual inspection | — | energy_progress |
| 12/27/2023 | HVAC-R and service water heating equipment | — | energy_progress |
| 12/27/2023 | Fenestration areas | — | energy_progress |
| 12/27/2023 | Electrical motors and elevators | — | energy_progress |
| 12/27/2023 | Concrete - Cast-In-Place | — | special |
| 12/27/2023 | Excavations - Sheeting, Shoring, and Bracing | — | special |
| 12/27/2023 | Masonry | — | special |
| 12/27/2023 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | — | special |
| 12/27/2023 | Structural Stability – Alterations of existing buildings | — | special |
| 12/27/2023 | Subsurface Investigations (Borings/Test Pits) | — | special |
| 12/27/2023 | Energy Code Compliance Inspections | — | progress |
| 12/27/2023 | Fire-Resistance Rated Construction | — | progress |
| 12/27/2023 | Lighting controls | — | energy_progress |
| 12/27/2023 | HVAC-R and service water heating system controls | — | energy_progress |
| 12/27/2023 | Maintenance information | — | energy_progress |
| 12/27/2023 | HVAC-R and service water piping design and insulation | — | energy_progress |
| 12/27/2023 | Metering | — | energy_progress |
| 12/27/2023 | Protection of exposed foundation insulation | — | energy_progress |
| 12/27/2023 | Air barrier — testing | — | energy_progress |
| 12/27/2023 | Fenestration air leakage | — | energy_progress |
| 12/27/2023 | Insulation placement and R values | — | energy_progress |
| 12/27/2023 | Vestibules | — | energy_progress |
| 12/27/2023 | Interior lighting power | — | energy_progress |
| 12/27/2023 | Lighting in dwelling units | — | energy_progress |
| 12/27/2023 | Exterior lighting power | — | energy_progress |