← Back
Four families
964 BEDFORD AVENUE
BROOKLYN · BIN 3055249
💬 Discuss this project
1905Year Built
3Stories
C3Building Class
R6BZoning
2,592 sfGross Floor Area
4Units
Rent Stabilized14 Open Violations ▸FDNY Report ↗
Four families · 2,150 sf lot · 1.21 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingGeneral
Permit Issued — active, not yet Signed-off
RoofUnder Construction30p · 1 filing · 20 docs
Floor 4Under Construction29p · 1 filing · 20 docs
Floor 3Under Construction28p · 1 filing · 20 docs
Floor 2Under Construction30p · 1 filing · 20 docs
Floor 1Under Construction29p · 1 filing · 20 docs
CellarUnder Construction30p · 1 filing · 20 docs
1 job · most recent 08/13/2026
Gas Storm Water/Sanitary
FiledStatusContractorScope
08/13/2026——Gas, Storm, Water/Sanitary
1 job · most recent 12/03/2025
General Wiring
FiledStatusContractorScope
12/03/2025Permit IssuedD & W ELECTRICAL CONT CORGeneral Wiring
1 job · most recent 08/13/2026
Steel
FiledStatusContractorScope
08/13/2026Permit IssuedLYNCH MANAGEMENT NY INCSteel
Building Lifecycle
All (122)Filed (8)Permit Issued (4)Violation (27)Objection (53)Special Inspection (30)
08/27/2026
Permit issued — Support of Excavation
B01348537-S3-SE
08/26/2026
Objection resolved — Resolved
08/26/2026
Objection resolved — Resolved
08/26/2026
Objection resolved — Resolved
08/25/2026
Objection raised — Other
08/25/2026
Objection raised — Other
08/25/2026
Objection raised — Other
08/14/2026
Permit issued — Structural
B01348537-S5-ST
08/13/2026
Filed — Alteration
Proposed horizontal extention for a 4-story + cellar residential building, converting from a 4 unit to a 2 unit.
B01348537-P1
08/13/2026
Objection resolved — Addressed
08/13/2026
Objection resolved — Addressed
08/12/2026
Special inspection requirement — Air barrier - visual inspection
Md Istiaque Hasan
08/12/2026
Special inspection requirement — Permanent certificate
Md Istiaque Hasan
08/12/2026
Special inspection requirement — Insulation placement and R values
Md Istiaque Hasan
08/12/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
Md Istiaque Hasan
08/12/2026
Special inspection requirement — Exterior Insulation and Finish Systems (EIFS)
Md Istiaque Hasan
08/12/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Md Istiaque Hasan
08/12/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
Md Istiaque Hasan
08/12/2026
Special inspection requirement — Energy Code Compliance Inspections
Md Istiaque Hasan
08/12/2026
Special inspection requirement — Final
Md Istiaque Hasan
08/12/2026
Special inspection requirement — Fire-Resistance Rated Construction
Md Istiaque Hasan
08/12/2026
Special inspection requirement — Interior lighting power
Md Istiaque Hasan
08/12/2026
Special inspection requirement — Metering
Md Istiaque Hasan
08/12/2026
Special inspection requirement — Maintenance information
Md Istiaque Hasan
08/12/2026
Special inspection requirement — Fenestration areas
Md Istiaque Hasan
08/12/2026
Special inspection requirement — Fenestration air leakage
Md Istiaque Hasan
08/11/2026
Objection raised — Other
08/11/2026
Objection raised — Other
08/03/2026
Objection resolved — Resolved
07/29/2026
Objection resolved — Addressed
07/22/2026
Filed — Alteration
Proposed horizontal extention for a 4-story + cellar residential building, converting from a 4 unit to a 2 unit.
B01348537-S6
07/15/2026
Objection raised — Cost
07/08/2026
Filed — Alteration
Proposed horizontal extention for a 4-story + cellar residential building, converting from a 4 unit to a 2 unit.
B01348537-S5
07/06/2026
Objection resolved — Resolved
06/12/2026
Objection raised — Other
06/07/2026
Objection raised — Other
06/05/2026
Filed — Alteration
Proposed horizontal extention for a 4-story + cellar residential building, converting from a 4 unit to a 2 unit.
B01348537-S4
06/05/2026
Permit issued — General Construction
B01348537-I1-GC
06/05/2026
Permit issued — Mechanical Systems
B01348537-S2-MS
06/03/2026
Filed — Alteration
Proposed horizontal extention for a 4-story + cellar residential building, converting from a 4 unit to a 2 unit.
B01348537-S3
06/02/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
06/02/2026
Special inspection requirement — Excavations - Sheeting, Shoring, and Bracing
Md Istiaque Hasan
06/02/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
Md Istiaque Hasan
06/02/2026
Special inspection requirement — Structural Steel - Details
Md Istiaque Hasan
06/02/2026
Special inspection requirement — Subsurface Investigations (Borings/Test Pits)
FERAS AYOUB
06/02/2026
Special inspection requirement — Subsurface Investigations (Borings/Test Pits)
06/02/2026
Special inspection requirement — Concrete - Cast-In-Place
05/28/2026
Special inspection requirement — Footing and Foundation
05/28/2026
Special inspection requirement — Final
05/06/2026
Filed — Alteration
Proposed horizontal extention for a 4-story + cellar residential building, converting from a 4 unit to a 2 unit.
B01348537-S2
05/05/2026
Filed — Alteration
Proposed horizontal extention for a 4-story + cellar residential building, converting from a 4 unit to a 2 unit.
B01348537-S1
05/04/2026
Special inspection requirement — Final
Md Istiaque Hasan
05/04/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Md Istiaque Hasan
05/04/2026
Special inspection requirement — Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation
Md Istiaque Hasan
05/04/2026
Special inspection requirement — Maintenance information
Md Istiaque Hasan
05/04/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
Md Istiaque Hasan
05/04/2026
Special inspection requirement — HVAC-R and service water heating equipment
Md Istiaque Hasan
05/01/2026
Violation issued (HPD, open)
A
03/26/2026
Objection resolved — Addressed
03/25/2026
Objection resolved — Addressed
Latest 60 of 122 events.
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
EI HOLDINGS NY1009/13/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
02/24/2026$2.2M—— → 964 BED LLC$849/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
BORIS BALKHIYEV, PE408/13/2026
AVISHAY I. MAZOR, P.E.407/22/2026
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
ADVANCED BUILDERS SERVICES103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
LYNCH MANAGEMENT NYGeneral Contractor408/30/2026
D & W ELECTRICAL CONT CORElectrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
RI CONSULTING SERVICES IN8904608/13/2026
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSupport of ExcavationPermit IssuedLYNCH MANAGEMENT NY INC08/27/2026
DOB NOWStructuralPermit IssuedLYNCH MANAGEMENT NY INC08/14/2026
DOB NOWGeneral ConstructionPermit IssuedLYNCH MANAGEMENT NY INC06/05/2026
DOB NOWMechanical SystemsPermit IssuedLYNCH MANAGEMENT NY INC06/05/2026
BISPLISSUEDPROGRAM UNLIMITED PLG & HTG04/24/1996
BISPLISSUEDF.D. GOODRICH PLG & HTG10/21/1993
▾Special Inspection Requirements (DOB NOW) — 49
DateRequirementInspectorRole
08/12/2026Air barrier - visual inspectionMd Istiaque Hasanenergy_progress
08/12/2026Permanent certificateMd Istiaque Hasanenergy_progress
08/12/2026Insulation placement and R valuesMd Istiaque Hasanenergy_progress
08/12/2026Fenestration and door U-factor and product ratingsMd Istiaque Hasanenergy_progress
08/12/2026Exterior Insulation and Finish Systems (EIFS)Md Istiaque Hasanspecial
08/12/2026Fire-Resistant Penetrations and JointsMd Istiaque Hasanspecial
08/12/2026Structural Stability – Alterations of existing buildingsMd Istiaque Hasanspecial
08/12/2026Energy Code Compliance InspectionsMd Istiaque Hasanprogress
08/12/2026FinalMd Istiaque Hasanprogress
08/12/2026Fire-Resistance Rated ConstructionMd Istiaque Hasanprogress
08/12/2026Interior lighting powerMd Istiaque Hasanenergy_progress
08/12/2026MeteringMd Istiaque Hasanenergy_progress
08/12/2026Maintenance informationMd Istiaque Hasanenergy_progress
08/12/2026Fenestration areasMd Istiaque Hasanenergy_progress
08/12/2026Fenestration air leakageMd Istiaque Hasanenergy_progress
06/02/2026Structural Stability – Alterations of existing buildings—special
06/02/2026Excavations - Sheeting, Shoring, and BracingMd Istiaque Hasanspecial
06/02/2026Structural Stability – Alterations of existing buildingsMd Istiaque Hasanspecial
06/02/2026Structural Steel - DetailsMd Istiaque Hasanspecial
06/02/2026Subsurface Investigations (Borings/Test Pits)FERAS AYOUBspecial
06/02/2026Subsurface Investigations (Borings/Test Pits)—special
06/02/2026Concrete - Cast-In-Place—special
05/28/2026Footing and Foundation—progress
05/28/2026Final—progress
05/04/2026FinalMd Istiaque Hasanprogress
Latest 25 of 49.
▾Documents — 92 on file (BIS + DOB NOW)
▸Plans & Drawings8
▸DOB NOWPlans/Sketch8
08/16/2026B01348537-S4Request digital key ↗
08/16/2026B01348537-S2Request digital key ↗
08/16/2026B01348537-S1Request digital key ↗
Showing 3 of 8 on file for this type
▸Zoning, Tax Lot & Property Records2
▸DOB NOWZD1: DOB Zoning Diagram2
08/16/2026B01348537-P1Open ↗
08/13/2026B01348537-I1Open ↗
▸Seals & Professional Certifications52
▸DOB NOWProgress Inspector Seal & Signature29
09/18/2026B01348537-I1Open ↗
09/18/2026B01348537-I1Open ↗
09/18/2026B01348537-I1Open ↗
Showing 3 of 29 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature15
09/18/2026B01348537-I1Open ↗
09/18/2026B01348537-I1Open ↗
09/18/2026B01348537-I1Open ↗
Showing 3 of 15 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature8
08/16/2026B01348537-P1Open ↗
08/16/2026B01348537-S6Open ↗
08/16/2026B01348537-S5Open ↗
Showing 3 of 8 on file for this type
▸Safety & Tenant Protection8
▸DOB NOWHPD-3: Single Room Occupancy Multiple Dwelling (SRO MD) Anti-Harassment Checklist8
08/16/2026B01348537-S2Open ↗
08/16/2026B01348537-S1Open ↗
08/16/2026B01348537-P1Open ↗
Showing 3 of 8 on file for this type
▸Environmental & Asbestos8
▸DOB NOWDEP ACP-5: Asbestos Assessment Report8
08/16/2026B01348537-P1Open ↗
08/16/2026B01348537-S2Open ↗
08/16/2026B01348537-S1Open ↗
Showing 3 of 8 on file for this type
▸Inspections & Test Reports4
▸DOB NOWTR4 Test Report and Plot Diagram2
08/16/2026B01348537-S4Open ↗
08/15/2026B01348537-S3Open ↗
▸DOB NOWSOIL REPORT2
08/15/2026B01348537-S3Open ↗
08/14/2026B01348537-S4Open ↗
▸Other Documents10
▸DOB NOWPlot Diagram5
08/16/2026B01348537-P1Open ↗
08/15/2026B01348537-S3Open ↗
08/15/2026B01348537-S6Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone3
08/16/2026B01348537-P1Open ↗
08/16/2026B01348537-I1Open ↗
08/13/2026B01348537-I1Open ↗
▸DOB NOWSite Survey: Initial2
08/16/2026B01348537-P1Open ↗
08/13/2026B01348537-I1Open ↗