| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/15/2026 | Permit Issued | BRIDGE ZALE CONSTRUCT COR | Ventilation Systems |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/15/2026 | Permit Issued | NEW YORK PARK PLBG&HTG CO | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/01/2026 | Permit Issued | JOSEPH WEINSTEIN ELECTRIC | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/15/2026 | Permit Issued | NEW YORK PARK PLBG&HTG CO | Tenant Protection Plan 72 Hour |
| Owner | Filings | Most Recent |
|---|---|---|
| BRIDGE ZALE CONSTRUCTION CORP. | 16 | 07/08/2026 |
| 499 GRAHAM AVE, LLC | 2 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 12/20/2024 | $1.1M | — | — → — | $279/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| HAMANN ENGINEERING, PLLC | 6 | 07/15/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| BRIDGE ZALE CONSTRUCT COR | General Contractor | 3 | 07/08/2026 |
| NEW YORK PARK PLBG&HTG CO | Plumbing | 2 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| HAMANN ENGINEERING, PLLC | 4949 | 6 | 07/15/2026 |
| STRUCT. ENGINEERING INTEG | 4174 | 1 | 02/09/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | NEW YORK PARK PLBG&HTG CO | 06/24/2026 |
| DOB NOW | General Construction | Permit Issued | BRIDGE ZALE CONSTRUCT COR | 06/04/2026 |
| DOB NOW | General Construction | Permit Issued | BRIDGE ZALE CONSTRUCT COR | 02/19/2026 |
| DOB NOW | Boiler Equipment | Permit Issued | NEW YORK PARK PLBG&HTG CO | 10/07/2025 |
| DOB NOW | General Construction | Permit Issued | BRIDGE ZALE CONSTRUCT COR | 07/30/2025 |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/19/2026 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 08/13/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 08/10/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 07/09/2026 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 07/08/2026 | Certified Storm Drainage-ST-Fixtures-Finish | Certified | View ↗ |
| 06/30/2026 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 04/17/2026 | Air barrier - visual inspection | CARL HAMANN | energy_progress |
| 04/17/2026 | Permanent certificate | CARL HAMANN | energy_progress |
| 04/17/2026 | Interior lighting power | CARL HAMANN | energy_progress |
| 03/12/2026 | Structural Stability – Alterations of existing buildings | Chris Yiu | special |
| 02/06/2026 | Tenant Protection Plan Compliance | CARL HAMANN | special |
| 01/15/2026 | Fenestration areas | CARL HAMANN | energy_progress |
| 01/15/2026 | Fire-Resistance Rated Construction | CARL HAMANN | progress |
| 01/15/2026 | Fenestration and door U-factor and product ratings | CARL HAMANN | energy_progress |
| 01/15/2026 | Fire-Resistant Penetrations and Joints | CARL HAMANN | special |
| 01/15/2026 | Concrete - Cast-In-Place | CARL HAMANN | special |
| 01/15/2026 | Fenestration air leakage | CARL HAMANN | energy_progress |
| 04/23/2025 | Maintenance information | CARL HAMANN | energy_progress |
| 04/23/2025 | Fire-Resistant Penetrations and Joints | CARL HAMANN | special |
| 04/23/2025 | Heating Systems | CARL HAMANN | special |
| 04/23/2025 | HVAC-R and service water heating system controls | CARL HAMANN | energy_progress |
| 04/23/2025 | HVAC-R and service water piping design and insulation | CARL HAMANN | energy_progress |
| 04/23/2025 | HVAC-R and service water heating equipment | CARL HAMANN | energy_progress |
| 04/04/2025 | Tenant Protection Plan Compliance | CARL HAMANN | special |