| Owner | Filings | Most Recent |
|---|---|---|
| AMERSON PARTNERS | 15 | 07/08/2026 |
| 323 GRAHAM OWNER LLC | 1 | 03/22/2026 |
| CARMINE N STELLA/OR OWNER | 5 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 06/01/2022 | $2.1M | — | Private party → 323 GRAHAM OWNER LLC | $896/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| CARUSONE & CHERRES ARCHITECTS, LLC | 2 | 03/06/2026 |
| ZENITH HOME INSPECTIONS | 1 | 12/05/2024 |
| AMERILAND BROOK LLC | 3 | 08/18/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| JP EXPEDITE | 2 | 03/21/2026 |
| AB WORKS PROCESSING | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| SPLEN CONSTRUCTION INC | General Contractor | 3 | 03/21/2026 |
| TOWER CREATIONS CORP | General Contractor | 3 | 03/21/2026 |
| KLE CONSTRUCTION INC | General Contractor | 1 | 07/08/2026 |
| WATSON'S PLBG, HTG, & BDG | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| BEYOND ARCH LLC | 3600 | 1 | 12/05/2024 |
| AMERILAND BROOK LLC | 1506 | 3 | 08/18/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Signed-off | TOWER CREATIONS CORP | 12/30/2024 |
| DOB NOW | General Construction | Signed-off | KLE CONSTRUCTION INC | 06/15/2023 |
| DOB NOW | Plumbing | Signed-off | WATSON'S PLBG, HTG, & BDG | 06/29/2022 |
| DOB NOW | Mechanical Systems | Signed-off | SPLEN CONSTRUCTION INC | 06/03/2022 |
| BIS | — | ISSUED | NEW YORK MID RISE CONSTRU | 11/10/2010 |
| BIS | PL | ISSUED | MAGOR PLUMBING & HEATING | 01/08/1999 |
| BIS | OT | ISSUED | TARRY CHANE D/B/A & PAINTING CO | 12/22/1998 |
| BIS | OT | ISSUED | ARDOYNE CONSTRUCTION CORP. | 05/04/1992 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/18/2022 | Complete | DKNJ ELECTRIC LLC | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/06/2026 | — | — | 1 scope_items |
| 03/13/2025 | — | — | Steel, Concrete |
| Date | Type | Result | Report |
|---|---|---|---|
| 11/22/2023 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 03/08/2023 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 03/01/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 02/28/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 08/24/2022 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 08/24/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/06/2026 | Fire-Resistance Rated Construction | — | progress |
| 03/06/2026 | Energy Code Compliance Inspections | — | progress |
| 03/06/2026 | Tenant Protection Plan Compliance | — | special |
| 03/06/2026 | Structural Stability – Alterations of existing buildings | — | special |
| 01/02/2026 | Final | — | progress |
| 08/19/2022 | HVAC-R and service water piping design and insulation | XIAOHONG ZHAO | energy_progress |
| 08/19/2022 | Fire-Resistant Penetrations and Joints | XIAOHONG ZHAO | special |
| 08/19/2022 | Energy Code Compliance Inspections | XIAOHONG ZHAO | progress |
| 08/19/2022 | HVAC-R and service water heating equipment | XIAOHONG ZHAO | energy_progress |
| 08/19/2022 | HVAC-R and service water heating system controls | XIAOHONG ZHAO | energy_progress |
| 08/18/2022 | Fire-Resistant Penetrations and Joints | XIAOHONG ZHAO | special |
| 08/18/2022 | HVAC-R and service water heating system controls | XIAOHONG ZHAO | energy_progress |
| 08/18/2022 | HVAC-R and service water piping design and insulation | XIAOHONG ZHAO | energy_progress |
| 08/18/2022 | HVAC-R and service water heating equipment | XIAOHONG ZHAO | energy_progress |
| 08/18/2022 | Energy Code Compliance Inspections | XIAOHONG ZHAO | progress |