General warehouse
8 REWE STREET
BROOKLYN · BIN 3070496
💬 Discuss this project
1957Year Built
1Stories
E1Building Class
M3-1Zoning
49,275 sfGross Floor Area
1Units
12 Open Violations ▸FDNY Report ↗
General warehouse · Owner of record: 8 REWE STREET LLC · 84,371 sf lot · 0.58 FAR built · Flood zone X500
Locations of Work
No floor-level scope or drawing coverage on file for this building.
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
8 REWE STREET703/22/2026
ADLER/THOMPSON CORP103/22/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
TAN ARCHITECT P.C110/27/2025
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
DAVIS JR, TOMMIEElectrical103/21/2026
ROOPCHAND SINGHElectrical103/21/2026
STRIANO, JOSEPHElectrical103/21/2026
JJK BUILDING CONSULTINGGeneral Contractor104/09/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Z & T ENGINEERING, P.C.591110/27/2025
Building Lifecycle
All (27)Filed (1)Permit Issued (1)Signed Off (1)Violation (18)Inspection (1)Special Inspection (5)
04/17/2026
Signed off — Alteration
PROPOSED INSTALLATION OF TWO OVERSIZED SERVICE DOORS FOR AN EXISTING WAREHOUSE.
B01305377-I1
04/02/2026
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
12/19/2025
Permit issued — General Construction
B01305377-I1-GC
11/14/2025
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
10/27/2025
Filed — Alteration
PROPOSED INSTALLATION OF TWO OVERSIZED SERVICE DOORS FOR AN EXISTING WAREHOUSE.
B01305377-I1
10/20/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
Fei Zeng
10/20/2025
Special inspection requirement — Air barrier - visual inspection
Fei Zeng
10/20/2025
Special inspection requirement — Fenestration areas
Fei Zeng
10/20/2025
Special inspection requirement — Fenestration air leakage
Fei Zeng
10/20/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
Fei Zeng
06/30/2023
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
06/30/2023
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
06/20/2023
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
06/20/2023
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
04/25/2023
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
08/23/2021
Violation issued (FDNY_ORDER, closed)
04/29/2021
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
04/06/2018
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
02/24/2017
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
10/01/2015
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
03/03/2015
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
05/15/2014
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
03/01/2013
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
12/31/2009
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
01/06/2006
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
12/20/1999
Violation issued (ECB, closed)
Boilers
08/28/1992
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionSigned-offJJK BUILDING CONSULTING12/19/2025
BISOTISSUEDNATIONAL GRID ENERGY MANA04/11/2014
BISSPISSUEDUNITED FIRE PROTECTION CRP01/03/2006
BISOTISSUEDSRC CONTRUCTION CORP04/07/1995
BISMHISSUEDMIDCOUNTY MECHANICAL CORP.09/16/1992
Nothing on file for this building.
▾Field Inspections (DOB CAP) — 1
DateTypeResultReport
04/02/2026Pass-Final General Construction Non-Directive 14PassView ↗
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
10/20/2025Structural Stability – Alterations of existing buildingsFei Zengspecial
10/20/2025Air barrier - visual inspectionFei Zengenergy_progress
10/20/2025Fenestration areasFei Zengenergy_progress
10/20/2025Fenestration air leakageFei Zengenergy_progress
10/20/2025Fenestration and door U-factor and product ratingsFei Zengenergy_progress
▾Documents — 29 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/20/2026B01305377-I1Request digital key ↗
▸Applications & Permits2
▸BISPLAN / WORK APPROVAL APPLICATION1
04/01/2014340128739Open ↗
▸BISWORK PERMIT APPLICATION1
04/11/2014340128739Open ↗
▸Seals & Professional Certifications5
▸BISTECHNICAL REPORT: RESPONSIBILITY-CERTIFICATION1
04/01/2014340128739Open ↗
▸BISApplicant / Owner Signature1
04/01/2014340128739Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/13/2026B01305377-I1Open ↗
▸DOB NOWProgress Inspector Seal & Signature1
08/29/2026B01305377-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
08/29/2026B01305377-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/13/2026B01305377-I1Open ↗
▸Energy Compliance7
▸BISSOLAR TAX ABATEMENT APPLICATION3
05/20/2015340128739Open ↗
05/20/2015340128739Open ↗
01/12/2015340128739Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
01/12/2015340128739Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY1
01/12/2015340128739Open ↗
▸BISSOLAR TAX ABATEMENT APPLICATION (PTA4)1
04/01/2014340128739Open ↗
▸BISTR8: Energy Code Progress Inspections1
04/01/2014340128739Open ↗
▸Inspections & Test Reports3
▸BISTECHNICAL REPORT: RESPONSIBILITY3
05/20/2015340128739Open ↗
05/20/2015340128739Open ↗
01/12/2015340128739Open ↗
▸Approvals, Objections & Sign-offs4
▸BISLETTERS - SUPPORTING DOCUMENTATION2
05/05/2015340128739Open ↗
01/12/2015340128739Open ↗
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
01/12/2015340128739Open ↗
▸BISUtility Company PV System Interconnection Acknowledgement Letter1
01/12/2015340128739Open ↗
▸Cost, Insurance & Ownership2
▸BISCOST AFFIDAVIT2
01/12/2015340128739Open ↗
04/01/2014340128739Open ↗
▸Filing & Intake Forms4
▸BISADDITIONAL INFORMATION3
05/20/2015340128739Open ↗
05/20/2015340128739Open ↗
01/06/2015340128739Open ↗
▸BISEFILING JOB APPLICATION COVER SHEET1
04/01/2014340128739Open ↗