← Back
Two family frame
358 MENAHAN STREET
BROOKLYN · BIN 3075993
💬 Discuss this project
1930Year Built
2Stories
B2Building Class
R6Zoning
1,360 sfGross Floor Area
2Units
14 Open Violations 10 unresolved · 4 paperwork only ▸FDNY Report ↗
Two family frame · Owner of record: AEM MENAHAN LLC · 2,000 sf lot · 0.68 FAR built · Flood zone X
Locations of Work
ArchitectureCivil
Roof1p · 1 filing · 5 docs
Floor 11p · 1 filing · 5 docs
Cellar2p · 1 filing · 5 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
358 MENAHAN STREET LLC.203/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
05/24/2022$800K—358 MENAHAN STREET, LLC → AEM MENAHAN LLC$588/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
CARUSONE & CHERRES ARCHITECTS, LLC105/12/2026
STROH ENGINEERING SERVICES, P.C.203/03/2026
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
EXPEDITE DEM403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
UNITED INDUSTRIES & CONSTGeneral Contractor207/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
STROH ENGINEERING SERVICE3316111/07/2025
Building Lifecycle
All (67)Filed (3)Permit Issued (2)Signed Off (1)Violation (16)Objection (24)Special Inspection (21)
08/11/2026
Special inspection requirement — Lighting controls
08/11/2026
Special inspection requirement — Exterior lighting power
08/11/2026
Special inspection requirement — Metering
08/11/2026
Special inspection requirement — Electrical motors and elevators
08/06/2026
Objection resolved — Resolved
08/06/2026
Objection resolved — Open
08/03/2026
Objection raised — Scope
08/03/2026
Objection raised — Energy
07/17/2026
Objection resolved — Resolved
07/17/2026
Objection resolved — Resolved
07/17/2026
Objection resolved — Addressed
07/17/2026
Objection resolved — Addressed
07/17/2026
Objection resolved — Resolved
07/17/2026
Objection resolved — Open
07/01/2026
Objection raised — Zoning
07/01/2026
Objection raised — Scope
07/01/2026
Objection raised — Admin
06/24/2026
Objection raised — Admin
06/02/2026
Signed off — Full Demolition
full demolition of two story structure, using hand held equipment.
B01307933-I1
06/02/2026
Objection resolved — Addressed
06/02/2026
Objection resolved — Addressed
06/01/2026
Objection resolved — Addressed
05/29/2026
Objection raised — Other
05/29/2026
Objection raised — Scope
05/29/2026
Objection raised — Fire_Protection
05/29/2026
Objection raised — Other
05/29/2026
Objection raised — Fire_Protection
05/12/2026
Filed — New Building
PROPOSED 4 STORY NEW BUILDING WITH 4 DWELLING UNITS AS PER PLANS
B01381488-I1
04/03/2026
Special inspection requirement — Insulation placement and R values
04/01/2026
Special inspection requirement — Energy Code Compliance Inspections
04/01/2026
Special inspection requirement — Fire-Resistance Rated Construction
04/01/2026
Special inspection requirement — Preliminary
04/01/2026
Special inspection requirement — Lighting in dwelling units
04/01/2026
Special inspection requirement — Maintenance information
04/01/2026
Special inspection requirement — Air barrier - visual inspection
04/01/2026
Special inspection requirement — Fenestration air leakage
04/01/2026
Special inspection requirement — Fenestration areas
04/01/2026
Special inspection requirement — Interior lighting power
04/01/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
04/01/2026
Special inspection requirement — Air barrier — testing
04/01/2026
Special inspection requirement — Concrete - Cast-In-Place
04/01/2026
Special inspection requirement — Concrete - Precast
04/01/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
04/01/2026
Special inspection requirement — Masonry
03/12/2026
Permit issued — Full Demolition
B01307933-I1-FD
03/10/2026
Permit issued — Construction Fence
B01307933-S1-FN
03/03/2026
Filed — Full Demolition
full demolition of two story structure, using hand held equipment.
B01307933-S1
02/24/2026
Objection resolved — Addressed
12/10/2025
Objection raised — Admin
11/07/2025
Filed — Full Demolition
full demolition of two story structure, using hand held equipment.
B01307933-I1
10/31/2025
Special inspection requirement — Structural Stability – Alterations of existing Buildings
PETER STROH
08/06/2012
Violation issued (ECB, open)
Construction
08/06/2012
Violation issued (ECB, closed)
Construction
09/14/2007
Violation issued (ECB, closed)
Unknown
04/19/2007
Violation issued (ECB, open)
Unknown
12/18/2006
Violation issued (ECB, open)
Quality of Life
12/18/2006
Violation issued (ECB, open)
Construction
12/12/2006
Violation issued (HPD, open)
B
12/09/2006
Violation issued (HPD, open)
B
11/30/2006
Violation issued (HPD, open)
B
Latest 60 of 67 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWFull DemolitionSigned-offUNITED INDUSTRIES & CONST03/12/2026
DOB NOWConstruction FenceSigned-offUNITED INDUSTRIES & CONST03/10/2026
1 project · most recent 05/12/2026
Storm Water/Sanitary
FiledStatusContractorScope
05/12/2026——Storm, Water/Sanitary
1 project · most recent 03/03/2026
Fence
FiledStatusContractorScope
03/03/2026Signed-offUNITED INDUSTRIES & CONSTFence
▾Special Inspection Requirements (DOB NOW) — 21
DateRequirementInspectorRole
08/11/2026Lighting controls—energy_progress
08/11/2026Exterior lighting power—energy_progress
08/11/2026Metering—energy_progress
08/11/2026Electrical motors and elevators—energy_progress
04/03/2026Insulation placement and R values—energy_progress
04/01/2026Energy Code Compliance Inspections—progress
04/01/2026Fire-Resistance Rated Construction—progress
04/01/2026Preliminary—progress
04/01/2026Lighting in dwelling units—energy_progress
04/01/2026Maintenance information—energy_progress
04/01/2026Air barrier - visual inspection—energy_progress
04/01/2026Fenestration air leakage—energy_progress
04/01/2026Fenestration areas—energy_progress
04/01/2026Interior lighting power—energy_progress
04/01/2026Fenestration and door U-factor and product ratings—energy_progress
04/01/2026Air barrier — testing —energy_progress
04/01/2026Concrete - Cast-In-Place—special
04/01/2026Concrete - Precast—special
04/01/2026Fire-Resistant Penetrations and Joints—special
04/01/2026Masonry—special
10/31/2025Structural Stability – Alterations of existing BuildingsPETER STROHspecial
▾Documents — 22 on file (BIS + DOB NOW)
▸Plans & Drawings4
▸DOB NOWPlans/Sketch4
08/18/2026B01307933-S1Request digital key ↗
08/17/2026B01381488-S1Request digital key ↗
08/14/2026B01381488-I1Request digital key ↗
Showing 3 of 4 on file for this type
▸Zoning, Tax Lot & Property Records1
▸DOB NOWZD1: DOB Zoning Diagram1
08/14/2026B01381488-I1Open ↗
▸Seals & Professional Certifications5
▸DOB NOWDPL-1: Design Professional Seal & Signature4
08/18/2026B01307933-I1Open ↗
08/18/2026B01307933-S1Open ↗
08/17/2026B01381488-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature1
08/25/2026B01307933-I1Open ↗
▸Trade Schedules & Equipment4
▸DOB NOWSewer Cut-Off1
08/14/2026B01307933-I1Open ↗
▸DOB NOWElectric Cut-Off1
08/14/2026B01307933-I1Open ↗
▸DOB NOWWater Cut-Off1
08/14/2026B01307933-I1Open ↗
▸DOB NOWGas Cut-Off1
08/14/2026B01307933-I1Open ↗
▸Safety & Tenant Protection1
▸DOB NOWStreet Tree Checklist1
08/14/2026B01381488-I1Open ↗
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/14/2026B01307933-I1Open ↗
▸DOB NOWRodent Control1
08/14/2026B01307933-I1Open ↗
▸Other Documents5
▸DOB NOWCommunity Board Notification1
08/14/2026B01307933-I1Open ↗
▸DOB NOWProperty Ownership Certification1
08/14/2026B01307933-I1Open ↗
▸DOB NOWFull Demo: 10-Day Notice1
08/14/2026B01307933-I1Open ↗
▸DOB NOWStructure Photographs1
08/14/2026B01307933-I1Open ↗
▸DOB NOWSite Survey: Initial1
08/14/2026B01381488-I1Open ↗