| Firm | Filings | Most Recent |
|---|---|---|
| CQ&J CORPORATION | 1 | 07/30/2026 |
| THOMAS C. TUNG, P.E. | 3 | 07/27/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| HOLNESS, GEORGE | Electrical | 2 | 03/21/2026 |
| TRANSCANADA | Electrical | 2 | 03/21/2026 |
| WILFRED JEFFREY | Electrical | 1 | 03/21/2026 |
| GLOBAL TEAM NY INC | General Contractor | 1 | 09/03/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| SIMON | 7555 | 1 | 04/01/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Construction Fence | Permit Issued | GLOBAL TEAM NY INC | 09/02/2026 |
| BIS | — | ISSUED | EDWARD'S CONSTRUCTION OF NY CORP | 02/19/2008 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/18/2024 | Permit Issued | BDS ELECTRIC CORP. | General Wiring, Lighting |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/27/2026 | — | — | 2 scope_items |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/30/2026 | Permit Issued | GLOBAL TEAM NY INC | Fence |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 04/22/2026 | Concrete - Cast-In-Place | — | special |
| 04/22/2026 | Subgrade Inspections | — | special |
| 04/20/2026 | Final | — | progress |
| 04/20/2026 | Footing and Foundation | — | progress |
| 03/02/2026 | Fenestration air leakage | THOMAS TUNG | energy_progress |
| 03/02/2026 | Lighting in dwelling units | THOMAS TUNG | energy_progress |
| 03/02/2026 | Fenestration and door U-factor and product ratings | THOMAS TUNG | energy_progress |
| 03/02/2026 | Insulation placement and R values | THOMAS TUNG | energy_progress |
| 03/02/2026 | Fire-Resistant Penetrations and Joints | SIMON JIANG | special |
| 03/02/2026 | Metering | THOMAS TUNG | energy_progress |
| 03/02/2026 | Air barrier - visual inspection | THOMAS TUNG | energy_progress |
| 03/02/2026 | Permanent certificate | THOMAS TUNG | energy_progress |
| 03/02/2026 | Maintenance information | THOMAS TUNG | energy_progress |
| 03/02/2026 | Energy Code Compliance Inspections | THOMAS TUNG | progress |
| 03/02/2026 | Fenestration areas | THOMAS TUNG | energy_progress |
| 03/02/2026 | Air barrier — testing | THOMAS TUNG | energy_progress |