1930Year Built
2Stories
M9Building Class
R6Zoning
16,000 sfGross Floor Area
1Units
2 Open Violations ▸FDNY Report ↗
Miscellaneous religious facility · 8,000 sf lot · 2 FAR built · Flood zone X
Locations of Work
StructuralMechanical
Roof2p · 1 filing · 7 docs
Floor 23p · 2 filings · 12 docs
Floor 12p · 1 filing · 7 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
AMERICA COME BACK TO GOD EVANGELIST1107/08/2026
RELIABLE ENTERPRISES407/08/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
BAZINI ENGINEERING, P.C.204/03/2025
Z & T ENGINEERING, P.C.203/25/2024
MJE PROFESSIONAL SERVICES109/28/2023
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
NULITE FUEL OIL CO., LTDGeneral Contractor707/08/2026
ZHONGSHUN JIANZHU INCGeneral Contractor303/21/2026
ALL WAYS ELECTRIC CORP.WElectrical103/22/2026
RELIABLE ENTERPRISES INCGeneral Contractor107/08/2026
VEZANDIO CONTRACTING CORPGeneral Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
BAZINI ENGINEERING, P.C.1808204/03/2025
Z & T ENGINEERING, P.C.591203/25/2024
Building Lifecycle
All (28)Filed (5)Permit Issued (7)Signed Off (3)Violation (6)Special Inspection (7)
06/16/2025
Violation issued (FDNY_ORDER, closed)
04/30/2025
Signed off — Alteration
INSTALL NINE (9) SPLIT AC SYSTEMS AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
B00945207-I1
04/04/2025
Special inspection requirement — Mechanical Systems
Joseph Bazini
04/04/2025
Special inspection requirement — Final
Joseph Bazini
04/03/2025
Filed — Alteration
INSTALL NINE (9) SPLIT AC SYSTEMS AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
B00945207-P1
12/13/2024
Permit issued — Mechanical Systems
B00945207-I1-MS
12/13/2024
Permit issued — General Construction
B00945207-I1-GC
06/21/2024
Signed off — Alteration
Proposed to repair the damaged/charred wood joist due to fire at the first floor ceiling and install stairs at the 2nd floor exit door passage way to building set-back roof. The filing is also addressed the ECB violation 39098605Y. There is no change occu
B00966934-I1
06/21/2024
Signed off — Alteration
INSTALLATION OF STEEL BEAMS AND POST FOR AIR CONDITIONER CONDENSER BRACKET ON EXISTING BUILDING
B00944741-S2
05/01/2024
Permit issued — Structural
B00944741-S2-ST
03/29/2024
Special inspection requirement — Final
Joseph Bazini
03/29/2024
Special inspection requirement — Mechanical Systems
Joseph Bazini
03/25/2024
Filed — Alteration
INSTALLATION OF STEEL BEAMS AND POST FOR AIR CONDITIONER CONDENSER BRACKET ON EXISTING BUILDING
B00944741-S2
01/16/2024
Permit issued — General Construction
B00945207-I1-GC
01/12/2024
Permit issued — Mechanical Systems
B00945207-I1-MS
12/27/2023
Permit issued — General Construction
B00966934-I1-GC
11/29/2023
Filed — Alteration
Proposed to repair the damaged/charred wood joist due to fire at the first floor ceiling and install stairs at the 2nd floor exit door passage way to building set-back roof. The filing is also addressed the ECB violation 39098605Y. There is no change occu
B00966934-I1
11/22/2023
Special inspection requirement — Final
Fei Zeng
11/22/2023
Special inspection requirement — Structural Stability – Alterations of existing buildings
Fei Zeng
11/22/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
Fei Zeng
11/03/2023
Filed — Alteration
INSTALL NINE (9) SPLIT AC SYSTEMS AS PER PLANS. NO CHANGE IN USE, EGRESS OR OCCUPANCY.
B00945207-I1
11/02/2023
Violation issued (ECB, closed)
Construction
11/02/2023
Violation issued (ECB, closed)
Construction
11/02/2023
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
11/02/2023
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
09/28/2023
Filed — Alteration
PROPOSED INSTALLATION OF HEAVY DUTY SIDEWALK SHED AS PER PLANS. LIVE LOAD 300 LBS PER SQUARE FEET. SIDEWALK SHED SHALL COMPLY WITH CHAPTER #33 OF THE NYC BUILDING CODE. NO CHANGE IN USE, OCCUPANCY, OR EGRESS UNDER THIS APPLICATION.
B00940175-I1
09/28/2023
Permit issued — Sidewalk Shed
B00940175-I1-SH
07/07/2021
Violation issued (ECB, closed)
Boilers
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsSigned-offNULITE FUEL OIL CO., LTD12/13/2024
DOB NOWGeneral ConstructionSigned-offNULITE FUEL OIL CO., LTD12/13/2024
DOB NOWStructuralSigned-offVEZANDIO CONTRACTING CORP05/01/2024
DOB NOWGeneral ConstructionSigned-offNULITE FUEL OIL CO., LTD01/16/2024
DOB NOWMechanical SystemsSigned-offNULITE FUEL OIL CO., LTD01/12/2024
DOB NOWGeneral ConstructionSigned-offZHONGSHUN JIANZHU INC12/27/2023
DOB NOWSidewalk ShedPermit IssuedRELIABLE ENTERPRISES INC09/28/2023
BIS—ISSUEDLOWE CONSTRUCTION CO07/22/1994
4 projects · most recent 03/30/2026
General Wiring
FiledStatusContractorScope
03/30/2026Permit IssuedBREEZY ELECTRICAL CORPGeneral Wiring
11/15/2023Permit IssuedGMJ ELECTRIC CORPGeneral Wiring
11/14/2023Permit IssuedALL WAYS ELECTRIC CORP.W—
09/28/2023Permit IssuedRICHARD NEU—
1 project · most recent 03/25/2024
Steel
FiledStatusContractorScope
03/25/2024Signed-offVEZANDIO CONTRACTING CORPSteel
1 project · most recent 09/28/2023
Sidewalk Shed
FiledStatusContractorScope
09/28/2023Permit IssuedRELIABLE ENTERPRISES INCSidewalk Shed
▾Special Inspection Requirements (DOB NOW) — 7
DateRequirementInspectorRole
04/04/2025Mechanical SystemsJoseph Bazinispecial
04/04/2025FinalJoseph Baziniprogress
03/29/2024FinalJoseph Baziniprogress
03/29/2024Mechanical SystemsJoseph Bazinispecial
11/22/2023FinalFei Zengprogress
11/22/2023Structural Stability – Alterations of existing buildingsFei Zengspecial
11/22/2023Fire-Resistant Penetrations and JointsFei Zengspecial
▾Documents — 20 on file (BIS + DOB NOW)
▸Plans & Drawings4
▸DOB NOWPlans/Sketch4
08/26/2026B00940175-I1Request digital key ↗
08/26/2026B00966934-I1Request digital key ↗
08/25/2026B00944741-S2Request digital key ↗
Showing 3 of 4 on file for this type
▸Seals & Professional Certifications12
▸DOB NOWDPL-1: Design Professional Seal & Signature4
08/26/2026B00940175-I1Open ↗
08/26/2026B00966934-I1Open ↗
08/13/2026B00944741-S2Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWProgress Inspector Seal & Signature4
09/02/2026B00945207-P1Open ↗
09/01/2026B00945207-I1Open ↗
09/01/2026B00966934-I1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
09/02/2026B00945207-P1Open ↗
09/01/2026B00945207-I1Open ↗
09/01/2026B00966934-I1Open ↗
Showing 3 of 4 on file for this type
▸Approvals, Objections & Sign-offs2
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter2
08/13/2026B00966934-I1Open ↗
08/13/2026B00944741-S2Open ↗
▸Other Documents2
▸DOB NOWFee Exempt Supporting Document - DOF Property Tax Assessment Roll2
08/13/2026B00945207-I1Open ↗
08/13/2026B00945207-P1Open ↗