← Back
Two family frame
33 HALE AVENUE
BROOKLYN · BIN 3086779
💬 Discuss this project
2021Year Built
2Stories
B2Building Class
R4Zoning
2,226 sfGross Floor Area
2Units
1 Open Violation 0 unresolved · 1 paperwork only ▸FDNY Report ↗
Two family frame · Owner of record: 33 HALE AVENUE OWNER LLC · 2,656 sf lot · 0.84 FAR built · Flood zone X
Locations of Work
ArchitectureStructural
Floor 11p · 1 filing · 2 docs
Cellar1p · 1 filing · 2 docs
1 job · most recent 10/03/2025
General Wiring
FiledStatusContractorScope
10/03/2025CompleteBLZ ELECTRIC INC.General Wiring
Building Lifecycle
All (52)Filed (7)Permit Issued (7)Signed Off (5)Violation (26)Inspection (3)Objection (4)
08/24/2026
Signed off — Alteration
B00227639-I1
06/30/2026
Signed off — Alteration
B00512671-I1
04/02/2026
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
03/30/2026
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
08/06/2025
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
08/05/2025
Permit issued — Sprinklers
B00227639-I1-EW-SP
07/02/2025
Signed off — Alteration
TEMPORARY CONSTRUCTION FENCE IN CONJUNCTION WITH NEW BUILDING APP # 321938052
B00234466-I1
06/20/2025
Signed off — Alteration
B01112348-I1
06/11/2025
Signed off — Alteration
Install shoring from cellar floor to 2nd floor and demolish exposure 4 walls from 1st floor to 2nd floor up to roof.
B01095249-I1
01/10/2025
Permit issued — Structural
B01112348-I1-ST
01/10/2025
Violation issued (ECB, closed)
Construction
01/09/2025
Permit issued — Protection and Mechanical Methods
B01095249-I1-PMM
12/12/2024
Permit issued — Construction Fence
B00234466-I1-FN
11/03/2024
Objection resolved — Addressed
10/02/2024
Filed — Alteration
TEMPORARY CONSTRUCTION FENCE IN CONJUNCTION WITH NEW BUILDING APP # 321938052
B00234466-P1
09/18/2024
Filed — Alteration
B01112348-I1
09/17/2024
Objection resolved — Addressed
08/23/2024
Objection raised — Other
08/23/2024
Objection raised — Other
08/16/2024
Filed — Alteration
Install shoring from cellar floor to 2nd floor and demolish exposure 4 walls from 1st floor to 2nd floor up to roof.
B01095249-I1
05/30/2023
Violation issued (ECB, closed)
Construction
05/30/2023
Violation issued (ECB, closed)
Construction
10/21/2021
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
10/21/2021
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
08/18/2021
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
08/18/2021
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
08/18/2021
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
05/20/2021
Violation issued (ECB, closed)
Construction
05/20/2021
Violation issued (ECB, closed)
Construction
05/20/2021
Violation issued (ECB, open)
Construction
05/11/2021
Violation issued (ECB, closed)
Construction
04/30/2021
Permit issued — Curb Cut
B00512671-I1-CC
04/29/2021
Filed — Alteration
B00512671-I1
03/08/2021
Permit issued — Construction Fence
B00234466-I1-FN
12/30/2020
Filed — Alteration
B00445622-I1
08/12/2020
Filed — Alteration
B00227639-I1
06/15/2020
Violation issued (ECB, closed)
Construction
06/15/2020
Violation issued (ECB, closed)
Construction
04/24/2020
Violation issued (ECB, closed)
Unknown
04/23/2020
Violation issued (ECB, closed)
Construction
04/23/2020
Violation issued (ECB, closed)
Unknown
04/02/2020
Violation issued (ECB, closed)
Construction
01/28/2020
Violation issued (ECB, closed)
Construction
11/14/2019
Permit issued — Construction Fence
B00234466-I1-FN
10/09/2019
Filed — Alteration
TEMPORARY CONSTRUCTION FENCE IN CONJUNCTION WITH NEW BUILDING APP # 321938052
B00234466-I1
04/26/2017
Violation issued (HPD, closed)
C
01/15/2014
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
08/06/2012
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
08/01/2012
Violation issued (ECB, closed)
Construction
07/04/2012
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
07/24/2003
Violation issued (ECB, closed)
Construction
07/09/2003
Violation issued (ECB, closed)
Construction
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
CORP YAFE MEOD103/22/2026
KAIETEUR CONSTRUCTION903/22/2026
QUEENSWAY BUILDERS203/22/2026
RAIETUER CONSTR INC103/22/2026
KAIETUER CONSTR INC103/22/2026
HOUSING PRES DEV203/21/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
01/14/2020$475K—— → —— not available
11/21/2017$175K—— → —— not available
07/21/2017$159K—— → —— not available
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
BORIS BALKHIYEV, PE410/02/2024
RI CONSULTING SERVICES INC209/18/2024
TABRIZ DESIGN GROUP112/30/2020
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
TABRIZ DESIGN GROUP403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
YAFE MEOD CORPGeneral Contractor507/08/2026
KAIETEUR CONSTRUCTION INC.General Contractor407/08/2026
AL PLUMBING & CONT. INCPlumbing403/22/2026
AMERICAN STANDARD PLUMBINPlumbing203/22/2026
BLZ ELECTRIC INC 001756General Contractor203/22/2026
PAUL LEFKOWITZElectrical103/21/2026
AMERICAN STANDARD PLUMBING &Fire Protection107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
RI CONSULTING SERVICES IN8904108/12/2020
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSprinklersSigned-offAMERICAN STANDARD PLUMBIN08/05/2025
DOB NOWStructuralSigned-offYAFE MEOD CORP01/10/2025
DOB NOWProtection and Mechanical MethodsSigned-offYAFE MEOD CORP01/09/2025
DOB NOWConstruction FenceSigned-offYAFE MEOD CORP12/12/2024
DOB NOWCurb CutSigned-offKAIETEUR CONSTRUCTION INC04/30/2021
DOB NOWConstruction FenceSigned-offKAIETEUR CONSTRUCTION INC03/08/2021
DOB NOWConstruction FenceSigned-offKAIETEUR CONSTRUCTION INC11/14/2019
BISPLISSUEDAL PLUMBING & CONT. INC03/28/2025
BIS—ISSUEDYAFE MEOD CORP09/10/2024
BIS—ISSUEDYAFE MEOD CORP08/15/2024
BIS—ISSUEDKAIETEUR CONSTRUCTION INC.04/01/2021
BISPLISSUEDWATERMARK PLUMBING CORP09/10/2020
BIS—ISSUEDKAIETEUR CONSTRUCTION INC.07/01/2020
BIS—ISSUEDKAIETEUR CONSTRUCTION INC.12/06/2019
BIS—ISSUEDKAIETEUR CONSTRUCTION INC.12/06/2019
BIS—ISSUEDA.RUSSO WRECKING INC11/29/2012
BISEQISSUEDA.RUSSO WRECKING INC11/29/2012
▾Field Inspections (DOB CAP) — 3
DateTypeResultReport
04/02/2026Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
03/30/2026Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
08/06/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
▾Documents — 104 on file (BIS + DOB NOW)
▸Plans & Drawings7
▸DOB NOWPlans/Sketch3
09/01/2026B00512671-I1Request digital key ↗
08/24/2026B01095249-I1Request digital key ↗
08/24/2026B01112348-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Construction Fence2
09/02/2026B00234466-I1Request digital key ↗
09/02/2026B00234466-P1Request digital key ↗
▸DOB NOWPlans/Sketch - Sprinkler1
09/02/2026B00227639-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Plumbing1
09/02/2026B00445622-I1Request digital key ↗
▸Applications & Permits30
▸BISWORK PERMIT APPLICATION16
03/31/2025321938052Open ↗
03/31/2025321938052Open ↗
09/10/2024321938052Open ↗
Showing 3 of 16 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION12
08/12/2025321938052Open ↗
04/22/2025321938052Open ↗
10/08/2024321938052Open ↗
Showing 3 of 12 on file for this type
▸BISBPP-5 - Authorization to the Department of Transportation1
07/09/2019321990173Open ↗
▸BISCERTIFICATE OF OCCUPANCY: APPLICATION1
12/12/2025321938052Open ↗
▸Zoning, Tax Lot & Property Records7
▸BISZONING EXHIBIT III:DESC. & OWNRSHP.STMNT2
07/16/2019321938052Open ↗
03/28/2019321938052Open ↗
▸BISZONING EXHIBIT I: CERTIFICATION2
07/16/2019321938052Open ↗
03/28/2019321938052Open ↗
▸BISADDRESS: NEW HOUSE NUMBER APPROVED1
07/29/2019321938052Open ↗
▸BISCO OBJ: VERIFY ADDRESS-TOPO STAMP1
06/16/2025321938052Open ↗
▸BISZONING DIAGRAM1
09/30/2019321938052Open ↗
▸Seals & Professional Certifications12
▸DOB NOWDPL-1: Design Professional Seal & Signature7
09/02/2026B00445622-I1Open ↗
09/01/2026B00512671-I1Open ↗
08/24/2026B01095249-I1Open ↗
Showing 3 of 7 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION5
12/11/2019321938052Open ↗
07/29/2019321938052Open ↗
07/29/2019321938052Open ↗
Showing 3 of 5 on file for this type
▸Trade Schedules & Equipment3
▸BISSCHEDULE B - PLUMBING2
08/12/2025321938052Open ↗
04/22/2025321938052Open ↗
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE1
03/28/2019321938052Open ↗
▸Safety & Tenant Protection4
▸BISSTREET TREE CHECKLIST3
12/11/2019321938052Open ↗
05/16/2019321990173Open ↗
05/15/2019321938052Open ↗
▸BISSRO MD ANTI-HARASSMENT CHECKLIST1
12/07/2012320583196Open ↗
▸Environmental & Asbestos2
▸BISDEP ASBESTOS PROJECT COMPLETION FORM1
12/07/2012320583196Open ↗
▸BISASBESTOS: COMPLETION OR CLOSEOUT (ACP 20-21-5)1
12/07/2012320583196Open ↗
▸Energy Compliance2
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS2
07/29/2019321938052Open ↗
03/28/2019321938052Open ↗
▸Inspections & Test Reports5
▸BISSOIL REPORT2
07/29/2019321938052Open ↗
03/28/2019321938052Open ↗
▸BISTECHNICAL REPORT: CONCRETE DESIGN MIX1
12/11/2019321938052Open ↗
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER1
12/11/2019321938052Open ↗
▸BISHYDRAULIC FLOW CALCULATIONS1
07/16/2019321938052Open ↗
▸Approvals, Objections & Sign-offs14
▸BISLETTERS - SUPPORTING DOCUMENTATION6
03/31/2025321938052Open ↗
12/07/2012320583196Open ↗
12/07/2012320583196Open ↗
Showing 3 of 6 on file for this type
▸BISSUPERSEDING LETTER5
09/10/2024321938052Open ↗
08/26/2024321938052Open ↗
08/26/2024321938052Open ↗
Showing 3 of 5 on file for this type
▸BISSCHEDULE A - OCCUPANCY / USE1
03/28/2019321938052Open ↗
▸BISADMINISTRATIVE OBJECTIONS1
09/13/2012320583196Open ↗
▸BISUtility Company PV System Interconnection Acknowledgement Letter1
12/07/2012320583196Open ↗
▸Cost, Insurance & Ownership6
▸BISPROJECT-SPECIFIC GL INSURANCE6
09/10/2024321938052Open ↗
09/10/2024321938052Open ↗
08/26/2024321938052Open ↗
Showing 3 of 6 on file for this type
▸Filing & Intake Forms7
▸BISADDITIONAL INFORMATION4
04/08/2021321938052Open ↗
09/18/2019321938052Open ↗
05/24/2019321938052Open ↗
Showing 3 of 4 on file for this type
▸BISEFILING COVER SHEET3
05/16/2019321990173Open ↗
03/28/2019321938052Open ↗
09/13/2012320583196Open ↗
▸Other Documents5
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION2
12/12/2012320583196Open ↗
12/12/2012320583196Open ↗
▸BISPLOT DIAGRAM1
07/29/2019321938052Open ↗
▸DOB NOWPARTIAL DEMO: 10-DAY Notice1
08/13/2026B01112348-I1Open ↗
▸DOB NOWWaiver Document1
08/13/2026B00512671-I1Open ↗