Locations of Work
ArchitectureStructuralMechanicalPlumbing
Roof5p · 1 filing · 13 docs
Cellar6p · 1 filing · 13 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
HKS CONSTRUCTION607/08/2026
CYPRESS HOMES HDFC403/21/2026
PITKIN-BERRIMAN HDFC403/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
LORING CONSULTING ENGINEERS, INC.202/18/2025
OLD STRUCTURES ENGINEERING112/03/2024
ESKW/A111/06/2024
HAIDER ENGINEERING, P.E.101/03/2019
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
HAIDER ENGINEERING, P.E.103/21/2026
BETRO DESIGN GROUP403/21/2026
HAIDER ENGINEERING P E103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
HKS CONSTRUCTION CORPGeneral Contractor407/08/2026
ROOPCHAND SINGHElectrical103/21/2026
Building Lifecycle
All (100)Filed (5)Permit Issued (2)Violation (44)Objection (22)Special Inspection (27)
01/13/2026
Objection resolved — Resolved
11/14/2025
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
10/28/2025
Objection resolved — Addressed
09/24/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
09/11/2025
Objection resolved — Addressed
08/15/2025
Objection resolved — Resolved
08/15/2025
Objection resolved — Resolved
08/15/2025
Objection resolved — Resolved
08/14/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
08/14/2025
Special inspection requirement — HVAC-R and service water heating system controls
08/14/2025
Special inspection requirement — Energy Code Compliance Inspections
05/19/2025
Violation issued (HPD, closed)
B
05/19/2025
Violation issued (HPD, closed)
B
05/09/2025
Violation issued (HPD, open)
C
04/18/2025
Objection raised — Admin
04/07/2025
Objection resolved — Addressed
03/20/2025
Special inspection requirement — Post-installed Anchors
02/20/2025
Objection raised — Plumbing
02/20/2025
Objection raised — Plumbing
02/20/2025
Objection raised — Plumbing
02/18/2025
Filed — Alteration
Roofing replacement, window & doors replacements, partial roof/cellar joist repairs, Demo/removals, Sitework, facade & masonry repairs as per plans filed.
B01135206-S2
02/05/2025
Objection raised — Fire_Protection
02/03/2025
Filed — Alteration
Roofing replacement, window & doors replacements, partial roof/cellar joist repairs, Demo/removals, Sitework, facade & masonry repairs as per plans filed.
B01135206-S3
01/16/2025
Objection raised — Structural
01/08/2025
Objection resolved — Addressed
12/17/2024
Special inspection requirement — HVAC-R and service water heating equipment
12/17/2024
Special inspection requirement — HVAC-R and service water piping design and insulation
12/17/2024
Special inspection requirement — HVAC-R and service water heating system controls
12/17/2024
Special inspection requirement — Maintenance information
12/17/2024
Special inspection requirement — Shutoff dampers
12/17/2024
Special inspection requirement — Heating Systems
12/17/2024
Special inspection requirement — Tenant Protection Plan Compliance
12/17/2024
Special inspection requirement — Mechanical Systems
12/17/2024
Special inspection requirement — Energy Code Compliance Inspections
12/17/2024
Special inspection requirement — Final
12/17/2024
Special inspection requirement — Tenant Protection Plan Compliance
12/12/2024
Objection resolved — Addressed
12/06/2024
Objection raised — Admin
12/06/2024
Objection raised — Structural
12/06/2024
Objection raised — Admin
12/03/2024
Filed — Alteration
Roofing replacement, window & doors replacements, partial roof/cellar joist repairs, Demo/removals, Sitework, facade & masonry repairs as per plans filed.
B01135206-S1
11/22/2024
Objection resolved — Addressed
11/11/2024
Special inspection requirement — Final
11/11/2024
Special inspection requirement — Tenant Protection Plan Compliance
11/11/2024
Special inspection requirement — Masonry
11/07/2024
Objection raised — Admin
11/07/2024
Objection raised — Scope
11/07/2024
Objection raised — Scope
11/06/2024
Filed — Alteration
Roofing replacement, window & doors replacements, partial roof/cellar joist repairs, Demo/removals, Sitework, facade & masonry repairs as per plans filed.
B01135206-I1
10/30/2024
Special inspection requirement — Lighting controls
10/30/2024
Special inspection requirement — Fenestration air leakage
10/30/2024
Special inspection requirement — Insulation placement and R values
10/30/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
10/30/2024
Special inspection requirement — Energy Code Compliance Inspections
10/30/2024
Special inspection requirement — Tenant Protection Plan Compliance
10/30/2024
Special inspection requirement — Final
10/30/2024
Special inspection requirement — Fenestration and door U-factor and product ratings
09/23/2024
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
10/19/2023
Violation issued (FDNY_NOV, closed)
06/30/2023
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
Latest 60 of 100 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSidewalk ShedPermit IssuedHKS CONSTRUCTION CORP03/20/2019
DOB NOWSidewalk ShedPermit IssuedHKS CONSTRUCTION CORP01/03/2019
BISMHISSUEDCENTRAL DEVELOPMENT CORP03/13/2009
BISPLISSUEDMONARCH MECHANICAL INC.10/05/1999
BISOTISSUEDP& P CONTRACTING CORP06/01/1999
BISOTISSUEDLOVELY CONSTRUCTION CORP03/03/1998
BISOTISSUEDBIN CONSTRUCTION INC03/12/1996
1 project · most recent 02/18/2025
Gas Water/Sanitary
FiledStatusContractorScope
02/18/2025——Gas, Water/Sanitary
2 projects · most recent 10/21/2019
FiledStatusContractorScope
10/21/2019Permit IssuedWCK ELECTRIC CORP.—
12/06/2018Permit IssuedRICHARD NEU—
1 project · most recent 02/18/2025
Concrete Masonry
FiledStatusContractorScope
02/18/2025——Concrete, Masonry
▾Special Inspection Requirements (DOB NOW) — 27
DateRequirementInspectorRole
09/24/2025Structural Stability – Alterations of existing buildings—special
08/14/2025HVAC-R and service water piping design and insulation—energy_progress
08/14/2025HVAC-R and service water heating system controls—energy_progress
08/14/2025Energy Code Compliance Inspections—progress
03/20/2025Post-installed Anchors—special
12/17/2024HVAC-R and service water heating equipment—energy_progress
12/17/2024HVAC-R and service water piping design and insulation—energy_progress
12/17/2024HVAC-R and service water heating system controls—energy_progress
12/17/2024Maintenance information—energy_progress
12/17/2024Shutoff dampers—energy_progress
12/17/2024Heating Systems—special
12/17/2024Tenant Protection Plan Compliance—special
12/17/2024Mechanical Systems—special
12/17/2024Energy Code Compliance Inspections—progress
12/17/2024Final—progress
12/17/2024Tenant Protection Plan Compliance—special
11/11/2024Final—progress
11/11/2024Tenant Protection Plan Compliance—special
11/11/2024Masonry—special
10/30/2024Lighting controls—energy_progress
10/30/2024Fenestration air leakage—energy_progress
10/30/2024Insulation placement and R values—energy_progress
10/30/2024Fire-Resistant Penetrations and Joints—special
10/30/2024Energy Code Compliance Inspections—progress
10/30/2024Tenant Protection Plan Compliance—special
Latest 25 of 27.
▾Documents — 30 on file (BIS + DOB NOW)
▸Plans & Drawings5
▸DOB NOWPlans/Sketch4
08/23/2026B01135206-S3Request digital key ↗
08/23/2026B01135206-S2Request digital key ↗
08/23/2026B01135206-S1Request digital key ↗
Showing 3 of 4 on file for this type
▸DOB NOWPlans/Sketch - Sidewalk Shed1
09/02/2026B00115044-I1Request digital key ↗
▸Applications & Permits2
▸BISPLAN / WORK APPROVAL APPLICATION1
03/11/2009310300359Open ↗
▸BISWORK PERMIT APPLICATION1
03/13/2009310300359Open ↗
▸Seals & Professional Certifications9
▸DOB NOWDPL-1: Design Professional Seal & Signature5
09/02/2026B00115044-I1Open ↗
08/23/2026B01135206-S2Open ↗
08/23/2026B01135206-S1Open ↗
Showing 3 of 5 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION2
03/26/2009310300359Open ↗
03/11/2009310300359Open ↗
▸BISPROFESSIONAL CERTIFIED CHECKLIST1
03/11/2009310300359Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM1
03/11/2009310300359Open ↗
▸Trade Schedules & Equipment1
▸BISEQUIPMENT USE APPLICATION/PERMIT1
03/27/2009310300359Open ↗
▸Environmental & Asbestos5
▸DOB NOWDEP ACP-5: Asbestos Assessment Report4
08/23/2026B01135206-S3Open ↗
08/23/2026B01135206-S2Open ↗
08/23/2026B01135206-S1Open ↗
Showing 3 of 4 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'1
03/11/2009310300359Open ↗
▸Approvals, Objections & Sign-offs3
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
03/26/2009310300359Open ↗
▸BISADMINISTRATIVE OBJECTIONS1
03/11/2009310300359Open ↗
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter1
08/13/2026B01135206-S1Open ↗
▸Cost, Insurance & Ownership2
▸BISCOST AFFIDAVIT2
03/26/2009310300359Open ↗
03/11/2009310300359Open ↗
▸Filing & Intake Forms1
▸BISEFILING COVER SHEET1
03/11/2009310300359Open ↗
▸Other Documents2
▸DOB NOWBSA Meeting Minutes/BSA Resolution1
08/13/2026B00115044-I1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone1
08/13/2026B01135206-I1Open ↗